You are on page 1of 20

THE ARUP JOURNAL

APRIL 1980
THEARUP
Vol. 15 No. 1 April 1980 Contents
Published by
Ove Arup Partnership
1 3 Fitzroy Street, London W1 P 6 B Q

JOURNAL Editor: Peter Hoggett


Art Editor: Desmond Wyeth F S I A D
Assistant Editor: David Brown

Safety f a c t o r s :
S o m e aspects of
C I R I A Research Project 2 2 3 ,
by P. B e c k m a n n
R u n n y m e a d Bridge, 5
by W . S m y t h
T h e south abutment 9
at Kessock Bridge,
by K. C o l e
Design and construction
at the Lukasrand m i c r o w a v e 12
tower, Pretoria,
by C . M c M i l l a n

Central B a n k , Dublin
18

Front and back covers : R u n n y m e d e Bridge across the T h a m e s alongside L u t y e n s ' Bridge ( P h o t o s : Harry S o w d e n )

Safety factors: The first code of practice in Europe to adopt


fully this principle w a s the Danish Foundation
gross errors in design and construction and
acts of G o d . ' ( T h e latter w a s , incidentally,

Some aspects of Code and generally the S c a n d i n a v i a n s


seemed to embrace this approach ahead of
defined during the research project as s o m e -
thing the designer c a n use as a n e x c u s e once.

CIRIA Research everybody else.


T h e European concrete committee introduced
W h e n s u c h an event has occurred, future
designs should foresee the possibility).

Project 223 the principle in their ' B l u e B o o k ' in the 1 9 6 0 s ,


and, as it is the unwritten rule for any code
Before getting alarmed about this loose talk
of risks, it is however useful to remind
committee never to be seen to reduce oneself of h o w small the risk of death from
Poul Beckmann substantially the factor of safety of anything, structural failure is, compared w i t h a lot of
risks w h i c h people quite happily accept, (see
they set themselves the aim to introduce
partial safety factors in s u c h a w a y that Table 1) The research project, w h i c h w a s led
W h a t is a safety factor ? In the old d a y s w h e n
structures designed on the basis of these and co-ordinated by Dr. A . R. Flint, included
strength of structural elements could usually
w o u l d provide substantially the same safety a lot of work on reliability theory by M. J .
only be quantified by testing, it w a s taken
as w h e n designed to existing 'permissible Baker of Imperial College, and later on a
to mean the ratio between the failure load
stress' codes. T h e y had certain statistical considerable amount of computer w o r k by
under test and the load the element w a s
information available w h i c h led them to S t a n Feneron of Building Design Partnership
required to carry in service.
deduce that the factors on the material sought aimed at demonstrating the reliability of a
W h e n engineering s c i e n c e had progressed number of structural elements designed to
s o far as to make engineers believe that to be in the order of 1.5 for the concrete
strength and 1.15 for the strength of the various codes as w e l l as some exercises
stresses could be accurately calculated, aimed at s h o w i n g h o w the n e w partial safety
reinforcement. T h e requirement for similar
the quantification of the safety of the factors, derived from probability theory, could
overall safety then led to a partial safety
structure took the form of stating that the be calibrated to give substantially the same
factor on the loads in the order of 1.5.
stresses under service load should be less than overall reliability as w o u l d result from present-
The result of this w a s , however, that the n e w
the relevant 'permissible working stress.' T h e day codes. Ian Potter of J e n k i n s & Potter pro-
method w a s no more rational in terms of the
permissible working stress w a s defined as the d u c e d a very interesting section on legal and
real safety provided than w a s the old, and
ultimate strength of the material ( w h e n economic aspects of safety.
hence it w a s thought that 'something ought
tested in a certain standardized w a y ) I w a s given the task of carrying out a 'state of
to be done about it.' T h e thought led to
divided by a 'factor of safety' w h i c h took C I R I A , in the beginning of 1 9 7 5 , sponsoring the art' investigation in current c o d e s and
a c c o u n t of the estimated c h a n c e of overload, a research project aimed at deriving a method regulations in the U K and abroad. T h i s in-
the variability of the strength of the materials by w h i c h more rational partial safety factors volved me in studying not only a large number
and past design tradition. could be calculated using the tool of the of British standards and codes of practice,
Experienced engineers were using this format 'reliability theory.' but also some of the German D I N Norms,
quite successfully for more than half a A m e r i c a n , French and Danish codes and some
century, but the new generation, brought up Reliability can in this connection be defined reports by the Nordic Committee for Building
to respect the w o r d s of codes of practice more as the reciprocal of the probability of failure, Regulations. T h e purpose of this study w a s to
than the advice of their elders and betters, ran and this will of course depend on both the demonstrate the extent to w h i c h the partial
into trouble because some codes had not loads and the structural resistance and the factors in these codes covered all the
stated explicitly that certain loads vary likely variability of both. variabilities they theoretically ought to a l l o w
independently of others and that variations Structural failures do of course mostly occur for.The C E B Bulletin III quotes the general
of materials strengths are of more significance for reasons other than those w h i c h can be design equation a s :
in some cases than in others. T h i s led to the connected directly with factors of safety a n d ,
development of 'the partial safety coefficient' whilst it is possible to calculate the risks
approach in w h i c h separate factors k n o w n T f x Effects of ( r , , D + T £ ^fi L Wi_)
due to a certain set of factors of safety, the 3 0

as partial coefficients' or partial safety actual risks of a failure of a structure designed < Resistance from — w h e r e W d is dead
factors, were allocated to the loads and to the to present day codes are about 10 times as big Ym
2 resistance of the structure. as the calculated risks, due to c a u s e s s u c h as load and W , covers live loads, w i n d loads,
etc. and fk is the characteristic material
strength. Fig.1 •
Both loads and strengths in this equation are Typical relationship
entered with a 'characteristic' value, that is between cost
a value that has a certain agreed probability and total probability
of occurring. of failure
Y is a reduction factor on material strength
m

w h i c h is intended to take account o f :


(7) Material strengths occasionally falling
below the specified characteristic value:
T h e probability of this depends mainly on
w o r k m a n s h i p a n d / o r quality control. Apart
fromthe masonry code, British c o d e s a n d drafts
don't allow for this. T h e probability of a failure
depends, everything else being equal, not only
on the characteristic strength of the material
but also on the variability of the strength. High Consequential losses
mean strength and high variability g i v e s
greater risk for the same characteristic
strength. T h e only mention of this is found in
the N K B document.
( 2 ) Possible differences between strength of
the material in the structure and that deter-
mined from control test specimens: Initial cost = f,
T h i s difference depends of the frequency of Fig. 2 •
sampling related to the consistency of 'Naive' application
production, and on the different behaviour of of partial safety
the standard sample in the testing machine factors to the 10 2
10" 3

from that of the bulk of the material in a real problem of


structure. For example, the British Standard Annual probability of failure
stability defeats
Concrete Cube is compacted and cured in a the object
completely different w a y from the concrete
in the structure.
It f o l l o w s that w h e n one is assessing an
existing structure on the basis of tests of
actual strengths of material in the structure
Y can be reduced.
m

{3) Possible weakness in the structural

I
material resulting from the construction
process:
T h i s is a function of w o r k m a n s h i p and super-
vision. British codes and drafts, except the
masonry draft w h i c h varies Y with m a n u f a c -
m

turing quality control and site testing, f o l l o w


A m e r i c a n and C a n a d i a n practice in having
invariant Y s.
m Scandinavian documents
grade their materials factors according to
frequency of a c c e p t a n c e testing and site F = /iA/ = n G cos * x (A
control.
(4) Possible inaccuracy in the assessment of N • G cos x
the resistance of a structural element resulting TfQ x l - Y\ G cos x x / i x i
G

from modelling errors:


It is impractical in a code of practice to
formulate simple calculations w h i c h will
predict accurately failure for the w h o l e range
of e a c h type of member that has to be covered
by the code. Hence, some a l l o w a n c e has to T a b l e 1 : Comparative annual probability of death per 1 0 0 0 0 persons
be made for the resulting errors. Grossly
erroneous assumptions can however not Hours Annual Approximate
be covered by partial safety factors. exposure/ risk/10,000 annual
annum persons risk/person
( 5 ) The effects of poor dimensional accuracy
in the finished structure on the resistance of a Mountaineering (International) 100 27 10- 2

section:
I n a c c u r a c i e s in construction are a function of Distant water trawling ( 1 9 5 8 - 7 2 ) 2900 17
w o r k m a n s h i p and hence supervision. T h e Air travel ( c r e w ) 1000 12 10- 3

