Professional Documents
Culture Documents
APRIL 1980
THEARUP
Vol. 15 No. 1 April 1980 Contents
Published by
Ove Arup Partnership
1 3 Fitzroy Street, London W1 P 6 B Q
Safety f a c t o r s :
S o m e aspects of
C I R I A Research Project 2 2 3 ,
by P. B e c k m a n n
R u n n y m e a d Bridge, 5
by W . S m y t h
T h e south abutment 9
at Kessock Bridge,
by K. C o l e
Design and construction
at the Lukasrand m i c r o w a v e 12
tower, Pretoria,
by C . M c M i l l a n
Central B a n k , Dublin
18
Front and back covers : R u n n y m e d e Bridge across the T h a m e s alongside L u t y e n s ' Bridge ( P h o t o s : Harry S o w d e n )
as partial coefficients' or partial safety actual risks of a failure of a structure designed < Resistance from — w h e r e W d is dead
factors, were allocated to the loads and to the to present day codes are about 10 times as big Ym
2 resistance of the structure. as the calculated risks, due to c a u s e s s u c h as load and W , covers live loads, w i n d loads,
etc. and fk is the characteristic material
strength. Fig.1 •
Both loads and strengths in this equation are Typical relationship
entered with a 'characteristic' value, that is between cost
a value that has a certain agreed probability and total probability
of occurring. of failure
Y is a reduction factor on material strength
m
I
material resulting from the construction
process:
T h i s is a function of w o r k m a n s h i p and super-
vision. British codes and drafts, except the
masonry draft w h i c h varies Y with m a n u f a c -
m
section:
I n a c c u r a c i e s in construction are a function of Distant water trawling ( 1 9 5 8 - 7 2 ) 2900 17
w o r k m a n s h i p and hence supervision. T h e Air travel ( c r e w ) 1000 12 10- 3
Yf, is a multiplier applied to loads or im- Home accidents (able bodied) 5500 0.4 4x10- 5
istic value:
There is here the difficulty that very f e w types
of load are sufficiently recorded to establish All causes ( E n g l a n d and Wales, 1 9 6 0 - 1 9 6 2 )
a mean value, let alone a characteristic.
T h e codes tend to apply factors to nominal Male age 3 0 8700 13 10- 3
Certain earth stability problems t h r o w up even BS 4360: one tensile test for every 4 0 In both instances w e found little that could
w o r s e predicaments: in the classical slip tonnes, is another matter. (It corresponds to usefully be adopted in building and civil
circle calculation the calculated factor of one test for each km length of 1 2 i n . x 6 J i n . engineering design because ( a ) w e do not
safety remains constant regardless of the U B ( 3 0 5 x 1 6 5 x 4 0 ) or one test per 2\ have enough data on performance, failures
value c h o s e n for 7f. milesof4in. x 3in.angle (102 x 7 6 ) . ) and their c a u s e s , ( b ) w e do not have long
Apart from the partial safety factors there are enough production runs to be able to benefit
certain other parameters that affect the D e f i n i t i o n of f a i l u r e : from prototype testing, and ( c ) w e cannot
reliability of a structure: Mention w a s made earlier of modelling practically enforce a materials testing regime
errors in calculation of resistance of a struc- a n y w h e r e as stringent as the aircraft industry.
D e s i g n life tural member, but occasionally our traditional T h i s article only deals w i t h a small part of the
assumptions about the mode of failure lead entire research project w h i c h is fully described
T h e limit state philosophy usually includes
to errors not of plus or minus 1 5 % but several in C I R I A report no. 6 3 .
the phrase: the structure shall not become
hundred %. For instance, a beam spanning I hope that none of the hardworking chairmen
unfit for its intended use during its design
between heavy c o l u m n s at 1st floor level of a and members of code committees take any
life.' No code defines the design life and yet
multi-storey building will carry, in a catenary of the comments in the report or in this
it w o u l d seem essential to do so w h e n
action, a load several times that w h i c h will article as a criticism of their work. Having been
dealing with materials w i t h strengths w h i c h
collapse an identical beam at the top of the involved on the sidelines of one of those
reduce with time s u c h as timber or forces
building. committees, I k n o w that it is difficult just
w h i c h increase w i t h age such as drag on
marine structures due to barnacle growth. Design practice in allied fields of to make the transition from permissible
S o m e confusion also occasionally o c c u r s stresses to partial safety factors, especially
engineering :
between design life and return period of w h e n it is also stipulated that design a c -
T h e treatment of safety in aeronautical, cording to the n e w principle must not result
natural phenomena, s u c h as w i n d forces.
marine and nuclear engineering w a s studied. in something significantly different from
T h e information obtained on nuclear practice the end result of the old code.
