4 quarry including cost and conveyance of all materials like cement, sand water, granite stones, etc., from approved
quarry to site and including labour for cutting stones to required size and shape, mixing of cement, mortar,
construction, scaffolding charges, curing etc., complete for finished item of work in foundation & basement Excluding
seigniorage charges (APSS No. 615 & 601)
Unit: 1Cu m
BLDCSTN-6-13
A)Materials
CR Stones 0.44 Cum 811.25 356.95
Rough Stone 0.5 Cu m 495.35 247.68
Bound Stone 7nos 0.24x0.24x0.39=0.16 Cu m 0.16 Cu m 1431.92 229.11
Cement 59.4 Kg 5.7 338.58
Sand 0.33 Cu m 459.95 151.78
1324.1
B)Lab our
1st class mason 1.2 Nos. 420 504
Man Mazdoor 2 Nos. 320 640
1144
Add for MA at 20% 0.2 1144 228.8
1372.8
ADD (A+B) 2696.9
Add over head charges & contractor profit 14% 0.13615 2696.9 367.18
Rate per 1 Cu m 3064.08
Rate per 1 Cu m 3064
Construction of granular sub-base by providing well graded material / Close graded material, spreading in uniform layers
with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with
5
smooth wheel roller 80-100 kN / Vibratory Roller to achieve the desired density, complete as per Technical
Specification Clause 401 MORD / MORTH.
Hire chargesof
plant & machinery
for Roads &
hour
Bridges works for
year 2015-16 Item
no.12
Tractor with rotavary 25 cum per hour 6 380.6 2283.6
As per WRD ( S.no
hour
62) Vibratory roller 8-10tonne 6 2308.9 13853.4
Hire chargesof
plant & machinery
for Roads &
hour
Bridges works for
year 2015-16 Item
no.10
Water tanker 6Kl capacity 3 588.5 1765.5
Total 17902.5
c). Material
For well /close graded graded Granular sub base Materials per table 400-2
Hire chargesof
plant & machinery
for Roads &
Hour
Bridges works for
year 2015-16 Item
no.38
Concrete mixer 0.28/0.4cum capacity (6mixers) with weigh batcher and suitable capacity calibrated
36 water
435.5 tank 15678
Hire chargesof
plant & machinery
Hour
for year 2015-16
Item no.40
Needle vibrator 40 mm dia ( petrol ) (CommSSR Items no: 40) 9 173.7 1563.3
Plater vibrator 40 mm dia ( petrol ) Hour 9 476.5 4288.5
Hire chargesof
plant & machinery
Hour
for year 2015-16
Item no.10
Water tanker 6Kl (As pper SSR vide page no:27, S.No: 10 SSR rate) 5 588.5 2942.5
Total hire charges of Machinery 24472.3
C. Matreials
Providing Dry lean cement concrete Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to
IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate
gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/ cum, optimum moisture
content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days,
mixed in a batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tonnes
vibratory roller, finishing and curing complete for finished item of work as per MoRT&H (5th Revision) specification
1500,1700 & 601 (5th Revision) and as directed by the Engineer-in-Charge for base coarse below CC Pavement.
Unit = cum
(A) Labour
Mason Skilled day 1.12 490 548.8
Mazdoor Skilled day 6 375 2250
Mazdoor day 22 320 7040
Total 9838.8
(B) Material
Coarse Sand as per IS: 383 @ 0.45 cum/cum of concrete cum 203 581 117943
Cement @ 150 kg/cum of concrete MT 67.5 2100 141750
701143
(c) Machinery
Front end loader 1 cum bucket capacity hour 6 1432 8592
Cement concrete batch mix plant @ 75 cum per hour hour 6 1122 6732
Electric generator 100 KVA hour 6 1107 6642
Paver with electronic sensor hour 6 2748 16488
Vibratory roller 8-10 t capacity hour 8 2308 18464
Water tanker 6 KL capacity hour 8 588.5 4708
Total 61626
(D) 772607.8
Add for Over head charges @ 13.615% on (A)+(B)+( C) % 13.615 105206.004
(E) Total of (A) + (B)+( C)+(D) 877813.804
(F)
Cost per 450 cum (E) + (F) 877813.804
Rate for 1 cum 1950.69734
Rate to be adopted 1951
Construction of Granular sub-base by providing HBG material confirming to Grading - III of MoRT&H Table 400-1 including
cost and conveyance of all materials to work site and spreading in uniform layers with motor grader or by approved means,
on prepared surface mixing by mix in place method with Rotavator / approved means at OMC and compacting with
vibratory roller to achieve the desired density etc., complete for finished item of work as per MoRT&H Specification 401
5 (5th revision) and as directed by the Engineer-in-charge.
Unit = cum
Taking output = 300 cum Page 95 of MoRT&H SDB
(A) Labour
0.4 day Mate 471 day 188.4
2 day Mazdoor skilled 472 day 944
8 day Mazdoor unskilled 420 day 3360
Total 4492.4
(B) Machinery
6 hr Motor grader 3.35M Blade @50 cum/Hr 3020.4 hr 18122.4
12 hr Tractor with Rotavator 423.6 hr 5083.2
Total 41302.2
(C) Material
Total 422246.4
101725.04
(C ) Material
945 Cum Crushed stone coarse aggregates of 25mm and 12.5mm nominal 1486.3
size @ 0.90
Cumcum/cum of concrete
1404553.5conforming to clause 6
473 Cum Sand as per IS: 383 and conforming to clause 602.2.4 @ 0.45 cum/cum
288.3ofCum
concrete 136365.9
16.33 Sqm Pre moulded Joint filler, 25 mm thick for expansion joint. 273 Sqm 4458.09
875 Kg Joint sealant 60 Kg 52500
1 116.67 Kg Sealant primer 496 Kg 57868.32
2 46.67 Sqm Plastic sheath,1.25 mm thick for dowel bars 5 Sqm 233.35
1850 liter Curing compound 112 liter 207200
2070 Kg Super plastisizer admixture IS marked as per 9103-1999 @ 0.5 per cent 43 by
Kgweight of cement 89010
4068872.91
Add 1 per cent of material for cost of miscellaneous materials like tarpauline, Hessian cloth,
406887.291
metal cap, cotton / compress
4475760.201
(D) Over head charges @ 4.615% (10%-VAT-Insurance)
4.615 % Add for Over head charges @ 4.615% on (A)+(B)+( C) 212299.56
(E) Total of (A) + (B)+( C)+(D) 4812506.801
(F) Add Contractors Profit at 10% on (E) 481250.6801
Cost per 1050 cum (E) + (F) 5293757.481
Rate for 1 cum 5041.67
Rate to be adopted 5042
1 Cum
Construction of Granular sub-base by providing HBG material confirming to Grading - V of MoRT&H Table
400-1 including cost and conveyance of all materials to work site and spreading in uniform layers with
motor grader or by approved means, on prepared surface mixing by mix in place method with Rotavator /
6
approved means at OMC and compacting with vibratory roller to achieve the desired density etc.,
complete for finished item of work as per MoRT&H Specification 401 (5th revision) and as directed by
the Engineer-in-charge.
Total 41302.2
(C) Material
53 mm to 9.5 mm @ 50%
(Av. rate of 50 - 55 mm, 40-45 mm, 25 - 27 mm, 19 -
192 cum 22 mm, 12 to 14 mm, 9.5-11.2mm HBG M/C metal) 1227.808 cum 235739.2
Total 404622.9