SOURCE OF FUNDING
The source of funding of the proposal “Transport Hub and Product Expo Center”
Is the Municipal government of Mariveles through the help of Municipal Mayor Hon. Ace
Jello C. Concepcion and Vice Mayor Hon. Angelito S. Rubia. AFAB and municipality of
Mariveles offers their help to make the proposal more feasible by, providing some
data’s, recommendation.
LAND ACQUISITION
Land acquisition cost is not included, because the chosen site for the project
proposal, is owned by the government. Republic act no: 9728 that give the AFAB
authority to protect and to manage the lot for future development of the municipality of
Mariveles.
181
CHAPTER
8
LAND DEVELOPMENT
This land development estimated cost is Php. 3,000 per sq. meters. Land cost
per sq. meter includes the following fees.
a. Clearing and Grubbing, trucks and machine rentals. per sq. meters.
b. 5 cu. Cement per 100 sq. meters.
c. Form works 400 board feet’s 2x10x12 per 100 sq. meters.
d. Labor: mason, foreman carpenters per day.
e. Reinforced bars 16mm x 6 meters 10 pcs. Per 100 sq. meters.
f. Drainage systems.
g. Cutting trees.
h. Others fees.
Maximum allowable building footprint 50%
Total Area: 64,188 sq. meters X 50% = 32,094 sq. meters (AMBF)
Total Area: 64,188 sq. meters X 40% = 25,675 sq. meters X COST PER SQ. METERS
Php. 3,000 = Total land development cost Php. 77,025,000
182
CHAPTER
8
BUILDING COST
Budget in different finishes. Values shown here are rough estimate for each
finishes and for budgetary purposes only. Budget already includes labor and materials
and also within the range quoted by most builders.
Total floor area of Transport hub. bus, jeepneys, and tricycle bays are not included:
1,337 sq. meters (ground floor)
Total floor area of Product Expo center: 736 sq. meters (possible in 3rd floor)
additional Php. 10,000 for floor extension.
Total floor area of booking and accommodation. Equipment room, and storage are
not included: 255 sq. meters (possible in 2nd floor) additional Php. 10,000 for f loor
extension.
183
CHAPTER
8
TOTAL FLOOR AREAS
TRANSPORT HUB
TOTAL
SPACE SPACE TOTAL AREA
AREA
ARRIVAL TICKETING OFFICE 36.27
72.15
BOARD OF
DIRECTOR OFFICE
36.27
WAITING AREA 42.25
FINANCE MANAGER
OFFICE
24.18
INFORMATION AREA 97.5
LEGAL DOCUMENTS
OFFICE
182
PUBLIC RESTROOM 58.5
CLINIC 11.7
LOUNGE 104
E. P. L 11.96
CHARGING STATION 16.9
MECH.PL 36.27
TELEPHONE AREA 14.43 WORKING STATION
364
AREA
ATM MACHINE AREA 16.9 CCTV ROOM 9.36
COMPUTER SERVER
DRINKING AREA 14.43 ROOM
4.68
CHIEF SECURITY
RETAIL STORES 67.6 OFFICE
24.18
STORAGE 36.4
SOUVENIRS STALL 16.9
BUS BAY
TICKETING AREA 19.5
JEEPNEY’S BAY
PRAYING AREA 42.25
TRICYLE’S BAY
BAGGAGE
INSPECTION AREA
7.215
184
CHAPTER
8
PRODUCT EXPO CENTER BOOKING AND ACCOMODATION
TOTAL TOTAL
SPACE SPACE
AREA AREA
WORKSHOP 29.9
EQUIPMENT
ROOM
185
CHAPTER
8
FURNISHING AND EQUIPMENT COST
TABLE AND CHAIR
186
CHAPTER
8
AIRCONDITIONING SYSTEM
Transport hub Quantity Type Price (set of AC.)
Ticketing office 1 Split-type Php. 30,000
Board of director 1 Split-type Php. 30,000
Finance office 1 Split-type Php. 30,000
Legal document office 1 Split-type Php. 30,000
Clinic 1 Window-type Php. 15,000
Chief sec, office 1 Window-type Php. 15,000
Charging station
Ticketing area
Telephone area
Atm. machine area Centralized
Drinking area 3 air-conditions system
Waiting area Php. 180,000
Lounge
Information area
Product expo center
Director office
Office personnel
Accounting office Split-type Php. 150,000
Sale association office 5 air-conditions system
Business assistant office
Retail shops 3 Centralized
air-conditions system Php. 180,000
Amphitheater 1 Centralized
Php. 60,000
air-conditions system
Stalls area 1 Centralized
Php. 60,000
air-conditions system
Workshop 1 Split-type Php. 30,000
Booking and accommodations
Split-type
Office personnel 1 Php. 30,000
air-conditions system
Split-type
clerk 1 Php. 30,000
air-conditions system
Split-type
Treasurer office 1 Php. 30,000
air-conditions system
Split-type
Chief mechanic office 1 Php. 30,000
air-conditions system
TOTAL Php. 960,000.00
Note: installation is not included in total price for air-condition system
187
CHAPTER
8
BACKUP POWER SUPPLY
Quantity Type Price
Transport Hub 1 Diesel standby generator Php. 435,000
Product expo center
1 Diesel standby generator Php. 435,000
Booking and accommodation
TOTAL Php. 870,000
ELECTROSTATIC PURIFIER
Transport Hub Quantity Price
Electrostatic Air purifier 1 Php. 800,000
Note: installation of electrostatic purifier is not included.
