Professional Documents
Culture Documents
QC Issues
QC Issues
As per FTTH sp#01 port#18 N/F#2/6 NTL#98846 address 412 exextive but as per tag 4121 exective
As per FTTH sp#01 port#49 N/F#6/4 NTL#93224 but as per tag N/F#06/02
As per FTTH sp#01 port#57 N/F#6/2 NTL#46843 but as per tag N/F#06/04As per
Activity # 4024 for Splitter up gradation was done by your (G-13) team on Dc # 1553. Visit has
been done by QC Team on DC to verify physical patching record and condition of DC after
activity. In activity following issues are found.
As per FTTH sp#01 port#03 N/F#8/2 NTL#104497 but as per tag N/F#12/06.
As per FTTH sp#01 port#12 N/F#13/8 NTL#26378 but as per tag N/F#10/01.
As per FTTH sp#01 port#24 N/F#14/2 NTL#71335 but as per tag N/F#15/01.
Dear Arsalan Bhai,
Activity # 4027 for Splitter up gradation was done by your (G-13) team on Dc # 1548. Visit has
been done by QC Team on DC to verify physical patching record and condition of DC after
activity. In activity following issues are found.
As per FTTH sp#01 port#06 N/F#6/8 NTL#24952 but as per tag N/F#06/02.
As per FTTH sp#01 port#28 N/F#9/3 NTL#88784 but no tag found.
As per FTTH sp#01 port#32 N/F#7/4 NTL#10722 but no tag found.
Binding tap use for Splitter tag.
Dear Arsalan Bhai,
Activity # 4028 for Splitter up gradation was done by your (G-13) team on Dc #
1502. Visit has been done by QC Team on DC to verify physical patching record
and condition of DC after activity. In activity no issue found.
Dear Arsalan Bhai,
Activity # 4030 for Splitter up gradation was done by your (G-13) team on Dc # 1555. Visit has
been done by QC Team on DC to verify physical patching record and condition of DC after
activity. In activity following issues are found.
As per FTTH sp#01 port#8 N/F#7/3 NTL#105687 but as per tag N/F#15/01.
As per FTTH sp#01 port#16 N/F#15/1 NTL#105631 but as per tag N/F#05/02.
As per FTTH sp#01 port#17 N/F#5/2 NTL#44579 but as per tag N/F#07/03.
As per FTTH sp#01 port#18 N/F#6/2 NTL#107550 but no tag found.
Dear Arsalan Bhai,
Activity # 4068 for Splitter up gradation was done by your (G-13) team on Dc # 1506. Visit has
been done by QC Team on DC to verify physical patching record and condition of DC after activity. In
activity following issues are found.