Professional Documents
Culture Documents
2. The system piping shall be traced from the source (e. g. chiller, heat
exchanger) to all terminal units to determine.
3. It shall be confirmed that the system has been cleaned, flushed, filled, and a l l a i r
purged. It shall be verified that strainer baskets have been cleaned and
construction baskets (if used) have been removed. The system cleanliness during
the TAB work shall be monitored and any debris build-up may affect the final
system balance.
4. It shall be verified that the system water level and pressure are correct for
the highest terminal units.
Inspect the pressure reducing valve's (PRV) for proper installation and operation.
The testing of RPV should always maintain a minimum 4 PSI static pressure at the
highest point of the system. Check the water level of the expansion or comparison
tank. Generally, 1/3 air and 2/3 water is the proper ratio of the cold expansion
tank. Please clarify if pressure relief valve / or air vent. There is no Pressure Reducing Valve installed for chilled water
system at Admin Building.
01 of 09
Testing, Adjusting & Balancing Procedures
B. Pumps:
1. All required data shall be recorded on the NEBB test report forms, include
pump nameplate and motor nameplate data.
2. The nameplate data shall be compared with manufacturer’s submittal data
and design requirements. Any discrepancies will be noted.
3. It shall be verified that the pumps have been properly aligned, grouted, anchored
and lubricated.
4. If vibration isolation is used, it shall be checked for proper installation and
adjustment. All piping should be supported independent of the pump housing.
Operation of the pump with out the proper support may result in damage to volute
casing.
5. It shall be confirmed that the drive guards are in place.
6. It shall be verified that access has been provided for accurate pressure drop
readings.
7. The cleanliness of any strainer (s) serving the pump shall be verified.
8. All air shall be purged from the volute casing. Operation the pump with air
may cause cavitations resulting in damage to impeller and volute casing.
9. The electrical starter, disconnect switches, and main circuit breaker for the
pumps shall be located and verified. It shall be confirmed that thermal overload
protection is installed and of the proper size.
10. It shall be confirmed that electrical power is available for start-up and that
the voltage equipment needs are compatible.
11. The motor shall be “bumped” for rotation check. It should be ensured that
the pump is completely full of water if mechanical seals are used. Operation of a
dry pump with mechanical seals, including “Bumping” will result in seal damage.
If a packing gland is used. It should be adjusted for proper shaft lubrication.
C. Coils/Terminal Units:
1. It shall be verified that the units are piped correctly including required valves,
vents and safety devices.
2. It shall be confirmed that provisions are available for making the required
temperature and pressure measurements.
O & M to assure that all pressure gauge and thermometer are at good working condition prior to water balancing.
02 of 09
Testing, Adjusting & Balancing Procedures
2. Safety Tagging:
1. preparation
A. All previously prepared paper work, etc., for the system to be balanced
shall be assembled and studied.
B. It shall be verified that the preliminary system checks and procedures have
been performed.
C. Safety precautions shall be observed prior to starting any equipment related to
the operation of hydronic systems i.e. pumps, chillers, etc.
2. Pump Start Up
Prior to pump start-up the TAB Engineer shall ensure that the system is filled
with water, all air is purged from the system, the
03 of 09
Testing, Adjusting & Balancing Procedures
make-up water system is with water, all air is purged from the system, the make-
up water system is operational, and that all strainers are clean. He shall also check
that all valves are in there normal operating position, and that all control valves are
open to full flow through the coils and equipment served by the system. All
automatic controls shall be checked for correct position.
B. Pump rotation shall be verified by “bumping” the motor i.e. the motor is
energized for a fraction of a second and the pump shaft is observed to determine
rotation direction. If the rotation is incorrect, it will be noted and the electrician
responsible for the HVAC equipment shall be advised to correct the fault. The
electrician, eliminate the possibility of the TAB technician being held responsible
for any possible damage to the motor or equipment will do this.
C. If the rotation is correct, the pump will be started. Amperage and voltage of
the motor will be measured. Amperage measurement shall be taken when the
motor is operating at full speed. Voltage should be within 10percent of the motor
nameplate rating, and there should be a very little difference of voltage and
amperage between each leg on three phase motors. Amperage should not exceed
the nameplate rating if the amperage is high, the pump will be start immediately.