British draft masonry code and some 1600 3.3


Coal mining
S c a n d i n a v i a n codes graduate mY accord-
ingly, but they are the only ones to do so. Car travel 400 2.2 2x10- 4

T h e effect of i n a c c u r a c i e s is greater for small Construction site 2200 1.7


members, so Y should vary ideally with size,
m
Air travel (passenger) 100 1.2
but no code seems to cater for this.
Home accidents (all persons) 5500 1.1 10- 4

Yf, is a multiplier applied to loads or im- Home accidents (able bodied) 5500 0.4 4x10- 5

posed deformations to take account of the Manufacturing 2000 0.4


possibility of loads exceeding their character-
STRUCTURAL FAILURE 5500 0.001 10- 7

istic value:
There is here the difficulty that very f e w types
of load are sufficiently recorded to establish All causes ( E n g l a n d and Wales, 1 9 6 0 - 1 9 6 2 )
a mean value, let alone a characteristic.
T h e codes tend to apply factors to nominal Male age 3 0 8700 13 10- 3

statutory' loads traditionally stipulated in


Female age 3 0 8700 11
regulations.
Male age 5 0 8700 73
Certain loads, e g : water pressures, are
calculable w i t h less uncertainty than usual Female age 5 0 8700 44
live loads and therefore deserve a lower value Male age 5 3 8700 100 10- 2

of Yf. S o m e codes a l l o w this, others don't.


* F is a multiplier
0 applied to load combina-
tions to take account of the reduced prob-
ability of all loads exceeding their character-
istic value simultaneously:
S o m e codes, e . g : the C a n a d i a n , apply f 2

this as a multiplier to the s u m of Yf, factored o


loads, others vary the T| for each type of II Y,on CP3I ve load
5
load depending on the combination.
T f is a multiplier
3 on load effects to take
account of errors in predicting load effects as a
result of neglecting dimensional inaccuracies:
to take account of non-linear behaviour
where there is a magnification of load effects:
Different accuracies of assumptions and , Ymlstee ) — on charade istic yield strenr. th
computations should qualify for c o r r e s p o n d -
J
ingly different values. In fact, the a c c u r a c y )
a s s u m e d in the implied Y f (as incorporated 1
3 > »-i
in the various c o d e s ' Y f - values) is n o w h e r e
defined. Non-linear behaviour is another \
matter and ought not to be introduced here,
Y T, (concrete) — o n a characteristic cube strength
as its effects vary so much from case to case.
Yn does not appear in the equation but is used 1 — on nominal c ead load
to modify Y | or 7m to take account of the
0 5 i 1• 1
nature of the structure and its behaviour and 4 6 8 10 12 14
the seriousness of attaining the limit state: Span(m)

Elements and structures that fail suddenly


should have a greater overall factor of safety
Fig. 3 A Fig.4T
than those w h i c h , due to their ductile behav-
Partial safety factors for Partial safety factors
iour give w a r n i n g of collapse. T h e G e r m a n ,
singly-reinforced beams—office loading for Grades 5 0 universal beams
A m e r i c a n and C a n a d i a n codes seem to give
the most explicit a l l o w a n c e for this d i s -
tinction. None deal with hidden ductile 3 a*.
structures, w h e r e the w a r n i n g signs cannot
be observed. ^""•s^^ Y f on CP3 office live loading

Structures, the collapse of w h i c h may kill or o


injure a large number of people, w o u l d s e e m II
to qualify for higher safety standards than a ? 2- Y i on CP3 retail premises (storage areas) live loading
lintel over a door in a transformer h o u s e . o
quired i

T h e S c a n d i n a v i a n drafts have three c l a s s e s


of structure according to the probability — * "
of death and injury and the level of damage
•* '
to property resulting in case of collapse.
T h e C a n a d i a n code has an importance S * ._ n n
" -..
o 1

factor' but only with t w o values, the lower nj

one applying to certain farm buildings.


Difficulties are sometimes experienced in
r 'm All in this zone /
Yt on nominal dead load
allocating some of the partial factors, notably
T f to one or the other side of the equation.
3 Yt on CP3 retails premises (sales areas) live loading
A factor of 1.4 to be applied to o w n w e i g h t is,
in the absence of any explanation, taken by ' i i i i i 1 1 1 r
0 2 4 6 8 10 12 14 16 18 20
some engineers as an insult to their standards
of calculation and the application in CP110 of Span(m)
1.4 and 1.0 to o w n weight in adjacent s p a n s ,
stretches the imagination of most of us. The
explanation lies of course in the positioning methods for calculating this value for a finite ful models. T h e same applies to shipbuilding.
number of tests. Whether these methods are (Probability theory w o u l d have predicted
of r .
adequate to deal with the testing frequency in B 7 0 7 s falling out of the skies by the dozens I)
f a

Certain earth stability problems t h r o w up even BS 4360: one tensile test for every 4 0 In both instances w e found little that could
w o r s e predicaments: in the classical slip tonnes, is another matter. (It corresponds to usefully be adopted in building and civil
circle calculation the calculated factor of one test for each km length of 1 2 i n . x 6 J i n . engineering design because ( a ) w e do not
safety remains constant regardless of the U B ( 3 0 5 x 1 6 5 x 4 0 ) or one test per 2\ have enough data on performance, failures
value c h o s e n for 7f. milesof4in. x 3in.angle (102 x 7 6 ) . ) and their c a u s e s , ( b ) w e do not have long
Apart from the partial safety factors there are enough production runs to be able to benefit
certain other parameters that affect the D e f i n i t i o n of f a i l u r e : from prototype testing, and ( c ) w e cannot
reliability of a structure: Mention w a s made earlier of modelling practically enforce a materials testing regime
errors in calculation of resistance of a struc- a n y w h e r e as stringent as the aircraft industry.
D e s i g n life tural member, but occasionally our traditional T h i s article only deals w i t h a small part of the
assumptions about the mode of failure lead entire research project w h i c h is fully described
T h e limit state philosophy usually includes
to errors not of plus or minus 1 5 % but several in C I R I A report no. 6 3 .
the phrase: the structure shall not become
hundred %. For instance, a beam spanning I hope that none of the hardworking chairmen
unfit for its intended use during its design
between heavy c o l u m n s at 1st floor level of a and members of code committees take any
life.' No code defines the design life and yet
multi-storey building will carry, in a catenary of the comments in the report or in this
it w o u l d seem essential to do so w h e n
action, a load several times that w h i c h will article as a criticism of their work. Having been
dealing with materials w i t h strengths w h i c h
collapse an identical beam at the top of the involved on the sidelines of one of those
reduce with time s u c h as timber or forces
building. committees, I k n o w that it is difficult just
w h i c h increase w i t h age such as drag on
marine structures due to barnacle growth. Design practice in allied fields of to make the transition from permissible
S o m e confusion also occasionally o c c u r s stresses to partial safety factors, especially
engineering :
between design life and return period of w h e n it is also stipulated that design a c -
T h e treatment of safety in aeronautical, cording to the n e w principle must not result
natural phenomena, s u c h as w i n d forces.
marine and nuclear engineering w a s studied. in something significantly different from
T h e information obtained on nuclear practice the end result of the old code.
Characteristic strength and materials w a s scanty and did not indicate any methods
testing: w h i c h were more rational than current
Acknowledgement
T h e 'characteristic' value of the strength of a structural practice. Aeronautical engineering
material is defined in British and C E B prac- uses probability theory extensively to predict Figs 2, 3 and 4 are reprinted from :
tice as being the one attained or exceeded design loads but has to apply severe modifi- C I R I A Report 6 3 , Rationalisation
by 9 5 % of a theoretically infinitely large cation factors to make the results compatible of safety and serviceability factors
4 number of tests, and there are statistical w i t h the safety records of previous s u c c e s - in structural c o d e s 1 9 7 6 .
Runnymede Bridge T h e L u t y e n s bridge w a s designed for six lanes
of traffic and t w o f o o t w a y s . T h e M 2 5 is n o w
possibilities. T h e modelscope w a s a great
help because it a l l o w e d u s to get the v i e w -
to cross the T h a m e s and requires four lanes point of a s c a l e - s i z e d m a n . W e decided to try

