REF I M&I SHUT DOWN JOBS - EP&S

I. OISD GAP IDENTIFICATION


Sl.No. JOB DESCRIPTION EQUIPMENTS REMARKS Dwg No.
Steam isolation valves on the Firebox to
1 OISD - 111 rev
be minimum 15 m distance
Stack Damper pressure monitoring - A
2 common PI shall be provided at the OISD - 111 rev
common inlet and outlet of furnaces

II. ESA/SSC/ISA RECOMMENDATIONS


Sl.No JOB DESCRIPTION EQUIPMENTS REMARKS Dwg No.
Naptha 7LPG Pumps to be converted
1
to Double Seal
9th SSC
Light HC Sample point drains to be
2
connected to closed system
3 Critical Hydrocarbon lines clamped

CDU-I CBD Vent is open to


4 Atmosphere shall be connected to ISA - 2016
Flare

III. CPCB/TNPCB RECOMMENDATIONS


Sl.No JOB DESCRIPTION EQUIPMENTS REMARKS Dwg No.
Stack Analyser Nozzle provision / TNPCB /CPCB
1
approach ladder / Platform modification guidelines

stack
2 Plant-13 - 13F01-Platform extension
monitoring
EQUIPMENTS
1F1A/B , 1F2/F3 ,4F1 , 9F201/301, 10F1&13F1

SD Planning Reply / Status