Characteristic strength and materials w a s scanty and did not indicate any methods
testing: w h i c h were more rational than current
Acknowledgement
T h e 'characteristic' value of the strength of a structural practice. Aeronautical engineering
material is defined in British and C E B prac- uses probability theory extensively to predict Figs 2, 3 and 4 are reprinted from :
tice as being the one attained or exceeded design loads but has to apply severe modifi- C I R I A Report 6 3 , Rationalisation
by 9 5 % of a theoretically infinitely large cation factors to make the results compatible of safety and serviceability factors
4 number of tests, and there are statistical w i t h the safety records of previous s u c c e s - in structural c o d e s 1 9 7 6 .
Runnymede Bridge T h e L u t y e n s bridge w a s designed for six lanes
of traffic and t w o f o o t w a y s . T h e M 2 5 is n o w
possibilities. T h e modelscope w a s a great
help because it a l l o w e d u s to get the v i e w -
to cross the T h a m e s and requires four lanes point of a s c a l e - s i z e d m a n . W e decided to try
Fig. 2
L u t y e n s ' bridge
( P h o t o : R. B e n a i m )
Fig. 3
Longitudinal section through L u t y e n s ' bridge
3T
LT
u u u u jrrrrmr' mnnnnr
The superstructure w a s detailed so that it force for sliding w a s produced by hydraulic Credits
c o u l d either be constructed in situ on false- j a c k s pushing between the frame and nuts on
Client:
w o r k (on piles in the river) or by casting the Dividag bars or, in some c a s e s , using strands
frames on the banks and sliding them to their and automatically gripping j a w s on the j a c k s . Department of Transport
final positions. T h e bridge w a s built by W h e n the t w o half-frames of e a c h pair were South Eastern Road Construction Unit
Fairclough w h o decided to use the sliding finally positioned there w a s a 2 m gap Road design:
method. between them. T h e s e c o n d stage cables were
South Eastern Road Construction Unit
The contractor had t w o sets of forms, one for placed, the gap concreted and the s e c o n d
Surrey S u b Unit
e a c h side of the river, so he got four uses of stage stressing took place. T h e top member
them. T h e form and falsework were arranged of each frame had sockets cast into the sides, Bridge design:
so that after casting and the first stage of and rails w e r e fixed to these w h i c h carried the Ove Arup & Partners, Civil Engineering
stressing, the units could be j a c k e d clear of the travelling forms for the deck. W h e n the deck Division w i t h Arup A s s o c i a t e s as consulting
soffit shutter and slid s i d e w a y s out of it on had been concreted, the third stage cables architects
P T F E coated skids sliding on tracks w h i c h could be threaded and stressed. T h e contractor
chose to use the B B R V 5 5 - w i r e s y s t e m , so the Contractor:
consisted of a thin layer of stainless steel fixed
wires forming those cables w h i c h w e r e Fairclough Civil Engineering ( S o u t h e r n ) L t d .
to mild steel plates on a concrete beam
supported by piles. After the s i d e w a y s move, threaded had to be button-headed on site.
L u t y e n s ' bridge w a s designed in c o n c e p t by
the unit w a s j a c k e d up and the skids and At the time of writing, w o r k on deck finishes
him w i t h Mr. Fitzsimons as engineer. T h e
track rearranged so that it could be slid and parapets is going on. W h e n our bridge is
w o r k s design w a s carried out by C . W . G l o v e r
forward to the river bank, again jacked and ready, traffic will be diverted onto it and w o r k
& Partners, consulting engineers a n d Mr.
slid s i d e w a y s to its final position. T h e motive on strengthening L u t y e n s ' bridge c a n start.
George Stewart, consulting architect.