Bill Smyth and t w o hard shoulders in e a c h direction and


these are s a n d w i c h e d between t w o lanes of
four kinds of s c h e m e s . T h e first w a s extension
of the existing structure. T h i s w a s thoroughly
the A 3 0 and a footpath in e a c h direction, s o unsatisfactory and w e w e r e able to get the
T h e t w o bridges over the T h a m e s at R u n n y - that a bridge of t w i c e the original w i d t h is roads realigned slightly so a s to create a gap
mede allow an interesting comparison to be required. of 3 m b e t w e e n the older and newer bridges.
made. One w a s designed by an architect w i t h
There w e r e t w o major problems, one aesthetic T h e other groups of s c h e m e s w e r e :
help from an engineer and the other by
and one technical w h i c h f a c e d the design ( a ) Imitations of L u t y e n s ' bridge in appear-
engineers w i t h help from architects.
team of the Civil Engineering Division and ance or form only
Sir E d w i n Lutyens designed the first bridge
Arup A s s o c i a t e s . ( b ) Neutral bridges ( a very thin flat plate for
to carry the S t a i n e s B y p a s s . T h e c o n c e p t u a l
instance)
design w a s completed in 1 9 3 9 , he died in T h e first is w h a t kind of bridge c a n you
( c ) Other kinds of bridges w i t h curved soffits
1 9 4 4 and the bridge w a s built in 1 9 6 1 1 2 . It is possibly put alongside the L u t y e n s bridge?
w h i c h w o u l d be compatible w i t h the
basically a thin arch of white concrete The Department of the Environment ( n o w
existing bridge.
spanning 5 6 m over the river and thrusting Transport) had emphasized the importance
against cellular abutments founded in L o n d o n w h i c h they attached to the problem by T h e final result of the studies of structure,
clay. In the space b e t w e e n arch and d e c k appointing Arup A s s o c i a t e s directly as cost, and appearance w a s our project design
are steel trusses transferring the loads to the consulting architects. T h e s e c o n d is that w h i c h w a s completed in 1 9 7 2 .
arch and stiffening it. T h e bridge w a s L u t y e n s ' bridge is founded in L o n d o n clay T h e bridge deck is carried by four concrete
constructed by cantilevering the trusses out w h i c h is a bad material for founding an arch in. frames w h o s e soffits over the river lie on the
from the abutments, and suspending the S o m e spreading of the abutments w a s same surface as that of L u t y e n s ' river a r c h .
formwork for the arch from them. T h e a l l o w e d for in design but not e n o u g h to cope E a c h frame is made up of t w o balanced half-
spandrels are closed by brick panels w h i c h with ground movements c a u s e d by another frames w h i c h are c o n n e c t e d over the centre
c o n c e a l the trusses, the abutments are clad arch alongside, and w e had to be careful not of the river. T h e trapezoidal portal ring at the
w i t h brick and the parapets are Palladian to break its back. heart of e a c h half-frame is supported by t w o
balustrades of Portland stone. T h e r e are t w o sets of laminated rubber bearings and a simple
W e made a cardboard model of the L u t y e n s
t o w p a t h arches through the abutments a n d truss cantilevers out on e a c h side of the
bridge and w e used this in conjunction w i t h
these are lined w i t h brickwork and have portal. T h e top members of the frames are
rough models made from card and balsa to
Portland stone facings. prestressed and the other members simply
examine the visual effects of the various
reinforced. Foundation loads ( w h i c h are of
course predominantly vertical) are taken into
the clay by large diameter bored piles w i t h
underreams.
T h e bridge superstructure is made of w h i t e
concrete using Balidon aggregate and w h i t e
cement, and is b u s h - h a m m e r e d . A similar,
though less strong, concrete w a s used by
A r u p A s s o c i a t e s at S t . J o h n ' s College,
Oxford.

New bridge T h e bridge deck is made up to the correct


level w i t h lightweight concrete, w h i c h helps
to reduce the effect of the very onerous
current requirements for differential t e m p e r a -
ture, w i t h waterproofing and black top
surfacing. T h e parapets are precast w i t h the
same finish as the rest of the bridge.

A30Egham Bypass Fig.1


Site plan

Fig. 2
L u t y e n s ' bridge
( P h o t o : R. B e n a i m )

Fig. 3
Longitudinal section through L u t y e n s ' bridge

3T

LT
u u u u jrrrrmr' mnnnnr
The superstructure w a s detailed so that it force for sliding w a s produced by hydraulic Credits
c o u l d either be constructed in situ on false- j a c k s pushing between the frame and nuts on
Client:
w o r k (on piles in the river) or by casting the Dividag bars or, in some c a s e s , using strands
frames on the banks and sliding them to their and automatically gripping j a w s on the j a c k s . Department of Transport
final positions. T h e bridge w a s built by W h e n the t w o half-frames of e a c h pair were South Eastern Road Construction Unit
Fairclough w h o decided to use the sliding finally positioned there w a s a 2 m gap Road design:
method. between them. T h e s e c o n d stage cables were
South Eastern Road Construction Unit
The contractor had t w o sets of forms, one for placed, the gap concreted and the s e c o n d
Surrey S u b Unit
e a c h side of the river, so he got four uses of stage stressing took place. T h e top member
them. T h e form and falsework were arranged of each frame had sockets cast into the sides, Bridge design:
so that after casting and the first stage of and rails w e r e fixed to these w h i c h carried the Ove Arup & Partners, Civil Engineering
stressing, the units could be j a c k e d clear of the travelling forms for the deck. W h e n the deck Division w i t h Arup A s s o c i a t e s as consulting
soffit shutter and slid s i d e w a y s out of it on had been concreted, the third stage cables architects
P T F E coated skids sliding on tracks w h i c h could be threaded and stressed. T h e contractor
chose to use the B B R V 5 5 - w i r e s y s t e m , so the Contractor:
consisted of a thin layer of stainless steel fixed
wires forming those cables w h i c h w e r e Fairclough Civil Engineering ( S o u t h e r n ) L t d .
to mild steel plates on a concrete beam
supported by piles. After the s i d e w a y s move, threaded had to be button-headed on site.
L u t y e n s ' bridge w a s designed in c o n c e p t by
the unit w a s j a c k e d up and the skids and At the time of writing, w o r k on deck finishes
him w i t h Mr. Fitzsimons as engineer. T h e
track rearranged so that it could be slid and parapets is going on. W h e n our bridge is
w o r k s design w a s carried out by C . W . G l o v e r
forward to the river bank, again jacked and ready, traffic will be diverted onto it and w o r k
& Partners, consulting engineers a n d Mr.
slid s i d e w a y s to its final position. T h e motive on strengthening L u t y e n s ' bridge c a n start.
George Stewart, consulting architect.

Fig. 4
Longitudinal section and cross-section of
Expansion |Oint - \
— A r u p s ' bridge

, 1 2 561 S H W M
Fig. 5
_ 9 290 River bed -Bearings AHUVMYI Model prepared for submission to the R o y a l
Fine Art C o m m i s s i o n . ( P h o t o : Henk S n o c k )
1200 dia bored piles - London Clay

Fig. 6
AA A;! 000

Diagram of sliding
Longitudinal Section

Fig. 7
V i e w from S o u t h bank
( P h o t o : Handford Photography)
3000 • 2500_ 3300 __yaries^

M 25 A 30 Fig. 8
The deck shuttering is carried on rails
Ewsting
-5 Uo o OO OO oo
4 bolted to the sides of the frames
( P h o t o : Kodak Vision)
bridge

Fig. 9
Precast paving
' slabs
Bearings access
chambers
Aerial v i e w looking north
( P h o t o : Milligan)
tl C 0 0 T T
5m
F i g . 10
HI. u uu Lj a u
General v i e w of n e w bridge
( P h o t o : Harry S o w d e n )
Section A A

4 A 5T
1

w
During construction
A -
5**

Casting area

" 'T£ II

During sliding Pile cap

Section A - A

Thames •

Plan on slide path

6 A

Mttflfl

9 A

s
Consultation with
Consultation
engineers

Send letter of
Finishes Parapets acceptance,
press release,
Preliminary Notice of inform unsuccessful
Appoint report probable tenderers, etc.
Oct 1971 completed delay
architects

ssue
Appoint DUbllC
engineers construct
notice Construction
Degins
Preliminary design

Consider alternatives Request


Collect available information programme
Assess requirements: S E R C U Meet contractor
TWA Set start date. etc.
Gas Board
Appoint
checkers Check
calculations
Revised tech
approval

Simplified, time-scale precedence diagram


R u n n y m e d e Bridge preconstruction stages

I
0 D A J A O D J A 0 J A O D A J A O J A 0 D F A J A

1971 1972 1973 1974 1975 1976 1977

R u n n y m e d e Bridge preconstruction
graph s h o w i n g cumulative staff hours
w o r k e d with time ( k e y events arrowed)

