Professional Documents
Culture Documents
Thiagarajah a/l Retnasamy [1995], which held that any submission as to whether a certain
clause in a contract is a penalty or liquidated damages is an exercise in futility because as
stated in Section 75 of the Contracts Act 1950, any sum named in a contract as the amount
to be paid in case of breach is to be treated as a penalty, in this case, the defendant has
failed to prove their claim for LD because of their failure to call the architect to testify. Clause
22 of the PAM contract clearly requires the architect to certify entitled to deduct LD. The
certificate of non-completion is a condition precedent to the deduction of the LD.
Lastly, I opine that employer should prove their actual loss in order to protect the contractor’s
right from the overestimation of the liquidated damages made by the employer.