Fig. 4
Longitudinal section and cross-section of
Expansion |Oint - \
— A r u p s ' bridge
, 1 2 561 S H W M
Fig. 5
_ 9 290 River bed -Bearings AHUVMYI Model prepared for submission to the R o y a l
Fine Art C o m m i s s i o n . ( P h o t o : Henk S n o c k )
1200 dia bored piles - London Clay
Fig. 6
AA A;! 000
Diagram of sliding
Longitudinal Section
Fig. 7
V i e w from S o u t h bank
( P h o t o : Handford Photography)
3000 • 2500_ 3300 __yaries^
M 25 A 30 Fig. 8
The deck shuttering is carried on rails
Ewsting
-5 Uo o OO OO oo
4 bolted to the sides of the frames
( P h o t o : Kodak Vision)
bridge
Fig. 9
Precast paving
' slabs
Bearings access
chambers
Aerial v i e w looking north
( P h o t o : Milligan)
tl C 0 0 T T
5m
F i g . 10
HI. u uu Lj a u
General v i e w of n e w bridge
( P h o t o : Harry S o w d e n )
Section A A
4 A 5T
1
w
During construction
A -
5**
Casting area
" 'T£ II
Section A - A
Thames •
6 A
Mttflfl
9 A
s
Consultation with
Consultation
engineers
Send letter of
Finishes Parapets acceptance,
press release,
Preliminary Notice of inform unsuccessful
Appoint report probable tenderers, etc.
Oct 1971 completed delay
architects
•
ssue
Appoint DUbllC
engineers construct
notice Construction
Degins
Preliminary design
I
0 D A J A O D J A 0 J A O D A J A O J A 0 D F A J A
R u n n y m e d e Bridge preconstruction
graph s h o w i n g cumulative staff hours
w o r k e d with time ( k e y events arrowed)
A Tender
Draft
documents
submitted
Draft technical
approval submitted
Public construction
Preliminary
report
/
/
Time
Runnymede Bridge
Method study diagrams by Greg A d a m i w
There is an interesting sidelight on our w o r k on had t w o of the students in February 1 9 7 9 and diagram s h o w i n g the total number of man
R u n n y m e d e Bridge. Lancaster University runs one of them, Greg A d a m i w , studied our hours Arup staff booked to the project plotted
a post-graduate course in Civil Engineering method of working on the R u n n y m e d e against time. T h e s e diagrams are reproduced
Production Studies. Part of it involves the Bridge project, talking to people and studying here. T h e y s h o w quite clearly the consider-
students in spending t w o w e e k s at each of a files, time sheets, operating plans and other able gap between project design and w o r k s
number of different organizations investigat- documents. Greg's very interesting report design w h i c h has been a feature of many of
8 ing some aspect of the running of jobs. A r u p s included a precedence diagram and a our h i g h w a y and bridge jobs.
The south abutment Bridge deck
Fill on heel
at Kessock Bridge, load (maximum)
225kNm included in
deadload of
Scotland abutment
Ken Cole
INTRODUCTION
Lateral force
T h e Kessock Bridge w h e n completed will of surcharge
span the Beauly Firth at Inverness, S c o t l a n d . -47kNm
A s s h o w n in F i g . 2, the abutment to the Deadload
Lateral soil force
southern approach viaduct retains a selected 1573kN/m
( K a = 0.3)
granular fill embankment some 1 2 m high, 524kN/m
and supports one end of the first 6 4 m span.
T h e bearings of the viaduct are designed to
transmit vertical load only, longitudinal forces
being absorbed in the piers and at the
northern abutment.
DESIGN OF FOUNDATIONS
Soil conditions Pile reactions vary
maximum 590 kN/m
T h e great depth of alluvial deposits at the site
have influenced the choice of f o u n d a t i o n s ;
a borehole for a pier adjacent to the navigation
channel reached 9 5 m below bed level, and
a borehole 1 km a w a y reached 8 9 m below Abutment foundations Fig.1
ground level, both encountering only alluvial Conventional analysis of the southern abut- Loading diagram of forces on abutment
deposits. T h e alluvial deposits increase in ment foundation indicated that three r o w s ( n o n - s e i s m i c loads)
density with depth and pad foundations have of piles raked at 1 in 4, and a rear row of
been adopted where maximum bearing vertical piles w e r e required to provide
pressures c a n be kept economically to within adequate support for the loads s h o w n in F i g . 1 .
