The Algebra of Successful Project Procurement
The Algebra of Successful Project Procurement
Let
X1, X2 and X3 be the quantity present in the material take off, requisitions and specifications
respectively. Refer this post for more clarity.
• piping
mto
• electrical
• ups
requisition • valves
• vessels
• hvac package
scope specification
• mechanical handling package
The value of X should not change in ideal situations. But it is not so.
Deviations taken by vendor during TQ, TBE, review, inspection stage are denoted by y1, y2, y3
and y4.
As the vendor item reaches site, there could be further problems with material like theft,
damage, defects, improper storage etc. Let this value be Y5
Hence ΣY = Y1 + Y2 + Y3 + Y4 + Y5
The contractor needs to track and control the value of ΣY. This is the algebra of successful
procurement.