Tes Awal :
Pertanyaan :
1. Sebutkan 5 sistem pemboran!
2. Sebutkan komponen dalam drawworks dan fungsinya!
3. Jelaskan perbedaan duplex pump dan triplex pump!
4. Jelaskan 2 well control system secara umum!
5. Sebutkan minimal 4 alat yang berfungsi sebagai contaminant removal!
Jawaban :
1. Hoisting System, Circulating System, Rotary System, Power System, Well Control System
2. Drum : Transmit torque for hoisting or braking
Brakes : Stop and sustain weights when lowering string
Transmission : Changing direction and speed of traveling block
Cathead : Assist lifting or moving equipment
3. Duplex :
- Two cylinders, double acting
- Generally used on land rigs

Triplex Pump
- Generally used on Offshore
- Three cylinders, single acting
4. In General, there are two types of well control system :
Primary Well Control, ensuring that the hydrostatic mud pressure is sufficient to
overcome formation pressure.
Secondary well control, using valves to prevent the flow of fluid from the well until such
time as the well can be made safe.
5. Shale Shaker , Degasser, Hydrocyclones, Decanting centrifuges