2 5 0 k P a . W h e r e bearing pressures e x c e e d this, T h e driving record of piles is given in Fig. 2 ;
or the depth of construction below water test loading of a vertical pile gave 7 m m
exceeds 1 0 . 5 m , steel H-section bearing piles settlement at the design workrng load of Fig. 2
have been driven into the alluvial deposits. 1600kN. Location and general details
1 052m
m 2 A 64m , 72m 80m 80m { 72m ; 5 6-lm
Embankment
constructed
Longitudinal elevation of Kessock Bridge during previous
contract
StudY Volume A
Volume selected
4m granular fi
StudX
Hammer B S P B 2 5
Rated energy 67kNm
Gravel &
silty shelly clay Studs X & Y
on centreline
Dense sand
Gravel &
sand Plan of abutment
-36m Dense silty sand
(Bridge deck removed)
Section on Penetration
centreline record of piles
of road Dense fine sand
with layers of
silty sandy clay
MOVEMENT OF THE FOUNDATIONS
Table 1
A n a l y s i s treating only f o r c e s on S A F E finite element input data of material parameters. All strength and modulus properties in
abutment MN/m . 2
Reference
80
S I M P S O N , B., O ' R I O R D A N , N. J . , and
C R O F T , D. D. A computer model for the
analysis of ground movements in L o n d o n
Clay, Geotechnique, 29 ( 2 ) , pp. 1 4 9 - 1 7 5 ,
1979.
Design and
construction of the
Lukasrand
Microwave Tower,
Pretoria
Cliff McMillan
Architects:
South Africa Public W o r k s Department,
Architecture Department
Introduction
In 1 9 7 3 the Public W o r k s Department
appointed Ove Arup and Partners as consult-
ing civil and structural engineers for the
design, documentation and supervision of a
n e w m i c r o w a v e tower at Lukasrand, Pretoria.
Initial design meetings were held immediately
to obtain the brief from the user client, the
Department of Posts & Telegraphs. T h i s
included the f o l l o w i n g main requirements: Fig.1 A Fig.2T
(a) A s an important link in South A f r i c a ' s Alternative forms considered General arrangement plan and elevation
m i c r o w a v e telecommunications s y s t e m , defining levels and key dimensions
the tower mainly serves a technical
function. Functional requirements in-
clude the provision of three antenna 176 950
platforms at the top of the concrete Steel
portion of the tower, with equipment mast
and technical rooms immediately below
them and a steel mast on top. LEVEL HEIGHT
N°
(b) B e c a u s e of the dominant location of the
tower in relation to Pretoria's skyline and 18 156 950
Radio
the numerous important buildings in the 16A
level
vicinity, particularly the U N I S A c a m p u s 16 149 250 SECTION 1-1
nearby on the same ridge, the tower had
to be an architectural statement of
quality appropriate for the capital city.
(c) There w a s to be public access to a
v i e w i n g platform but this should not
interfere with the technical functioning 11 A
of the tower. Restaurant facilities w e r e Technical
not required. level
V*
(d) There w a s to be a t w o - l e v e l building
serving the tower at the base, w i t h 112 900
related roads, parking, stormwater drains
and other civil engineering services.
(e) T h e height of the tower w a s limited by
considerations relating to the flight path SECTION 2-2
to Waterkloof Airport.
W o r k c o m m e n c e d immediately on the design, Public
r:iO
but in 1 9 7 5 the project w a s delayed for nearly observation
6A
t w o years due to lack of available funds and level
the general economic climate prevailing. 79 300
Work w a s h o w e v e r resumed in March 1 9 7 7 ,
enabling construction of the tower to start
t o w a r d s the end of 1 9 7 7 w i t h a target \
Design concept
The design c o n c e p t evolved through very
close collaboration between the P W D A r c h i -
tectural Department and the consulting
engineers. S i x different alternatives providing
the s p a c e requirements called for in the brief,
w e r e finally developed and c h e c k e d for
SECTION 3-3
n
structural stability and cost. S m a l l - s c a l e
models were made so that their aesthetic
merits could be assessed ( F i g . 1 ) .
0
These were: SECTION 5- 5
•'
(a) A circular cylindrical tower with a
circular multi-level turret on top
(b) A rectangular shaft with rectangular
platforms
SECTION 4-4
(c) A cruciform-shaped shaft with
(d)
octagonal platforms
Four separate circular shafts, one in the
0 000
v m-m
middle and three spaced at 1 2 0 ° around
( the perimeter, with circular platforms
(e) A configuration comprising four separate
rectangular shafts arranged in a c r u c i - Fig. 3 4
form pattern w i t h rectangular platforms S p a c e frame configuration
(t) A three-cornered 'star - s h a p e d shaft
(g) A configuration comprising a central
hexagonal shaft and three rectangular
shafts located at the a p e x e s of an Fig.4T
equilateral triangle, with hexagonal W i n d orientations and strain gauge positions
platforms.