A. Prior to testing the pump for flow rate, it shall be tested in a no flow condition.
Placing the pump in operation will do this and gradually closing the discharge
valve until the valve is fully closed and no water flow occurs. After the valve is
fully closed, a differential pressure reading will be obtained and plotted on the
manufacturer’s pump curve for the particular pump being tested. This will verify
the shutoff head and in turn verify from the curve, the actual size of the impeller
installed and establish the actual performance curve. After measurement of no
flow differential, the discharge valve shall be opened to the full open position.
O & M to provide chilled water pump 's pump curve to be obtain from the archive at library.
04 of 09
Testing, Adjusting & Balancing Procedures
Balancing shall only be obtained by means of the proper balancing valves and
automatic flow control valves. Service valves will only be used where they are
equipped with memory stop.
After balancing flow through the coils, all 3-way valves shall be reset for flow to
by-pass and the by-pass balancing valves adjusted to equal the pressure drop
across the coil during full flow.
Upon completion of all adjustments, all balancing valves shall be marked to
indicate the final set point.
D. After completion of all adjustments, the flows, pressure and amperage of the
pumps shall be rechecked and recorded.
E. Calibrated test gauges shall be used to measure the final pressure drop across each
component after balancing is complete. All final measured flow rates, pressure
drops, etc. shall be recorded on the relevant NEBB Test Report Form.
Note: Be sure to take the final readings for the pumps and chillers after the balancing.
Record the final VFD setting & differential pressure close to DPT.
4. Certified Reports:
Upon completion of the aforementioned test, three (3) copies of the certified reports
will be submitted to the client prior to final tests and inspection. All reports shall
contain all relevant data obtained during the testing of the systems.
The report will conspicuously identify items not conforming from contract require-
ments, and obvious mal-operation and/or design. This will be noted on the Tests
Report if after notifications, no satisfactory response is obtained. We proudly used
NEBB BALPRO Software to generate TAB reports.
06 of 09
Testing, Adjusting & Balancing Procedures
All final test and inspection required for acceptance of the aforementioned work
shall be done and rechecked in the pressure of the client’s representative at random
selection of data recorded on the reports.
All final tests and required for acceptance of the aforementioned work shall be
preformed in strict compliance with project specification.
09 of 09
Testing, Adjusting & Balancing Procedures
Operation:
Chillers must be in operation before the test and balance technician begins the
procedure. All controls are to be installed, calibrated, and fully operational.
Inspection:
1. Inspect the system to determine if it is complete and operable. If not, then end the
procedure, list any deficiencies, and proceed when they are corrected.
2. Verify that the chiller is running at the maximum load available and at a normal water
temperature setting.
3. Verify that the condenser water temperatures are correct and the cooling tower
operates properly.
4. Verify that the chilled water pumps and condenser water pumps are lined up correctly
and operate properly.
5. Verify that the flow meters are installed in chilled water piping and in condenser
piping. Flow meters are required for this rest. Provide operating manual for ultra sonic flow meters and
calibration certificate.
6. Verify that the thermometer wells and test thermometers are installed properly in
chilled water and condenser water piping according to the Basic Temperature Testing
Measurements procedure.
Condenser water not applicable. Verify chiller condenser fan working conditions in line with compressor
performance on same refrigeration circuit.
Procedures:
1. Balance and set the chilled and condenser water flow through the chiller.
2. Measure and record the entering and leaving vessel pressure on the cooler and con-
denser, and compare to the manufacturer’s submittal data, if available.
3. Load the chiller to the maximum obtainable load until an equilibrium steady state is
reached in the chilled and condenser water temperatures.
4. Log the entering and leaving condenser and chilled water temperature every five min-
utes for a one-hour duration (12 readings).
5. Log the compressor motor input kw and verify water flow and vessel pressure drop
every 15 mintues (four readings) during temperature log time.
6. Average each station reading.
7. Calculate the cooler (evaporator) capacity in tons.
8. Calculate the condenser capacity in tons.
9. Calculate the compressor motor input kw in tons.
10. Add the cooler tonnage to the compressor motor kw tonnage. This sum should equal
the condenser tonnage within 10% for a valid heat balance and acceptable field test.
