Bobot
No Daftar Pekerjaan Biaya Pekerjaan (Rp) MINGGU KE - %
(%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
100 %
I PEKERJAAN PERSIAPAN Rp 27,474,207.70 16.20 4.051 4.051 4.051 4.05
II PEKERJAAN PONDASI Rp 112,825,663.40 66.54 8.317 8.317 8.317 8.317 8.317 8.317 8.317 8.317 50 %
III PEKERJAAN STRUKTUR UTAM A Rp 25,373,069.35 14.96 2.993 2.993 2.993 2.993
III PEKERJAAN DINDING PAGAR Rp 3,888,110.28 2.29 1.15 1.15
0%
TOTAL Rp 169,561,050.73 100.00 4.051 4.051 4.051 4.05 8.32 8.32 8.32 8.32 8.32 8.32 8.32 11.31 2.99 2.99 2.99 1.15 1.15 0.00
BOBOT RENCANA KOMULATIF (%) 0 4.051 8.102 12.15 16.2 24.52 32.84 41.16 49.47 57.79 66.11 74.43 85.74 88.73 91.72 94.71 95.86 97.01 97.01
BOBOT RENCANA KOMULATIF (%)
SELISIH (%)