T h e simplest and cheapest solution from a
Medium
structural and construction viewpoint w a s the
circular shaft w i t h circular platforms. There
were valid aesthetic reservations about this
solution for a number of reasons. T h e tower is
not very tall, being about 1 5 7 m to the top
of the concrete portion and 187 m to the top
of the steel mast. T h e functional space
requirements for lifts, staircase and ducts North
dictate the size of shaft, making it relatively Low ^ S t r a i n gauge
large in relation to its height and thereby positions
making it impossible to achieve the visual
appearance of a tall slender structure. More
important, the form did not relate w e l l to the members and 84 joints and w a s analyzed for
surrounding buildings or topography and various load cases, including many different
w o u l d not have created a distinctive a r c h i - w i n d directions, using our i n - h o u s e G A 1 8 / 3 0
tectural statement for Pretoria. computer. T h e frame analysis w a s also used
The notion of separating the four shafts arose during the conceptual design stage for a s s e s -
from the functional requirements. Each shaft sing the required stiffness and strength of w a l l
serves a separate function, namely three beams and for determining the natural
separate lift shafts plus the central core to frequency of vibration for the w i n d tests using
accommodate the staircase and service ducts the R a y l e i g h - R e i t z method.
for cables, ventilation, plumbing and other C P 1 1 0 w a s used as the basis for design and
services. Moreover the brief called for load combinations.
separation between the a c c e s s to the public
The main cantilever platforms were analyzed
spaces and the technical areas. At the same
elastically using quadrilateral finite elements
time it w a s decided that the public v i e w i n g
with the program O V E F I N E to determine the
1
various w i n d directions.
T h e s e results are also s h o w n in Fig. 5. T h e
0,7
centroid of the w i n d force w a s found to be
at about 7 9 m above ground level for all
w i n d directions.
For one particular w i n d direction ( 0 = 3 0 ° ) LEGEND
0,6
noticeable oscillation of the model occurred / / Most probable rang* of Cp
w i t h i n a small range of model w i n d velocity Cp determined with a wind tunnel balance (without mast)
around 1 3 . 4 m / s e c (approximately 8 6 k m / h r Weighted average Cp = 0,82.
full scale at the height from w h i c h the o s c i l l a -
tions w e r e found to emanate or 5 8 k m / h r at 4-
30 60 120 150 180 210 24 0 270 300 330 360
10 m reference height).
T h e amplitude of these oscillations w a s Wind direction 8*
halved for w i n d s p e e d 5 % higher or lower than
this value, and no oscillations w e r e evident Fig. 5 A
for w i n d directions other than 5 ° above or Variation of w i n d force
below 0 = 3 0 ° . T h e oscillations w e r e approxi- co-efficient with
mately a c r o s s - w i n d and had a frequency of w i n d direction
3 0 . 3 Hz w i t h an amplitude w h i c h varied with
time. Their cause w a s found to be regular I5tm
vortex shedding from the portion of the tower
above the public v i e w i n g gallery and below
A
the underside of Level 9. It w a s found these
oscillations could be controlled by the
introduction of aerodynamic fins within this
portion of the model.
H o w e v e r , in v i e w of the following it w a s \
decided that no s u c h precautions w e r e
necessary:
(a) T h e frequency of occurrence of the
\
disturbing w i n d velocity and direction is
less than once in 10 years.
(b) T h e m a x i m u m resulting acceleration on — 68m
the tower w o u l d be 0 . 8 2 % g, w h e r e a s
1 % g is considered to be the limit of
\
s
acceptability and 1.5% g disturbing.
(c) T h e amplitudes measured w e r e w e l l
w i t h i n the acceptable limits for the
structure. \\,\
No other oscillations w e r e detected up to a \\
N
m a x i m u m test speed equivalent to a full \
scale w i n d of 1 4 4 km/hr.
Construction
A number of special construction problems
existed, n a m e l y :
(a) T h e construction of the raft foundation.
(b) T h e method of construction of the i .1
l
the client adopted our recommended pro-
cedure of pre-qualification of tenderers.
In this w a y a short-list of invited tenderers,
fully qualified to handle the project and 1
A
horizontally-layered pours.
The m a x i m u m depth of pour w a s 1.5 m.
Heavy reinforcement only occurred in the
bottom and top pours and could be fixed
only w h e n required, thereby avoiding the
need for e x c e s s i v e support for the top rein- Fig. 7
forcement. E a c h section w a s protected w i t h The partially completed tower s h o w i n g the sliding platform
polythene sheets for curing after casting.
