REPUBLIC OF THE PHILIPPINES

PROVINCE OF BATANGAS
MUNICIPALITY OF LIAN

OFFICE OF THE MUNICIPAL ENGINEER

Date: November 12, 2019


Project: Supply of Electrical Materials
Location: Plaza Covered Court
Total Est. Cost: 14,840.00 Php
Durations: 7 calendar days
Source of Fund:

SCOPE OF WORK

1.00 Supply of electrical materials

Prepared by: Eng'r Reynaldo A. Limon


Municipal Engineer

Approved by: Dr. Isagani I. Bolompo


Municipal Mayor

4
4
REPUBLIC OF THE PHILIPPINES
PROVINCE OF BATANGAS
MUNICIPALITY OF LIAN

OFFICE OF THE MUNICIPAL ENGINEER

PROGRAM OF WORKS
DETAILED AGENCY COST ESTIMATE

Date: November 20, 2019


Project: Maintenance of Generator Set
Location: Municipal Building and R.H.U.
Total Est. Cost: 14,840.00 Php
Durations: 7 calendar days
Source of Fund:

Item no. Description Unit Quantity Unit Cost Amount


1.00 Materials

1.01 Oil - Dezo Gold gal 14.00 960.00 13,440.00


1.02 207 Oli Filter pcs. 2.00 320.00 640.00
1.03 512 Oil Filter pcs. 2.00 380.00 760.00

sub-total (1) 14,840.00


Summary
a. Total Cost of Materials 14,840.00
say Php 14,840.00

Prepared by: Eng'r Reynaldo A. Limon


Municipal Engineer

Approved by: Dr. Isagani I. Bolompo


Municipal Mayor