8 CCTV PER SET. 450X450 1 CCTV IS FOR 20 sq. meter Php. 7,800
Quantity (sets) Total sq. meters Price
Transport Hub 8 1,337 sq. meters Php. 62,400
Product expo center 4 736 sq. meters Php. 31,200
Booking accommodations 2 255 sq. meters Php. 15,600
TOTAL Php. 109,200
Note: installation of CCTV is not included.
188
CHAPTER
8
MAINTENANCE SUSTAINABILITY
Electric consumption for product expo and other commercial establishments in the
project, is based on their own individual electric meter usage.
MINOR MAINTENANCE
The minor maintenance for the product expo center is per materials that will
replace or need to be fix. The maintenance personnel breakdown the list of needed
materials, with exact price range. Example of minor maintenance are listed below:
Replacement of lights
Electrical repairs
Paints
Roof maintenance
Mechanical system repair
Air-condition system repair
MAJOR MAINTENANCE
The municipal government of Mariveles, have the authority to conduct a major
maintenance. The estimated cost of the major maintenance is the engineering
department duties and responsibilities. Major maintenance is listed below:
Renovation
Expansion
Road widening
Drainage maintenance
189
CHAPTER
8
SALARY OF EMPLOYEES OF TRANSPORT HUB & PRODUCT EXPO CENTER
PER-DAY PER-MONTH
Transport hub APPROX.8500 Php. 255,000
Product expo
APPROX.7200 Php. 144,000
center
Booking and
APPROX.8000 Php. 120,000
accomoodation
Approximately total of: Php. 519,000 per-month
Approximately total of: Php. 6,228,000 per-year
190
CHAPTER
8
RETURN OF INVESTMENTS
TRANSPORT HUB
NUMBER
PUV’S TERMINAL FEES PER-MONTH PER-YEAR
OF PUV’S
ORDINARY BUS 120 Php. 20,00 Php. 74,400 Php. 892,800
GENESIS 60 Php. 20,00 Php. 37,200 Php. 446,400
BATAAN TRANSIT 40 Php. 20,00 Php. 24,800 Php. 297,600
JEPPNEYS
SENTRO 130 Php. 3,00 Php. 145,080
Php. 12,090
OUTSIDE 60 Php. 10,00 Php. 223,200
Php .18,600
MARIVELES
TRICYCLES 305 Php. 2,00 Php. 18,910 Php. 226,920
UV EXPRESS 20 Php. 20,00 Php. 12,400 Php. 148,800
TOURIST VAN
10 Php. 20,00 Php. 6,200 Php. 74,400
PARKING
TOURIST VAN
10(5) Php. 4,000 Php. 620,000 Php. 7,440,000
RENT
APPROX.
PAY-PARKING Php. 15.00 Php. 46,500 Php. 558,000
100
TOTAL INCOME PER-MONTH Php.846,300
TOTAL INCOME PER-YEAR Php. 10,453,200
STALL RATES
NO: OF RATE PER SQ. MIN. SQ
SECTION PER-MONTH PER-YEAR
STALLS METERS METERS
LOCAL GOODS 10,00/per sq. 20 sq.
Approx. 100 PHP. 620,000 PHP. 7,440,000
GARMENTS meters Meters
30,00/per sq. 16 sq.
EXPORT GOODS 30 PHP. 446,400 PHP. 5,356,800
meters Meters
20,00/per sq. 10 sq.
PROCESS FOODS 10 PHP. 62,000 PHP. 744,000
meters Meters
LOCAL PROCESS 7,00/per sq. 10 sq.
20 PHP. 43,400 PHP. 520,000
FOODS meters Meters
DRY GOOD MUSLIM 10,00/per sq. 16 sq.
30 PHP. 148,800 PHP. 1,785,600
TRADERS meters Meters
INDUSTRIALS 10,00/per sq. 25 sq.
30 PHP. 232,500 PHP. 2,790,000
PRODUCTS meters Meters
10,00/per sq. 20 sq.
SOUVENIRS 5 PHP. 31,000 PHP. 372,000
meters Meters
10,00/per sq. 10 sq.
DRIED FISH LOCAL 10 PHP. 31,000 PHP. 372,000
meters Meters
TOTAL INCOME PER-MONTH Php. 1,615,100
191
CHAPTER
8
TYPES NO: ESTABLISHMENT RATE PER-MONTH PER-YEAR
RESTAURANT 3,00/per
APPROX. 10 sq. meters Php. 27,900 Php. 334,800
30 sq. meters
10,00/per
GROCERY APPROX. 2 Php. 12,400 Php. 148,800
sq. meters
CONVINIENT 15,00/per
APPROX. 4 sq. meters Php. 55,800 Php. 669,600
STORE
TOTAL INCOME PER-MONTH Php. 96,100
TOTAL INCOME PER-YEAR Php. 1,153,200
TOTAL INCOME PER-YEAR Php. 19,381,200
Note: not all the stall is permanent, it will be function all for the month of October until December 28
For trade fair
COMMERCIAL ESTABLISHMENT
192