A Tender

Draft
documents
submitted

Draft technical
approval submitted

Public construction

Preliminary
report
/
/

Time

Runnymede Bridge
Method study diagrams by Greg A d a m i w

There is an interesting sidelight on our w o r k on had t w o of the students in February 1 9 7 9 and diagram s h o w i n g the total number of man
R u n n y m e d e Bridge. Lancaster University runs one of them, Greg A d a m i w , studied our hours Arup staff booked to the project plotted
a post-graduate course in Civil Engineering method of working on the R u n n y m e d e against time. T h e s e diagrams are reproduced
Production Studies. Part of it involves the Bridge project, talking to people and studying here. T h e y s h o w quite clearly the consider-
students in spending t w o w e e k s at each of a files, time sheets, operating plans and other able gap between project design and w o r k s
number of different organizations investigat- documents. Greg's very interesting report design w h i c h has been a feature of many of
8 ing some aspect of the running of jobs. A r u p s included a precedence diagram and a our h i g h w a y and bridge jobs.
The south abutment Bridge deck
Fill on heel
at Kessock Bridge, load (maximum)
225kNm included in
deadload of

Scotland abutment

Ken Cole
INTRODUCTION
Lateral force
T h e Kessock Bridge w h e n completed will of surcharge
span the Beauly Firth at Inverness, S c o t l a n d . -47kNm
A s s h o w n in F i g . 2, the abutment to the Deadload
Lateral soil force
southern approach viaduct retains a selected 1573kN/m
( K a = 0.3)
granular fill embankment some 1 2 m high, 524kN/m
and supports one end of the first 6 4 m span.
T h e bearings of the viaduct are designed to
transmit vertical load only, longitudinal forces
being absorbed in the piers and at the
northern abutment.

DESIGN OF FOUNDATIONS
Soil conditions Pile reactions vary
maximum 590 kN/m
T h e great depth of alluvial deposits at the site
have influenced the choice of f o u n d a t i o n s ;
a borehole for a pier adjacent to the navigation
channel reached 9 5 m below bed level, and
a borehole 1 km a w a y reached 8 9 m below Abutment foundations Fig.1
ground level, both encountering only alluvial Conventional analysis of the southern abut- Loading diagram of forces on abutment
deposits. T h e alluvial deposits increase in ment foundation indicated that three r o w s ( n o n - s e i s m i c loads)
density with depth and pad foundations have of piles raked at 1 in 4, and a rear row of
been adopted where maximum bearing vertical piles w e r e required to provide
pressures c a n be kept economically to within adequate support for the loads s h o w n in F i g . 1 .
2 5 0 k P a . W h e r e bearing pressures e x c e e d this, T h e driving record of piles is given in Fig. 2 ;
or the depth of construction below water test loading of a vertical pile gave 7 m m
exceeds 1 0 . 5 m , steel H-section bearing piles settlement at the design workrng load of Fig. 2
have been driven into the alluvial deposits. 1600kN. Location and general details

1 052m
m 2 A 64m , 72m 80m 80m { 72m ; 5 6-lm

North abutment boulh abutment


2.5m M H W S

Embankment
constructed
Longitudinal elevation of Kessock Bridge during previous
contract

17.6m Finished road level Fill surface on 28.6.79 Fill surface


on 1.5.79 15.2m
Bridge deck
13.5m 14.3

StudY Volume A
Volume selected
4m granular fi
StudX

Original ground surface


WfJWkWSO*' 100 150
4 s
200 blows/

Hammer B S P B 2 5
Rated energy 67kNm

Universal bearing piles Medium dense Majority of


3 5 6 > 358 174kg/m sand gravel readings lie
Grade 5 0 B steel cobbles & within this
To B S 4 3 6 0 boulders envelope

Gravel &
silty shelly clay Studs X & Y
on centreline

Dense sand
Gravel &
sand Plan of abutment
-36m Dense silty sand
(Bridge deck removed)
Section on Penetration
centreline record of piles
of road Dense fine sand
with layers of
silty sandy clay
MOVEMENT OF THE FOUNDATIONS
Table 1
A n a l y s i s treating only f o r c e s on S A F E finite element input data of material parameters. All strength and modulus properties in
abutment MN/m . 2

A n a l y s i s of the movement of the abutment,


taking a c c o u n t of the forces s h o w n in Fig. 1 , Concrete
and treating the piled foundation as elastic Material Soil (All Piles Soils
springs, s h o w e d that abutment movements parameters (Analyses 3 & 4 ) analyses) (Analyses 3 & 5) (Analysis 5)
w o u l d tend to be d o w n w a r d s and forwards,
the base of the abutment moving some 4 0 m m Material number 1 2 3 4 5 6 7
t o w a r d s the north. H o w e v e r , it w a s evident
that the analysis of movement of the abutment Material type LE LE LE LE LE LE(s) LE(s)
could not be considered in isolation from the
ground movements that w o u l d be generated Drainage Drained Drained Drained Drained Drained Drained Drained
by the construction of the short length of
granular fill embankment between the already E, 50 30 30 000 50 50 50 30
placed embankment and the abutment. U,z 0.3 0.3 0.1 0.3 0.3 0.3 0.3
E 2
50 30 30 000 4 809 7 642 50 30
Loading sequence U12 0.3 0.3 0.1 0.3 0.3 0.3 0.3
T h e loading sequence used is s h o w n in Fig.4, G-I2 19.20 11.54 13 636 19.20 19.20 19.20 11.54
the construction process being simulated by CO 0 0 0 -14.036 0 0 0
four stages, A to D. T o c h e c k on the effect of c' — — — — — 0.017 0.017
the simplifying assumption that the embank- 0 ' — — — — — 0 0
ment load applied only a vertical load, Stage Z,
in w h i c h horizontal shear loads from the
embankment w e r e applied, w a s run in addition Note
to Stage B in A n a l y s i s 3 . LE linear elastic model
LE(s) linear elastic model w i t h strength limitation
A n a l y s e s of i n t e r a c t i o n o f s o i l a n d Drained e x c e s s pore water pressures assumed dissipated
structure E„E 2 principal Y o u n g ' s modulii in x, y plane, suffix 1 denoting horizontal (in p l a n e ) ,
A f i n i t e e l e m e n t p r o g r a m , S A F E . 1 incorporating 2 denoting vertical and 3 denoting horizontal (normal to plane) directions w h e n
facilities to take a c c o u n t of soil and structural oo = 0
material properties, w a s used to compute shear modulus between directions 1 and 2
ground movements and stresses in the anticlockwise inclination of direction 1 to horizontal (degrees)
structural elements. Previous computations cohesive resistance (limiting v a l u e )
using S A F E program, including modelling frictional resistance (limiting value)
of anchored retaining w a l l s , had s h o w n that
the program gave reasonably accurate predic-
tions of movements w h e n compared w i t h
Volume B Volume A
field measurements. Abutment loads applied as pressure
loads and shear loads to abutment base
A t w o - d i m e n s i o n a l finite element model of Fill loads applied as pressure loads
(Material 3 ) Nt
the abutment and the soil w a s established, A * i » + » . * * i
see Fig.3, and a series of analyses undertaken, \W///////M, f* 1 nl
m i
l rhnir<rniv\ fill

the a s s u m e d soil and structural material J T i d e range — J J jJJJ (Analysis3, S t a g e Z o n l y )


properties for A n a l y s e s 3, 4 and 5 being
s h o w n in T a b l e 1 .
Upper stratum
T h e soils w e r e given linear elastic properties (Material 1,6)
and a s s u m e d to be drained, since their rate Piles ^^^Ijljl
of consolidation w a s expected to be rapid.
T h e assumptions concerning the pile elements (Material4) llllll * (Material 5)
are stated in Fig. 5 ; for A n a l y s i s 4 the piles
w e r e a s s u m e d to be absent in order to
demonstrate the general validity of the
method. T h e main defect of the model w a s
that the pile elements had to be considered
as having the same unit depth' (of 1 m ) a s
Lower stratum
the soil and concrete elements, thus pro- (Material 2, 7 )
hibiting relative movement in the line of the
bridge between the piles and adjacent soil.

Computed and measured movements


The results of the computations of movement Boundary of mode
are presented in diagrammatic form in Fig. 5,
w i t h the measured results to date s h o w n on &
A n a l y s i s 3. Studs X and Y , on w h i c h level
readings have been made, are located on the
road centreline at the positions s h o w n in Fig. 3
Fig. 2. Site measurements of movement of Finite element model.
the abutment in the line of the road w e r e For properties of materials 1 to 7 see Table 1 Stage A
attempted, but, s h o w i n g little if any movement Build abutment 185
. i I
and being difficult to make with sufficient
'116
accuracy, they w e r e discontinued. The
abutment movements have therefore been Stage B
presented on the assumption that only Place volume A 185 25 5 5 230 230
vertical movement took place. embankment i
Fig.4 fill
116
Movements were time dependent Loading diagram for finite element model 25 40 45 38 20
T h e diagram giving settlement against time, St.iqe C Stage Z Add lateral shear from fill
Fig. 6, s h o w s that realization of full settlement Place Volume B 185 240 240 240 230 2 3 0
at e a c h stage of loading w a s delayed by embankment fill i > i .. * * 1 i l
material against the stem of the retaining w a l l
classical consolidation involving the dissi- 16 277
as the base took up the major part of its
pation of e x c e s s pore water pressures from
b a c k w a r d rotation during the placing of
the fine grained soils, complete dissipation Stage D
Volume A, see Fig. 5. In the event, the fill Place bridge 195 240 240 240 230 230
for e a c h stage taking about 6 months. T h e
surface w a s raised uniformly over the entire deck
specified sequence of embankment filling 44.
fill length from about 5m above datum to 13m y-Z
w a s that Volume A should be completely 281
above datum in one continuous lift, followed
placed in Stage B ( F i g . 4 ) before the placing nb All load and shears in kPa units
by further filling to road base level at 1 7 m
of Volume B w a s started in Stage C , the
above datum after a delay of t w o months.
10 object being to eliminate the pressure of fill
EFFECTOF MOVEMENTSON
STRUCTURE
Restraint on b a c k w a r d rotation
A s a c o n s e q u e n c e of following the described
s e q u e n c e of filling, the lateral pressure of
retained soil restrained the tendency of the
base to tilt b a c k w a r d s by developing the
bending strength of the connection between
stem and base, the measured average angular
rotation between the stem and base being
about 1 in 9 0 0 after the filling to 13m above Stud
datum. During the subsequent filling this 120
rotation increased to about 1 in 5 2 5 . It is
thought that the average vertical movements
Dates on which settlement
of base will have not been affected by the 160 readings were made
difference b e t w e e n the intended and the ') 17 January 1979
actual s e q u e n c e s of filling, but the b a c k - ii) 23 April 1979
w a r d tilt of the base may have been reduced. in) 18June1979
iv) 28 September 1979
v) 1 9 November 1979
S t i f f e n i n g e f f e c t of p i l e d f o u n d a t i o n
ANALYSIS 3 ANALYSIS 4 ANALYSIS 5
From Figs. 5 and 6, reasonably good cor-
Assumptions Assumptions Assumptions
relations are apparent between the predicted Pile elements have correct Pile elements deleted and Pile elements have correct
settlement from A n a l y s i s 3 and the actual axial stiffness, are replaced by soil. axial stiffness, are
settlement on 17 J a n u a r y 1 9 7 9 , w h e n the anisotropic and are connected anisotropic and connections to
to adjacent soil elements. adjacent soil elements have
loading w a s the abutment base and stem
shear strength limitation
( S t a g e A ) and on 1 8 J u n e 1 9 7 9 w h e n all cohesion - 170 kPa, f> = 0
loads except the bridge deck had been placed
and consolidation under those loads w a s
virtually complete ( S t a g e C ) . It is evident that
the piles moved together w i t h the surrounding
soil to give m u c h greater settlements than Fig. 5
could have been predicted from the results Computed and measured movements
of the pile test loading and considerations
of group a c t i o n ; the movements w e r e of the
same form but smaller than those that w o u l d Fig. 6
have occured if the foundation had not had Loading and settlement w i t h time
piles. T h e smaller actual b a c k w a r d tilt than
predicted by A n a l y s i s 5 indicates that the soil
adjacent to the rear r o w of piles did not move
differentially to the piles, and that shear
failure played little part in the overall be- Final fill level - 17.2m
Height of 20 100%
haviour. fillm completion „
"^onstrucrj^n
above of structure
datum 10 complete
Credits 50%
S Fill Level
T h e client is the Scottish Development
Department w h o kindly gave their consent to
the publication of this paper.
T h e contractor is a consortium of Cleveland
20
Bridge and Engineering Company and
Stud 'X
Redpath Dorman Long ( C o n t r a c t i n g ) Ltd.
T h e bridge w a s designed by Dr. Ing H. 40
Homberg in association w i t h C l e v e l a n d , and
the substructure by Trafalgar H o u s e Engineer- Settlement
ing S e r v i c e s in association w i t h R D L . mm
T h e joint engineers for the client are C r o u c h
and Hogg of G l a s g o w and Ove Arup and 20
Partners.
A c k n o w l e d g e m e n t is made of the dedication 40
of the site staff in obtaining the readings
w h i c h made possible this contribution.
6.)

Reference
80
S I M P S O N , B., O ' R I O R D A N , N. J . , and
C R O F T , D. D. A computer model for the
analysis of ground movements in L o n d o n
Clay, Geotechnique, 29 ( 2 ) , pp. 1 4 9 - 1 7 5 ,
1979.
Design and
construction of the
Lukasrand
Microwave Tower,
Pretoria
Cliff McMillan
Architects:
South Africa Public W o r k s Department,
Architecture Department

Introduction
In 1 9 7 3 the Public W o r k s Department
appointed Ove Arup and Partners as consult-
ing civil and structural engineers for the
design, documentation and supervision of a
n e w m i c r o w a v e tower at Lukasrand, Pretoria.
Initial design meetings were held immediately
to obtain the brief from the user client, the
Department of Posts & Telegraphs. T h i s
included the f o l l o w i n g main requirements: Fig.1 A Fig.2T
(a) A s an important link in South A f r i c a ' s Alternative forms considered General arrangement plan and elevation
m i c r o w a v e telecommunications s y s t e m , defining levels and key dimensions
the tower mainly serves a technical
function. Functional requirements in-
clude the provision of three antenna 176 950
platforms at the top of the concrete Steel
portion of the tower, with equipment mast
and technical rooms immediately below
them and a steel mast on top. LEVEL HEIGHT

(b) B e c a u s e of the dominant location of the
tower in relation to Pretoria's skyline and 18 156 950
Radio
the numerous important buildings in the 16A
level
vicinity, particularly the U N I S A c a m p u s 16 149 250 SECTION 1-1
nearby on the same ridge, the tower had
to be an architectural statement of
quality appropriate for the capital city.
(c) There w a s to be public access to a
v i e w i n g platform but this should not
interfere with the technical functioning 11 A
of the tower. Restaurant facilities w e r e Technical
not required. level

V*
(d) There w a s to be a t w o - l e v e l building
serving the tower at the base, w i t h 112 900
related roads, parking, stormwater drains
and other civil engineering services.
(e) T h e height of the tower w a s limited by
considerations relating to the flight path SECTION 2-2
to Waterkloof Airport.
W o r k c o m m e n c e d immediately on the design, Public

r:iO
but in 1 9 7 5 the project w a s delayed for nearly observation
6A
t w o years due to lack of available funds and level
the general economic climate prevailing. 79 300
Work w a s h o w e v e r resumed in March 1 9 7 7 ,
enabling construction of the tower to start
t o w a r d s the end of 1 9 7 7 w i t h a target \

completion date of the end of 1 9 7 9 . <

Design concept
The design c o n c e p t evolved through very
close collaboration between the P W D A r c h i -
tectural Department and the consulting
engineers. S i x different alternatives providing
the s p a c e requirements called for in the brief,
w e r e finally developed and c h e c k e d for
SECTION 3-3

n
structural stability and cost. S m a l l - s c a l e
models were made so that their aesthetic
merits could be assessed ( F i g . 1 ) .
0
These were: SECTION 5- 5
•'
(a) A circular cylindrical tower with a
circular multi-level turret on top
(b) A rectangular shaft with rectangular
platforms
SECTION 4-4
(c) A cruciform-shaped shaft with