Precautions w e r e taken w i t h the mix design
to minimize the heat of hydration by using a
5 0 / 5 0 combination of cement and slag and temporary c o l u m n s were cast around the The heavy w a l l - b e a m reinforcement w a s
large 4 0 mm aggregate to reduce the water j a c k i n g rods to give them the required placed prior to sliding, it being possible to fix
demand of the mix. Temperatures w e r e support). T h e sliding platform consisted of a maximum height of only about 9 0 0 mm at a
measured by means of thermo-couples three l e v e l s ; namely, the shutter level, time due to the interference of the j a c k i n g
through the depth of the raft after casting and finishing level and the curing c o m p o u n d frames. T h i s portion w a s then slid before
differential temperatures remained within application level, and w a s braced to ensure fixing on the next could proceed. During this
acceptable limits. rigidity during sliding. T h e sliding shutter stop-start procedure for sliding the w a l l -
incorporated sections w h i c h linked the lift beams, and in particular the 8 m deep beam
shafts and w e r e used in sliding the w a l l between levels 5 and 6 w h i c h took a total of
Sliding form work beams. 2 2 5 hours, care had to be taken w i t h the
Before c o m m e n c e m e n t of the slide, t w o small concrete preparation at each stop to avoid
The contractor proposed a sliding form of
test slides were conducted using different blemishes at the construction joints.
construction for all the vertical elements
including the w a l l - b e a m s . T h e procedure w a s concrete mixes, and as a result the most Where necessary, s c r e w couplers were used to
to slide continuously to the underside of suitable mix satisfying both slidability and c o n n e c t the main reinforcement in the slid
each w a l l - b e a m , at w h i c h stage a steel soffit finish w a s c h o s e n . concrete portion to the beams and slabs to be
girder w a s installed between the shafts and In early d i s c u s s i o n s with the contractor it w a s constructed later. T h i s again meant a
fixed by means of welding to plates cast into decided to use reinforcement c a g e s in the s l o w i n g d o w n of the sliding speed and in
the w a l l s . T h e s e girders formed the soffit shafts tied together with the lighter horizontal some cases a stop, and as a result special care
of the w a l l - b e a m s and supported jacking reinforcement. T h e height to w h i c h horizontal w a s necessary with the finishing.
rods to enable the w a l l - b e a m s to be slid reinforcement could be fixed w a s dictated by The alignment of the slide w a s controlled
concurrently w i t h the shafts after making the j a c k i n g frames w h i c h span the shutter. by means of optical plummets set in the
minor c h a n g e s to the shutter ( F i g . 7 ) . The c a g e s were staggered vertically to enable shaft corners at ground level. Readings
T o a c h i e v e the required high standard of the reinforcement to be placed in a c o n - were taken on a target on the underside of the
finish on the vertical elements a steel shutter tinuous sequence thereby avoiding a bottle- sliding platform. External c h e c k s were carried
w a s used w i t h j a c k i n g rods positioned to neck in the fixing operations. out using a s i n g l e - s e c o n d theodolite set up
miss the openings in the shafts. (Where During the sliding of the deep w a l l - b e a m s it over beacons near the base of the tower. In
jacking rods had to go through openings. w a s more difficult to control the surface finish. the later stages a laser beam w a s also used, 1 5
but this did not prove as s u c c e s s f u l as the 1
1
within 5 0 mm, but at one stage a deviation
of nearly 1 0 0 mm w a s detected on the
northern shaft. T h i s w a s gradually corrected
and is not visible and does not impair the
performance of the lift.
Fig. 8 A
Finishing of the concrete surface w a s done
The sliding platform
on the s e c o n d level of the sliding platform.
s h o w i n g girders,
Under normal sliding conditions the concrete
emerged from the underside of the sliding hangers, precast
forms relatively soft' (six hours o l d ) . T h e slabs and
surface w a s then rubbed d o w n using a reinforcement
w o o d e n float and brushed vertically to give it
an even appearance. After a stop in the sliding, i
the first concrete to emerge from the forms
w a s hard,-and to get an equivalent finish the
\
surface w a s first rubbed w i t h carborundum
stones and then lightly brushed w i t h a grout
made by sieving the coarse aggregate out of
the concrete used in the slide.
Fig. 9 •
Due to the difficulties involved in getting
Ground leve
uniform distribution of water for curing, and
off-shutter concrete
the possibility of freezing during the winter
months w h e n the majority of sliding took
place, water spray curing w a s not used.
Instead, a resin-based curing compound
between panels w e r e sealed using a sealing Off-shutter concrete
(Cormix CM 90) w a s sprayed onto the c o n -
cord and grout. T h e reinforcement w a s fixed on the l o w - r i s e building
crete by hand from the lowest level of
also using the steel cantilever s y s t e m for The finish required for the l o w - r i s e building
the sliding platform. During the early stages
support and the s t o p - e n d s w e r e positioned at ground level w a s to express the grain
of sliding, the spray equipment w a s not
before casting the concrete. T h e s t o p - e n d s pattern of s a w n timber boards on the
adequate to ensure e v e n distribution of the
w e r e located so as to allow the hangers to be surface. T o achieve this, tongued-and-
c o m p o u n d and over-application occurred in
re-used. grooved boards w e r e sandblasted to e n h a n c e
certain areas, leaving y e l l o w marks. T h e s e
have almost entirely disappeared w i t h time. O n c e the concrete had reached the required the grain pattern and then sealed. J o i n t s
strength, the hangers w e r e loosened and the w e r e sealed by means of compriband strips
w h o l e system moved out using the n e w against the timber m o c k - m a s o n joints.
Cantilever platforms concrete for support. T h e next row of precast The design mix for the off-shutter concrete
Detailed d i s c u s s i o n s w e r e held w i t h the panels were then hung and the process w a s developed in consultation w i t h P C I .
contractor on alternative proposals for the repeated. Strict site controls w e r e set up to monitor the
construction of the main cantilever platforms T o finish the edge strip, steel shutters w e r e stockpiling and use of the various mix
at levels 6 and 9 and w e w e r e appointed to supported from the cantilever s y s t e m . T h e constituents.
design the temporary w o r k s on behalf of the same system w a s used for both levels 6 and The details of the formwork for e a c h panel
contractor. 9, there being four r o w s of panels and the edge w e r e d r a w n up by the contractor and s u b -
T h e final solution adopted w a s a launching strip at Level 6 and t w o r o w s of panels and mitted for approval. T o gain a s many r e - u s e s
system using precast concrete panels approxi- the edge strip at Level 9. T h e initial in situ from e a c h form a s possible, the w o o d e n
mately 1.5 m square and 1 0 0 mm thick a s a n n u l u s w a s more difficult to construct at m o c k - m a s o n joints w e r e made movable
permanent soffit shutter panels. T h e pattern of Level 9 because of the a b s e n c e of a shaft on on the form. This w a s a c h i e v e d by the use
joints between panels w a s detailed to meet the one side. T h i s w a s replaced by a steel of compressible sealing strips to seal it
architects' requirements. T h e slab at Level 9 is cantilever bracket in that position. against the 'rough' timber grain. T h i s meant
technically the most difficult, being supported Due to the critical nature of the hanging that, w i t h i n the restriction of the board
unsymmetrically by the central core and the details, a f u l l - s c a l e load test w a s carried out on pattern, one form could be used for any size of
t w o remaining lift shafts at that level and one of these precast panels at the S A B S . T h e panel.
cantilevering s o m e 8 m beyond the central girders, hangers, precast slabs and rein- All construction joints had to fall on mock-
core. ( S e e F i g . 2 section 2 - 2 ) . It tapers from forcement are s h o w n in Fig. 8. mason joints and to prevent grout leakage the
1.5 m deep at the core to 4 5 0 mm at the edge A n interesting facet w a s the detail developed forms w e r e sealed onto existing concrete
w h e r e it supports the c o l u m n s carrying the for the stop-end between pours. This using a compressible sealing strip on the edge
technical floors and roof above. consisted of a lightweight frame covered w i t h of the completed concrete. All details of
A concrete a n n u l u s about 1.5 m deep w a s e x p a n d e d metal, w h i c h enabled the heavy ferrule holes, expressed joints, colour of
first cast around the shafts using conventional cantilever reinforcement to be placed simply concrete, concrete finish, etc. w e r e resolved
shuttering supported on steel brackets off the by cutting holes through it w h e r e required. between the architect and the contractor
vertical shafts. Radial structural steel c a n t i - A certain amount of shutter oil w a s left on the priorto starting construction. ( F i g . 9 ) .