Testing, Adjusting & Balancing Procedures
11. Upon completion of the test record the following data on report forms.
1. Factory and actual data of the installed chiller.
2. Water flow gpm for chilled and condenser water, include flow meter data, if
installed.
3. All water vessel pressure drops.
4. Final average temperatures of cooler and condenser measured to 0,10°F.
5. KW power readings, including amperage and voltage.
6. Cooler tons, condenser tons, kw tons, and heat balance equation results.
Report:
1. Include all test data on a chiller capacity data sheet.
2. List conditions at the time of the test and the results.
3. List any uncorrected deficiencies that affected the test results on the deficiency report
form.
4. Include required data from the Report Contents procedure.
Compliance:
1. Compliance with this procedure requires completion of all of the above steps with all
data recorded on the report forms.
2. All deficiencies that affect the test must be resolved by the installing contractors or in-
cluded in that deficiency report.
3. Instrumentation must be accurate and suitable for this type of testing. Test accuracy
should be within 5%.
Checklist Prior To
Start TAB Works
Checklists Prior To Start TAB Works
S# Description Remarks
1 Systems are started and operating in a safe and
normal condition.
2 Temperature control systems are installed
complete and operable.
3 Proper thermal overload protection is in place for
electrical equipment.
4 Final filters are clean and in place. If required,
install temporary media in addition to final filters.
5 Duct systems are clean of debris.
6 Fans are rotating correctly.
7 Fire and volume dampers are in place and open.
8 Air coil fins are cleaned and combed.
9 Access doors are closed and duct end caps are in
place.
10 Air outlets are Installed and connected.
11 Duct system leakage is minimized.
Regards,
Page 1 of 4
Construction Team Responsibilities:
1. Provide the TAB firm with a conformed set of contract documents
(drawings, specifications, and approved submittal), including all
current approved change orders and contract modifications.
2. Develop a project schedule, with the input of TAB firm, that
coordinates the work of other disciplines and provides adequate
time in the construction process to allow successful completion of
the TAB.
3. Notify the TAB Firm of all schedule changes.
4. Ensure that the building enclosure is complete, including but not
limited to, all structural components, windows and doors installed,
door hardware complete, ceilings complete, stair, elevator and
mechanical shafts complete, roof systems complete, all plenums
sealed, etc.
5. Ensure that all necessary mechanical and HVAC work is complete
and is safe to operate. This includes, but is not limited to, duct
leakage testing and hydrostatic testing. The piping systems should
be flushed, filled, vented, and chemically treated. All strainers
should be cleaned and the correct screens installed. The duct
systems and all related equipment should be cleaned and the
specified clean air filters installed. For additional requirements see
the Pre-TAB checklist (attached).
6. Complete the installation of permanent electrical power systems
serving the HVAC equipment and systems. Such electrical systems
shall be properly installed in accordance with all applicable codes
to ensure the safety of all construction personnel.
7. Perform start up of all HVAC equipment and systems in accordance
with manufacturers’ recommendations.
8. Complete the installation, programming (including design
parameters and graphics), calibration, and startup of all building
control systems. Verify that the building control system provider has
commissioned and documented their work before balancing
begins
9. Require that the building control system firm provide access to
hardware and software, or onsite technical support required to
assist the TAB effort. The hardware and software or the onsite
technical support shall be provided at no cost to the TAB Firm.
10. Furnish and install all drive changes as required.
Page 2 of 4
SAMPLE PRE-TAB CHECKLIST
This is a sample checklist to be provided by the TAB Firm to the installing contractor for the contractor’s
use in verifying system readiness prior to balancing.
Project:
Ready Ready
1. HVAC Units & Built-Up Units Date Date
Yes No Yes No
a) GENERAL d) FANS
c) COILS (ELECTRIC)
Airflow direction
Duct connection
Safety switches
Ready Ready
2. Duct Systems Date Date
Yes No Yes No
Other checks
a) Other trade or personnel
notified of TAB work requirements
TOTAL
REMARKS: