Basic Price
No Jenis Bahan Satuan Harga Dasar Ongkos Galian Over Harga Pajak Total Dibulatka
Angkut C Head Di Lainnya n
Lokasi
Proyek
1 2 3 4 5 6 7 8 9 10 11

I Bahan

1 Semen 50 kg Kg 65,000.00 5,200.00 7,020. 77,220 1544.4 78,76 79,000.0


00 .00 4.4 0

2 Pasir M3 65,000.00 5,200.00 182,0 7,020. 259,22 5184.4 264,4 270,000.


00 00 0.00 04.4 00

3 Kerikil M3 70,000.00 5,600.00 252,0 7,560. 335,16 6703.2 341,8 345,000.


00 00 0.00 63.2 00

4 Kayu 5/7 kls M3 20,000.00 1,600.00 21,60 43,200 864 44,04 44,1000.
II 0.00 .00 6 00

II Upah

1 Pekerja Org/H 95,000.00 95,000 95,00 95,000.0


r .00 0.00 0
2 Mandor Org/H 175,000.00 175,00 175,0 175,000.
r 0.00 00.00 00

3 Kepala Org/H 145,000.00 145,00 145,0 145,000.


Tukang r 0.00 00.00 00