lever beams w e r e then attached above this precast panels and some grout had leaked T o ensure that the required quality of finish
concrete and supported a series of trans- from the joints. It w a s therefore necessary to w o u l d be a c h i e v e d , a number of sample
verse beams at their extremities. T h e precast clean the underside of the slabs after c o n - panels w e r e prepared prior to c o m m e n c i n g
soffit panels w e r e supported on the c o m - struction, using a lightweight structural steel construction and compared w i t h a test panel
pleted concrete on the inside and hung by platform hung under the slab. After this w h i c h had been produced prior to tendering
adjustable hangers, from the transverse treatment a very satisfactory soffit finish w a s and w a s specified as representing the required
16 beams on their extreme edge. T h e joints achieved. quality.
Fig.10
T o w e r during construction
Window walls
T h e w i n d o w w a l l s w h i c h occur between
Levels 6 a and 6, 9 and 1 1 a and 16 and 1 6 a .
consist of a series of structural steel mullions
hung from the upper levels and supported
horizontally at e a c h level, into w h i c h the
w i n d o w frame is fixed so that all glazing is
done from the inside of the building. A n
additional feature is the use of single glazing
and external w a l k w a y s , enabling the glazing
to be cleaned from the outside as w e l l as the
inside of the building and thereby eliminating
expensive pivoting w i n d o w frames.
Special care w a s taken with the specification
for this steelwork.
A m o c k - u p w a s made to study the details
and test the system against rain penetration.
A s a result of the tests, modifications had to
be made to meet the architectural require-
ments and still ensure adequate corrosion
protection. T h e specification adopted w a s
1 5 0 microns of bronze metal spray over 1 0 0
microns of zinc metal spray, sealed with a
clear acrylic sealer.
Credits:
Architects:
S o u t h Africa Public W o r k s Department,
Architectural Department
Quantity surveyors:
Southby, B i h l , Detert & Slade
Consulting electrical engineers:
Bidermann, Finn, Beekhuizen & Partners
Mechanical services:
South Africa Public W o r k s Department,
M e c h a n i c a l Department
Main contractors:
S t o c k s - F u t u r u s ( P t y ) Ltd. 2 - a consortium
between S t o c k s and S t o c k s ( P t y ) Ltd. and
Futurus.
T h e author is indebted to the many individuals
w h o formed part of the team w h i c h made this
project a s u c c e s s : firstly, to the relationship
w h i c h existed throughout between the
architect responsible, Mrs H. Lenddorff, the
consulting engineers, the P W D engineers
and the quantity surveyors, out of w h i c h it
w a s possible to create a tower of quality;
secondly, to those members of Ove A r u p &
Partners w h o participated tirelessly on the
project, particularly J a n Heynike for his
contribution to the development of the basic
concept and to the engineers w h o executed it,
Vincent Diesel, R o n Finkelstein, H. Scott and
the late Fred H o o g e n d i j k ; thirdly, to Mr V.
Chasteau for his contribution in advising on
and carrying out the w i n d tunnel t e s t i n g ;
finally to the contractors, and particularly
Dr. W. V a n c e , for the excellent relationship
w h i c h prevailed on site and the enthusiastic
manner in w h i c h challenging problems were
met and overcome.
Central Bank, Dublin
Architects: Stephenson & Associates
T h e A s s o c i a t i o n of Consulting Engineers of
Ireland has given its 1 9 8 0 Excellence A w a r d
for a structural project to the Central Bank,
Dame St. Frank Lydon of Ove Arup &
Partners Ireland, consulting engineers for the
project, accepted the A w a r d at the annual
dinner of the Association on 7 M a r c h .
T h e main building is an eight storey, 4 5 m
high structure and measures 4 5 m • 4 5 m on
plan. It is set towards the north of the site
overlooking a landscaped piazza fronting
onto D a m e Street. T w o ancillary buildings
are also incorporated on the site. One of these
a c c o m m o d a t e s the staff dining facilities. T h e
other is a reconstruction of a listed 19th
century building w h i c h stood on the site
prior to this development. There is a t w o
storey underground car park covering most
of the site to accommodate 1 3 0 cars.
T h e principal feature of the building design
of engineering interest is the superstructure
w h i c h is suspended from the top of t w o
reinforced concrete service cores. Other
aspects of the building construction, the use
of slip forming to construct the concrete
service cores and the lifting into position of
complete floors assembled at ground level,
are also unusual features.
— :
I T
•
w ,
Pi
i
:
o
£ •