(d)
octagonal platforms
Four separate circular shafts, one in the
0 000
v m-m
middle and three spaced at 1 2 0 ° around
( the perimeter, with circular platforms
(e) A configuration comprising four separate
rectangular shafts arranged in a c r u c i - Fig. 3 4
form pattern w i t h rectangular platforms S p a c e frame configuration
(t) A three-cornered 'star - s h a p e d shaft
(g) A configuration comprising a central
hexagonal shaft and three rectangular
shafts located at the a p e x e s of an Fig.4T
equilateral triangle, with hexagonal W i n d orientations and strain gauge positions
platforms.
T h e simplest and cheapest solution from a
Medium
structural and construction viewpoint w a s the
circular shaft w i t h circular platforms. There
were valid aesthetic reservations about this
solution for a number of reasons. T h e tower is
not very tall, being about 1 5 7 m to the top
of the concrete portion and 187 m to the top
of the steel mast. T h e functional space
requirements for lifts, staircase and ducts North
dictate the size of shaft, making it relatively Low ^ S t r a i n gauge
large in relation to its height and thereby positions
making it impossible to achieve the visual
appearance of a tall slender structure. More
important, the form did not relate w e l l to the members and 84 joints and w a s analyzed for
surrounding buildings or topography and various load cases, including many different
w o u l d not have created a distinctive a r c h i - w i n d directions, using our i n - h o u s e G A 1 8 / 3 0
tectural statement for Pretoria. computer. T h e frame analysis w a s also used
The notion of separating the four shafts arose during the conceptual design stage for a s s e s -
from the functional requirements. Each shaft sing the required stiffness and strength of w a l l
serves a separate function, namely three beams and for determining the natural
separate lift shafts plus the central core to frequency of vibration for the w i n d tests using
accommodate the staircase and service ducts the R a y l e i g h - R e i t z method.
for cables, ventilation, plumbing and other C P 1 1 0 w a s used as the basis for design and
services. Moreover the brief called for load combinations.
separation between the a c c e s s to the public
The main cantilever platforms were analyzed
spaces and the technical areas. At the same
elastically using quadrilateral finite elements
time it w a s decided that the public v i e w i n g
with the program O V E F I N E to determine the
1

platform could be a c c o m m o d a t e d well


magnitude and directions of the principal
below the technical platforms on the grounds
moments and to obtain the desirable arrange-
that this w o u l d provide an adequate v i e w
ment of reinforcement. The c h o s e n reinforce-
over Pretoria.
ment arrangement w a s then c h e c k e d by yield
A s a result of these factors it became feasible line analysis.
to stop off each of the lift shafts just above the
level served, thereby giving a more distinctive W i n d loading
unsymmetrical form to the tower. After due B e c a u s e of the tower's unusual shape,
consideration of all the factors involved, information on w i n d loading co-efficients
alternative ( g ) w a s c h o s e n . It w a s decided and structural response to w i n d could not be
to terminate each lift shaft just above the obtained from available s o u r c e s . It w a s
highest level it served, namely the public therefore decided to carry out w i n d tunnel
v i e w i n g platform, the technical service floors tests on an aeroelastic model of the structure
and the top respectively. T h e result is a so that the force co-efficients as w e l l as the
distinctive sculptural form w h i c h reflects the aerodynamic excitation could be investigated
functional requirements of its various for various w i n d directions. T h i s testing
elements, and is in harmony w i t h the pre- w a s carried out at the University of Pretoria,
dominantly linear appearance of the nearby under the direction of Mr. V. C h a s t e a u . 2

U N I S A buildings. A model scale of 1 :250 w a s c h o s e n so that the


For structural reasons the three outer shafts model w o u l d fit satisfactorily into the available
and the central core had to be inter-linked w i n d tunnel c r o s s - s e c t i o n of 1.3 m x 0.9 m.
at various levels to ensure shear transference T h e model w a s made out of 'jelugtong'
between the various vertical elements in w o o d . All external dimensions were to
resisting the horizontal w i n d loads and scale w h i l e the thicknesses of the concrete
eccentric vertical loads. This inter-connection in the shafts w e r e modelled as 1.25 times the
is provided by a series of w a l l - b e a m s and actual scaled thicknesses in order to give a
platforms at various levels w h i c h are inte- model stiffness w h i c h w o u l d lead to a
grated into the functional requirements and convenient model natural frequency and test
aesthetics of the tower. w i n d speed. Discreet metal masses were
Major horizontal cantilever platforms are introduced to model the mass distribution of
required at levels 6 and 9 ( F i g . 2 ) . Level 6 the tower correctly.
supports the public v i e w i n g platform and is a The f u l l - s c a l e natural frequency of oscillation
tapering hexagonal slab w h i c h supports the of the tower w a s determined from the
columns from the roof slab above on its computer s p a c e frame analysis to be 0.22 Hz
perimeter. Level 9 is a more complex structure, and the torsional frequency as 0.39 Hz.
being supported unsymmetrically on the The damping of the model should be the
central core and the t w o remaining lift shafts same as for the full-scale structure, and a value
at that level and cantilevering some 8 m of logarithmic decrement of 0.06 w a s
beyond the central core. It carries the three chosen as reasonable for good quality
floors and roof of the technical service uncracked concrete. T h e model w a s instru-
building on c o l u m n s supported on its mented with three strain gauges on each lift
perimeter. It is a concrete slab with a maximum shaft at ground level to measure the vertical
depth of 1.5 m tapering to 4 5 0 mm at the strains at various points on the shafts. From
perimeter. these strains the response of the structure for
the 12 different w i n d directions could be
Structural analysis
determined. T h e positions of the strain gauges
B e c a u s e of the unsymmetrical form of the
are s h o w n in F i g . 4.
structure and the importance of the interaction
between the vertical elements through the w a l l T h e natural frequencies of the model were
beams and platforms in resisting w i n d and measured by t w o independent methods. T h e
eccentric vertical loads, a s p a c e frame analysis bending oscillation frequency w a s found to
w a s necessary. T h e frame, ( F i g . 3 ) , had 1 8 6 vary between 2 5 Hz and 3 3 Hz depending on
1
the direction of oscillation. T h e torsional T w o alternative foundation solutions w e r e samples were not feasible because of the
oscillation frequency w a s approximately considered, namely a deep shaft under each of difficulty of sampling the weathered material
6 4 Hz. T h e logarithmic decrement for bending the main shafts and a raft foundation. T h e undisturbed. It w a s therefore decided to
oscillation w a s an average of 0 . 0 5 5 for all raft foundation w a s preferred on the grounds carry out d o w n - t h e - h o l e tests using a
directions. of its lower cost, shorter construction time pressure meter.
T h e results of the w i n d tunnel tests w e r e used and reduced construction risk. H o w e v e r there Four NX boreholes w e r e drilled to depths of
to a s s e s s the d y n a m i c response of the w a s concern about possible differential b e t w e e n 26.4 and 29.1 m. T h e y w e r e
tower to w i n d as w e l l as to determine the settlement and rotation of a raft because of the immediately filled with cement grout, left to
force c o - e f f i c i e n t s for the various w i n d weathered strata. Calculations based on the set overnight and then re-drilled the following
directions for use in the design. In addition, percentages of weathered material observed day. T h e pressure meter w a s a pneumatically
pressure measurements w e r e taken to deter- in the boreholes and on the a s s u m e d elastic operated instrument w i t h a 7 5 mm diameter
mine local w i n d pressures on elements of the modulus of 4 0 0 M P a for the weathered probe w h i c h w a s buried into the borehole.
tower s u c h as the w i n d o w w a l l panels at the material, indicated a total vertical elastic Tests w e r e carried out in the weathered
public v i e w i n g platform and technical levels. settlement of the order of 2 5 mm and negli- material only. Although the majority of the
T o obtain the equivalent drag and lift c o - gible consolidation settlement. tests failed due to breakages of the pressure
efficients from the test measurements w a s not Differential settlements arising from this and cells, the results obtained w e r e sufficient to
straightforward as they had to be derived from w i n d loading proved to be within acceptable confirm that the a s s u m e d elastic modulus w a s
six independent strain gauge readings for limits, the m a x i m u m calculated rotation being conservative and that the raft solution could
e a c h w i n d direction. T h i s w a s achieved by less than 0.001 5 radians ( 0 . 0 9 ° ) . be adopted without c o n c e r n about differen-
a s s u m i n g that the w i n d velocity profile w a s It w a s desirable to check the elastic modulus tial settlement. T h e results of the tests
k n o w n and that the force co-efficient, Cp, of the weathered material as this governs the produced values of elastic modulus between
w a s constant w i t h height. A space frame deformations. Laboratory tests on small 5 8 0 and 7 9 0 0 M P a .
analysis of the model w a s carried out w i t h this
pressure distribution in the given direction to
determine unit strains at those points w h e r e 1,0
measurements w e r e made. B y fitting these
results the required co-efficients could be
obtained. T h e resulting force co-efficients
for the various w i n d directions are given in 0,9
F i g . 5. T h e average value of C F w a s found
to be 0.82 and this value w a s used in the LL
<_>
design. T h e s e results w e r e later verified by
direct measurement of the resultant w i n d
force by means of a w i n d tunnel balance for
c 0,8

