Professional Documents
Culture Documents
1
Who Are We?
2
Our Assets
~460 Km of
transmission
pipeline
Gas storage field
Pipeline
Supplies
3
Why LNG?
Dubai Electricity Load Growth
jan-01 jan-02 jan-03 jan-04 jan-05 jan-06 jan-07 jan-08 jan-09 jan-10
Quick to implement
Waterfront access is at a premium
Lower life cycle cost than conventional terminal for short
operational period of 10-15 years
New application but based on existing technologies
5
Project Background:
Marine facilities
Shell contracted for concept selection and the initial design
Halcrow performed detailed engineering
Archirodon Construction (Overseas) Company constructed the marine facilities
Breakwater, Jetty and sub-sea pipeline construction October 6th 2010
FSRU
Golar was contracted to deliver the FSRU and to undertake the detailed design
through Moss Maritime, based on DNV Regas notation.
Conversion at Keppel Shipyard Singapore completed in April 2010
Commissioning at the jetty and first gas October 30th 2010
Shell performed overall technical and safety assurance on the whole project on
behalf of DUSUP
6
FSRU – Golar Freeze
8
Process Overview
Auxiliaries MSO
(Fuel) COMPRESOR
REGASIFICATION
SKIDS
SUCTION
2 METERING
DRUM
Vapor
LNG
3
9
Regasification Skids
LNG GAS
LNG/Propane Ex
HP Pumps
Trim Heaters
Propane Drum
Propane
Pump
SW/Propane Ex
10
Regas Skids
Skid’s Outlet
Trim Heater
HP Pumps LNG/Prop. Ex
& Propane
drum
SW/Propane Ex
11
Forward Machinery Space
Vaporizers
Turbo Generators
5.5 MW each
Condensers
12
Terminal Layout Design
13
Jetty & Mooring Dolphins
Gas Arms to
FSRU
Mooring
Dolphins
Isolation Valve
• 16 inch
• 2 Liquid
• 1 Vapor
• QC/DC
• PERC
• ESD 1
• ESD 2
15
LNGC - Terminal Interface
Integrated controls between Jetty & Speed of approach monitoring & vessel
FSRU, so systems operate as one unit. movement recording during approach &
berthing
QR hooks on jetty and FSRU allow
release of LNGC (FSRU permanently
moored)
Operations similar to berthing at a
Mooring load monitoring information to shore based terminal
LNGC via fiber optic
16
Commissioning & Startup
• Challenges:
• Safety & Environmental considerations
• Geographic locations
• Solutions:
• Close coordination of interfaces during design & construction
• Enforcing cleanliness, tightness & Integrity protocols
• Rethinking typical terminal commissioning sequences/timings
• Segregation of commissioning activities to reduce
interdependencies
17
Questions?
Author: Co-Author:
Abdi Nayak Maaike van der Werf
Assets Manager –LNG Senior Process Engineer LNG & Gas Processing
Dubai Supply Authority Shell Global Solutions International BV
Mobile: +971 50 628 1054 Mobile: +31 6 5236 0374
abdi.nayak@dusup.ae M.vanderwerf@shell.com
18