You are on page 1of 9

Ejercicio Determinación de Ley de corte - Lane

Cutoff grade is defined as the grade that is normally used to discriminate between ore
and waste within a given orebody. Although the definition of cutoff grade is very
precise, the choice of a cutoff grade policy to be used during an exploitation of a
deposit is not. Use of simply calculated breakeven cutoff grades during the production
will in most instances lead to sub-optimum exploitation of the resource.

Traditional Cutoff Grades in Open Pit Mining


Consider a hypothetical case study where an epithermal gold deposit will be mined by
an open pit Table 1 gives the grade distribution of the material within the ultimate pit
limits of this deposit. Table 2 gives assumed capacities and accepted costs to mine
this deposit at 3000 tons/day milling rate.
The second cutoff grade is used to ensure that any material that provides positive
contribution beyond the direct milling, refining and marketing costs will be milled.

Heuristic Cutoff Grade Optimization Techniques


In Table 3, Qm represents amount of total material mined (in millions of tons) in a
given year; Qc represents the ore tonnage (in millions) processed by the mill; Qr
represents the recovered ounces (in thousands) produced in a given year. The annual
cash flows are given as profits in millions of dollars and they are determined by using
the following equation (see also Table 2 for variable definition):

Profits($M) = (P – s) x Qr -Qc x c -Qm x m

As long as the operators mine and process the blocks of material with grades greater
than equal to static cutoff grades without considering deposit characteristics, only the
undiscounted profits will be maximized.

The concept of using cutoff grades higher than breakeven grades during the early
years of an operation for a faster recovery of capital investments and using breakeven
grades during the later stages of the mine has been practiced in the industry for
heuristic NPV optimizations.
The year by year tons and grade schedule obtained from the modified cutoff grade
policy is given in Table 4.

In the previous calculations the G & A costs were not included in the cutoff grade and
profit calculations.
Table 5 gives yearly tons and grades schedules resulting from the cutoff grade policy
that includes fixed costs as part of the cutoff grade and the profit calculation.

Optimizing The Cutoff Grades By Lane’s Approach


The preceding discussion has demonstrated the significant impact of the cutoff grade
policy on the NPV of a project. It is generally accepted that the cutoff grade policy that
gives higher NPV’s is a policy that uses declining cutoff grades throughout the life of
the project.
Where i = 1, N (mine life), gmilling,(i) is the cutoff grade to be used in Year i. The Fi is
the opportunity cost per ton of material milled in Year i and it is defined as:

Where d is the discount rate; NPVi is the NPV of the future cash flows of the years (i)
to the end of mine life N; and the C is the total processing capacity in Year i.
Algorithm for Determining Optimum Cutoff Grades
The cutoff grades gmilling(i) given in Equation (1) depend on estimates of NPVi of the
future profits in year i through the end of mine life from the operation and NPVi of the
future profits cannot be calculated until the optimum cutoff grades have been decided.

It is shown in this paper that returns on investments can be improved by exploitation of


a deposit through optimum cutoff grade policy. It is also shown that the use of
traditional cutoff grades in some cases will give sub-optimal NPV for a given deposit to
an extent that the deposit can be rejected. I believe that only through the use of
optimization techniques like the one presented here the accuracy of the decisions with
respect to major mining investments can be assured.

You might also like