various w i n d directions.
T h e s e results are also s h o w n in Fig. 5. T h e
0,7
centroid of the w i n d force w a s found to be
at about 7 9 m above ground level for all
w i n d directions.
For one particular w i n d direction ( 0 = 3 0 ° ) LEGEND
0,6
noticeable oscillation of the model occurred / / Most probable rang* of Cp
w i t h i n a small range of model w i n d velocity Cp determined with a wind tunnel balance (without mast)
around 1 3 . 4 m / s e c (approximately 8 6 k m / h r Weighted average Cp = 0,82.
full scale at the height from w h i c h the o s c i l l a -
tions w e r e found to emanate or 5 8 k m / h r at 4-
30 60 120 150 180 210 24 0 270 300 330 360
10 m reference height).
T h e amplitude of these oscillations w a s Wind direction 8*
halved for w i n d s p e e d 5 % higher or lower than
this value, and no oscillations w e r e evident Fig. 5 A
for w i n d directions other than 5 ° above or Variation of w i n d force
below 0 = 3 0 ° . T h e oscillations w e r e approxi- co-efficient with
mately a c r o s s - w i n d and had a frequency of w i n d direction
3 0 . 3 Hz w i t h an amplitude w h i c h varied with
time. Their cause w a s found to be regular I5tm
vortex shedding from the portion of the tower
above the public v i e w i n g gallery and below
A
the underside of Level 9. It w a s found these
oscillations could be controlled by the
introduction of aerodynamic fins within this
portion of the model.
H o w e v e r , in v i e w of the following it w a s \
decided that no s u c h precautions w e r e
necessary:
(a) T h e frequency of occurrence of the
\
disturbing w i n d velocity and direction is
less than once in 10 years.
(b) T h e m a x i m u m resulting acceleration on — 68m
the tower w o u l d be 0 . 8 2 % g, w h e r e a s
1 % g is considered to be the limit of
\
s
acceptability and 1.5% g disturbing.
(c) T h e amplitudes measured w e r e w e l l
w i t h i n the acceptable limits for the
structure. \\,\
No other oscillations w e r e detected up to a \\
N
m a x i m u m test speed equivalent to a full \
scale w i n d of 1 4 4 km/hr.

Foundations 0 0,1 0,2 0,3 OA 0,5 0,6 0,7 0,8


Boreholes drilled at the positions of each shaft Ratio R = F / F for
n 8 = 0*
indicated a s u c c e s s i o n of alternating layers
LEGEND
of intact and weathered shale d o w n to depths Fh Wind force on tower segment above h
of 3 0 m. Core recovery in the weathered F Total wind force on whole tower
shale w a s very poor, and it w a s estimated that Fig. 6 • —©— As measured in wind tunnel {without mast)
the percentage of weathered material in the Distribution of w i n d —H— Theoretical value (without mast)
upper 2 0 m below founding level w o u l d force with height o— Theoretical value (with mast)
vary b e t w e e n 2 0 % and 3 0 % for the four shaft
positions.
m
The raft w a s 3.5 m deep and designed to
ensure that the centroid of the dead load
of the tower coincided with the centroid
of the raft w i t h a m a x i m u m bearing pressure
of 6 0 0 k P a under dead plus live load and
7 0 0 k P a w i t h w i n d loads included.

Construction
A number of special construction problems
existed, n a m e l y :
(a) T h e construction of the raft foundation.
(b) T h e method of construction of the i .1

vertical elements, their inter-connection 1


w i t h the w a l l - b e a m s and the control of
alignment and verticality.
(c) Control of the quality of concrete finish
on the vertical shaft elements and the
special off-shutter concrete finish
required on the low rise building at the
base of the t o w e r .
3

(d) T h e construction of the major horizontal


cantilever floors at Levels 6 and 9.
(e) Detailing a n d construction of the
window walls.
B e c a u s e of the special nature of the project,

l
the client adopted our recommended pro-
cedure of pre-qualification of tenderers.
In this w a y a short-list of invited tenderers,
fully qualified to handle the project and 1

briefed on the design intent, w a s obtained.


Raft construction
It w a s imperative that a high quality concrete . J
finish w a s obtained. T o achieve this, great
s
IB
care w a s taken w i t h the concrete mix design
and the choice of aggregates. T h i s w a s done 7
w i t h assistance from the Portland Cement =£•91
Institute. Test panels w e r e manufactured
prior to tender using various concrete mixes
to examine both the off-shutter finish and the
concrete colour. T o avoid c h a n g e s in the US"
colour of aggregates during the construction i I
period, the contractor w a s asked to stockpile
all the aggregate required for the project
prior to c o m m e n c e m e n t of construction.
Despite this precaution, the s a n d ran out
towards the end of the project and as the
supply at that quarry had changed colour
since the start of the contract it w a s necessary
to match the sand from elsewhere.
The 3.5 m deep raft involved some 1,400 m 3

of concrete w h i c h w a s cast in three separate

A
horizontally-layered pours.
The m a x i m u m depth of pour w a s 1.5 m.
Heavy reinforcement only occurred in the
bottom and top pours and could be fixed
only w h e n required, thereby avoiding the
need for e x c e s s i v e support for the top rein- Fig. 7
forcement. E a c h section w a s protected w i t h The partially completed tower s h o w i n g the sliding platform
polythene sheets for curing after casting.
Precautions w e r e taken w i t h the mix design
to minimize the heat of hydration by using a
5 0 / 5 0 combination of cement and slag and temporary c o l u m n s were cast around the The heavy w a l l - b e a m reinforcement w a s
large 4 0 mm aggregate to reduce the water j a c k i n g rods to give them the required placed prior to sliding, it being possible to fix
demand of the mix. Temperatures w e r e support). T h e sliding platform consisted of a maximum height of only about 9 0 0 mm at a
measured by means of thermo-couples three l e v e l s ; namely, the shutter level, time due to the interference of the j a c k i n g
through the depth of the raft after casting and finishing level and the curing c o m p o u n d frames. T h i s portion w a s then slid before
differential temperatures remained within application level, and w a s braced to ensure fixing on the next could proceed. During this
acceptable limits. rigidity during sliding. T h e sliding shutter stop-start procedure for sliding the w a l l -
incorporated sections w h i c h linked the lift beams, and in particular the 8 m deep beam
shafts and w e r e used in sliding the w a l l between levels 5 and 6 w h i c h took a total of
Sliding form work beams. 2 2 5 hours, care had to be taken w i t h the
Before c o m m e n c e m e n t of the slide, t w o small concrete preparation at each stop to avoid
The contractor proposed a sliding form of
test slides were conducted using different blemishes at the construction joints.
construction for all the vertical elements
including the w a l l - b e a m s . T h e procedure w a s concrete mixes, and as a result the most Where necessary, s c r e w couplers were used to
to slide continuously to the underside of suitable mix satisfying both slidability and c o n n e c t the main reinforcement in the slid
each w a l l - b e a m , at w h i c h stage a steel soffit finish w a s c h o s e n . concrete portion to the beams and slabs to be
girder w a s installed between the shafts and In early d i s c u s s i o n s with the contractor it w a s constructed later. T h i s again meant a
fixed by means of welding to plates cast into decided to use reinforcement c a g e s in the s l o w i n g d o w n of the sliding speed and in
the w a l l s . T h e s e girders formed the soffit shafts tied together with the lighter horizontal some cases a stop, and as a result special care
of the w a l l - b e a m s and supported jacking reinforcement. T h e height to w h i c h horizontal w a s necessary with the finishing.
rods to enable the w a l l - b e a m s to be slid reinforcement could be fixed w a s dictated by The alignment of the slide w a s controlled
concurrently w i t h the shafts after making the j a c k i n g frames w h i c h span the shutter. by means of optical plummets set in the
minor c h a n g e s to the shutter ( F i g . 7 ) . The c a g e s were staggered vertically to enable shaft corners at ground level. Readings
T o a c h i e v e the required high standard of the reinforcement to be placed in a c o n - were taken on a target on the underside of the
finish on the vertical elements a steel shutter tinuous sequence thereby avoiding a bottle- sliding platform. External c h e c k s were carried
w a s used w i t h j a c k i n g rods positioned to neck in the fixing operations. out using a s i n g l e - s e c o n d theodolite set up
miss the openings in the shafts. (Where During the sliding of the deep w a l l - b e a m s it over beacons near the base of the tower. In
jacking rods had to go through openings. w a s more difficult to control the surface finish. the later stages a laser beam w a s also used, 1 5
but this did not prove as s u c c e s s f u l as the 1

optical plummets because of the divergence,


shape and movement of the beam. A l s o , the
s h a p e of the t o w e r did not lend itself to the use
of a single laser. B e c a u s e of the rate of sliding
( u p to 2 0 0 mm per hour) the optical plummet

readings had to be taken every f e w hours.
E a c h j a c k i n g frame had a water level fed by a
central reservoir for levelling the shutter. B y
sliding w i t h the shutter slightly off level the
alignment could be adjusted. A lever device
w a s incorporated into the sliding shutter to
enable a force to be applied to adjust the
alignment of any shaft.
Difficulties w e r e experienced both in o b -
taining consistently reliable readings w i t h the
optical plummet and w i t h maintaining align-
ment, particularly because the balance and
response of the sliding shutter appeared to
be upset w h e n s u c c e s s i v e shafts stopped off,
resulting in a different shutter configuration.
Generally the alignment w a s controlled to

