You are on page 1of 4

peter evans partnership 27 July 2015

Practice Note 1: Rider 1 to the SCL


Delay and Disruption Protocol has just
been published, so what’s new?
Paul Thornton, our head of Forensic Delay and Programme Analysis,
reviews the main changes and comments upon the likely impact on
Engineers and Contractors.

“The Protocol recommends that, in deciding


Background
entitlement to EOT, the adjudicator, judge or
On 16 October 2002, the Society of Construction arbitrator should, so far as is practicable, put him/
Law published its Delay and Disruption Protocol herself in the position of the CA at the time the
(the “Old Protocol”), introduced as: “a scheme for Employer Risk Event occurred.”
dealing with delay and disruption issues that is
This Core Principle, more than any other,
balanced and viable”. Although it has been
suggested that Time Impact Analysis (“TIA”) was
regularly cited in Contractors’ claims in the
the best method to retrospectively analyse delay
Middle East, a rising tide of practitioners have
to a project. There is little doubt that TIA is a
objected to, as one stated, the:
preferred method to prospectively claim an EOT
“inappropriately strong endorsement of the time during the works, but Core Principle 12 of the
impact analysis method of delay analysis within New Protocol suggests:
the post contract dispute environment”.
“...[after the event] the parties have knowledge of
Following discussion at a Society of Construction the facts which superseded the delay event
Law’s 10-year anniversary event in London in (rather than these being forecast, which is the
April 2013, it was agreed that a revised edition basis of a time impact analysis) and these facts
would be required. Consequently, a Committee should be factored into the delay analysis to
has just released, a few days ago, what is dubbed
arrive at conclusions which are consistent with the
the Rider 1 to the SCL Delay and Disruption
way in which the Project in fact progressed.”
Protocol, or “New Protocol”.
This crystallises the Committee’s preference for
The Committee’s Objectives using fact-based approaches to measure the
impact of delay retrospectively. The Committee
The main objective of the New Protocol is to have felt it necessary to add elsewhere that a
downgrade the importance of Time Impact “common sense approach” should be adopted.
Analysis in favour of other fact-based methods in
assessing an Extension of Time (“EOT”) retro- New Definitions proposed
spectively. The Committee has therefore sought
to make changes to the Core Principles and Whilst the use of common sense was obviously
introduce methods, that were not originally implied in the Old Protocol, the new wording
included, to retrospectively analyse the delay. perhaps recognises the fact that the application
of TIA has sometimes been the cause of over-
Core Principle 12 of the Old Protocol recomm-
confidence by claimants, resulting in unsus-
ended how to deal with an EOT assessment after
tainable claims being put forward. The New
the event, namely:
Protocol therefore goes some way to helping

© Peter Evans FZ LLC Page 1


! www.peterevans.ae
peter evans partnership 27 July 2015

practitioners understand what “common sense” By defining how each method determines the
1is, by defining some commonly used terms. critical path and impact of delay, there is now
good guidance about each method. Perhaps
Firstly, the New Protocol defines the mechanics of practitioners’ discord against the Old Protocol
how an analysis may take place. Methods either developed because poor choice of methodology
identify and describe an event and then establish led to unfavourable results in proceedings.
its impact (“Cause and Effect”) or identify the
critical path and establish what might have Six methods replace four
caused the delay (“Effect and Cause”). The Cause
and Effect methods align with the Old Protocol’s The Old Protocol suggested four methods to
Core Principle 12 and the Effect and Cause analyse delay, which strongly favoured TIA above
methods strongly align with the newly drafted the other methods. It placed limitations on each
Core Principle 12. of the other methods, for example:

Secondly, the New Protocol defines three ways to • The Impacted As-planned …”is restricted
determine the critical path: due to the theoretical nature of the projected
delays”
“Purely prospective critical path assessments
adopt the perspective at the outset of the project • The As-Planned v As-Built … “is useful as a
only and take no account of progress achieved.” starting point in relation to other, more
complex methods of analysis”
“Contemporaneous critical path assessments
adopt an evolving perspective over the course of • The Collapsed As-Built … “is restricted by
the works and take account of the effect that both its inability to identify concurrency, re-
historical progress and changes in the strategy for sequencing, redistribution of resources or
the future prosecution of the works have on acceleration.”
predicted criticality.”
Whereas the Old Protocol at 4.8, elevates TIA as
“Retrospective critical path assessments adopt the best method for retrospective analysis:
the perspective evident at the end of the project
(or window of time).” “the amount of EOT may not precisely reflect the
actual delay suffered by the Contractor. That does
Whilst the retrospective assessment definition is not mean that time impact analysis generates
entirely new, the contemporaneous assessment is hypothetical results – it generates results showing
effectively used to separate TIA from retro- entitlement”
spective methods. Thirdly, the New Protocol
defines two methods to determine the impacts of The New Protocol, however, suggests six
delays: methods; The ‘As-Planned v As-Built’ method has
been redefined as ‘As-Planned v As-Built
“The prospective delay analysis identifies the Windows Analysis’, and there are now two
likely impact of historical progress or delay events additional methods: ‘Time Slice Windows
on the completion milestones.” Analysis’ and the ‘Longest Path’. The table below
puts these methods in the context of the
“A retrospective delay analysis identifies the
definitions already discussed.
actual impact of the delay events on the
identified actual or as-built critical path.”

1 The principle of common sense is considered by the UK courts as a foundation to the law of causation. Lord
Osborne in City Inn Ltd v. Shepherd Construction Ltd [2010] BLR 473, Para 42 provides an apt quote: “the decision
as to whether the relevant event possesses such causative effect is an issue of fact which is to be resolved, not by the
application of philosophical principles of causation, but rather by the application of principles of common-sense.”

© Peter Evans FZ LLC Page 2


! www.peterevans.ae
peter evans partnership 27 July 2015

It is interesting to note that the three new The New Protocol elevates, from the Guidance
methods put forward are “Effect and Cause” Section to a Core Principle, the need to deal with
methods that strongly align to the newly drafted delay events as soon as possible and, as per the
Core Principle 12. In my experience, using these Old Protocol, cautions against using the “Wait
methods allows practitioners to focus the delay and see approach”. The New Protocol at 3.2.4,
analysis and avoid superfluous analysis of delay suggests assessment of EOTs ought to be
events that are not necessarily linked to the contemporaneous:
actual critical delays experienced on the project.
“the CA [Contract Administrator] will award only
the minimum EOT that can be justified at the
The Effect on Contractors and time.” [emphasis added as wording has changed]
Engineers
This effectively advocates an iterative approach
The New Protocol will have quite profound for the Engineer to award EOTs.
consequences. It is currently common to all the
It would appear that this was a hotly debated
major standard forms of contract, that any interim
subject, given that one of the committee
EOT cannot be reduced in his final award. As the
members stated in a paper, following the 10th
Protocol at 3.2.4 states:
anniversary meeting:
“it is difficult if not impossible to withdraw an
EOT once granted”. “In revising the protocol, ... the first thing I would
change; i.e. if a prospective “impact assessment”
The Engineer therefore faces difficulty if it is not carried out contemporaneously, then one
transpires that an interim EOT award is signif- should lose the right to apply it after the fact.
icantly more than the finally provable delay, Certain popular contracts would benefit from a
which is entirely plausible given that prospective similar adjustment.”2
analysis can produce an unrealistic picture of the
impacts of delay. Whilst this could incentivise the Contractor to
submit EOT claims prospectively it would do little
In practice, particularly in the Middle East, an to motivate an Engineer to agree an EOT.
Engineer receiving an EOT claim will often tend Perhaps, the wider problem of the standard
to veer on the side of caution when awarding an forms of contract including FIDIC, is that
interim EOT or, indeed, not make an assessment Engineers are powerless to adjust, specifically
at all if he can avoid doing so. reduce, EOTs as new facts become apparent.

Determination of the Delay Impact

Prospectively Retrospectively

Impacted As-Planned
Prospectively
Analysis

As-Planned v As-Built
Contemporaneously Time Impact Analysis
Determination of Windows Analysis*
the Critical Path
Collapsed As-Built
Time Slice Windows Analysis
Retrospectively
Analysis*
Longest Path*

*The three new “Effect & Cause” methods put forward in the New Protocol

2 29 Const. L.J., Issue 5 (2013) “The SCL Delay and Disruption Protocol —10 years on”

© Peter Evans FZ LLC Page 3


! www.peterevans.ae
peter evans partnership 27 July 2015

The Committee encourages the Contractor to put favoured by Contractors. The main points are
forward prospective analyses during the works, in summarised as follows:
line with whatever the contract requires, and then
potentially refine its claim with a retrospective • The New Protocol defines six methods,
fact-based method. To satisfy the New Protocol, including three new “Effect and Cause”
where no EOT is agreed prospectively, the methods, and describes the handling of each.
Contractor could adopt a dual procedure -
• Prospectively, Engineers should award only the
prospectively or contemporaneously defining the
minimum EOT that can be justified at the time.
critical path, then again retrospectively.
• TIA is considered unsuitable for a retrospective
The Contractor’s ability to exaggerate its final
delay analysis which should be informed by the
EOT claim is limited by defining the critical path
way in which the Project, in fact, progressed.
retrospectively. This avoids the current situation
whereby the use of TIA instills undue confidence • Practitioners should exercise “common sense”
in the Claimant – encouraging the Claimant to and realise that the facts are of primary
resort to litigation or arbitration where, in reality, importance.
there may be little chance of success.
Industry Impacts
The disadvantage (for the contractor at least) is
that he will potentially have to do more than one • The New Protocol offers a more defined delay
analysis to claim an EOT and will have to expend analysis landscape that should influence the
time and effort to fully understand why each way contracts will be written in the future.
method is appropriate in each circumstance.
However, Contractor’s will produce more robust • Lawyers will need to give direction when
claims with potentially improved results. advising clients who have based their delay
analysis after the event solely on prospective
The New Protocol will likely be a game changer methods.
for contractors and engineers and potentially
reduce the number of unsustainable claims. • Judicial panels will benefit from the guidance
given on the new “Effect and Cause” methods
Conclusions to direct planning experts or analyse EOT
claims.
It has been 13 years since the introduction of the
Old Protocol, since when the industry appears to • Improved, robust retrospective Contractor
have woken up to the prospect of using a claims will likely be a game changer and
“common sense” approach to delay claims. It has reduce the number of unsustainable disputes.
sidelined the use of TIA long after the events
• If the New Protocol gains the same traction as
have taken place and brought a reality check to
the Old Protocol, it could be the catalyst to
potentially theoretical techniques commonly
change how EOTs are agreed in the industry.

Paul Thornton joined Peter Evans Partnership in May 2015 as an Associate Director, Head of Forensic
Delay and Programme Analysis. Paul has a Master’s degree in Civil and Environmental Engineering,
Imperial College London and thesis stage for a Masters in Construction Law and Dispute Resolution
from Kings College London. Paul has 15 years of experience in the construction industry, much of which
has been gained in the Middle East region since 2007.

We hope you found this paper informative. Any feedback please contact: paul.thornton@peterevans.ae.
A follow-up paper, will review the Effect and Cause methodologies from the New Protocol.

© Peter Evans FZ LLC Page 4


! www.peterevans.ae

You might also like