1
within 5 0 mm, but at one stage a deviation
of nearly 1 0 0 mm w a s detected on the
northern shaft. T h i s w a s gradually corrected
and is not visible and does not impair the
performance of the lift.
Fig. 8 A
Finishing of the concrete surface w a s done
The sliding platform
on the s e c o n d level of the sliding platform.
s h o w i n g girders,
Under normal sliding conditions the concrete
emerged from the underside of the sliding hangers, precast
forms relatively soft' (six hours o l d ) . T h e slabs and
surface w a s then rubbed d o w n using a reinforcement
w o o d e n float and brushed vertically to give it
an even appearance. After a stop in the sliding, i
the first concrete to emerge from the forms
w a s hard,-and to get an equivalent finish the

\
surface w a s first rubbed w i t h carborundum
stones and then lightly brushed w i t h a grout
made by sieving the coarse aggregate out of
the concrete used in the slide.
Fig. 9 •
Due to the difficulties involved in getting
Ground leve
uniform distribution of water for curing, and
off-shutter concrete
the possibility of freezing during the winter
months w h e n the majority of sliding took
place, water spray curing w a s not used.
Instead, a resin-based curing compound
between panels w e r e sealed using a sealing Off-shutter concrete
(Cormix CM 90) w a s sprayed onto the c o n -
cord and grout. T h e reinforcement w a s fixed on the l o w - r i s e building
crete by hand from the lowest level of
also using the steel cantilever s y s t e m for The finish required for the l o w - r i s e building
the sliding platform. During the early stages
support and the s t o p - e n d s w e r e positioned at ground level w a s to express the grain
of sliding, the spray equipment w a s not
before casting the concrete. T h e s t o p - e n d s pattern of s a w n timber boards on the
adequate to ensure e v e n distribution of the
w e r e located so as to allow the hangers to be surface. T o achieve this, tongued-and-
c o m p o u n d and over-application occurred in
re-used. grooved boards w e r e sandblasted to e n h a n c e
certain areas, leaving y e l l o w marks. T h e s e
have almost entirely disappeared w i t h time. O n c e the concrete had reached the required the grain pattern and then sealed. J o i n t s
strength, the hangers w e r e loosened and the w e r e sealed by means of compriband strips
w h o l e system moved out using the n e w against the timber m o c k - m a s o n joints.
Cantilever platforms concrete for support. T h e next row of precast The design mix for the off-shutter concrete
Detailed d i s c u s s i o n s w e r e held w i t h the panels were then hung and the process w a s developed in consultation w i t h P C I .
contractor on alternative proposals for the repeated. Strict site controls w e r e set up to monitor the
construction of the main cantilever platforms T o finish the edge strip, steel shutters w e r e stockpiling and use of the various mix
at levels 6 and 9 and w e w e r e appointed to supported from the cantilever s y s t e m . T h e constituents.
design the temporary w o r k s on behalf of the same system w a s used for both levels 6 and The details of the formwork for e a c h panel
contractor. 9, there being four r o w s of panels and the edge w e r e d r a w n up by the contractor and s u b -
T h e final solution adopted w a s a launching strip at Level 6 and t w o r o w s of panels and mitted for approval. T o gain a s many r e - u s e s
system using precast concrete panels approxi- the edge strip at Level 9. T h e initial in situ from e a c h form a s possible, the w o o d e n
mately 1.5 m square and 1 0 0 mm thick a s a n n u l u s w a s more difficult to construct at m o c k - m a s o n joints w e r e made movable
permanent soffit shutter panels. T h e pattern of Level 9 because of the a b s e n c e of a shaft on on the form. This w a s a c h i e v e d by the use
joints between panels w a s detailed to meet the one side. T h i s w a s replaced by a steel of compressible sealing strips to seal it
architects' requirements. T h e slab at Level 9 is cantilever bracket in that position. against the 'rough' timber grain. T h i s meant
technically the most difficult, being supported Due to the critical nature of the hanging that, w i t h i n the restriction of the board
unsymmetrically by the central core and the details, a f u l l - s c a l e load test w a s carried out on pattern, one form could be used for any size of
t w o remaining lift shafts at that level and one of these precast panels at the S A B S . T h e panel.
cantilevering s o m e 8 m beyond the central girders, hangers, precast slabs and rein- All construction joints had to fall on mock-
core. ( S e e F i g . 2 section 2 - 2 ) . It tapers from forcement are s h o w n in Fig. 8. mason joints and to prevent grout leakage the
1.5 m deep at the core to 4 5 0 mm at the edge A n interesting facet w a s the detail developed forms w e r e sealed onto existing concrete
w h e r e it supports the c o l u m n s carrying the for the stop-end between pours. This using a compressible sealing strip on the edge
technical floors and roof above. consisted of a lightweight frame covered w i t h of the completed concrete. All details of
A concrete a n n u l u s about 1.5 m deep w a s e x p a n d e d metal, w h i c h enabled the heavy ferrule holes, expressed joints, colour of
first cast around the shafts using conventional cantilever reinforcement to be placed simply concrete, concrete finish, etc. w e r e resolved
shuttering supported on steel brackets off the by cutting holes through it w h e r e required. between the architect and the contractor
vertical shafts. Radial structural steel c a n t i - A certain amount of shutter oil w a s left on the priorto starting construction. ( F i g . 9 ) .
lever beams w e r e then attached above this precast panels and some grout had leaked T o ensure that the required quality of finish
concrete and supported a series of trans- from the joints. It w a s therefore necessary to w o u l d be a c h i e v e d , a number of sample
verse beams at their extremities. T h e precast clean the underside of the slabs after c o n - panels w e r e prepared prior to c o m m e n c i n g
soffit panels w e r e supported on the c o m - struction, using a lightweight structural steel construction and compared w i t h a test panel
pleted concrete on the inside and hung by platform hung under the slab. After this w h i c h had been produced prior to tendering
adjustable hangers, from the transverse treatment a very satisfactory soffit finish w a s and w a s specified as representing the required
16 beams on their extreme edge. T h e joints achieved. quality.
Fig.10
T o w e r during construction

A n interesting aspect of the shuttering w a s the


method used for construction of openings for
w i n d o w s , etc. T o avoid the problem of
concrete not reaching the centre of the base of
an opening, small temporary c o l u m n s were
constructed w i t h i n the opening. T h i s a l l o w e d
placing and vibration of concrete in the
inaccessible areas.
Forms were generally stripped in under 24
hours w h i c h meant that if some patching
became necessary, it c o u l d be undertaken
w i t h minimal effect on the final finish.
These areas were patched using grout and a
sponge.
Water curing w a s used, the w a l l s being
sprayed w i t h water t w i c e daily. A total of
2,000 m of off-shutter concrete w a s cast
2

in the ground level structure.

Window walls
T h e w i n d o w w a l l s w h i c h occur between
Levels 6 a and 6, 9 and 1 1 a and 16 and 1 6 a .
consist of a series of structural steel mullions
hung from the upper levels and supported
horizontally at e a c h level, into w h i c h the
w i n d o w frame is fixed so that all glazing is
done from the inside of the building. A n
additional feature is the use of single glazing
and external w a l k w a y s , enabling the glazing
to be cleaned from the outside as w e l l as the
inside of the building and thereby eliminating
expensive pivoting w i n d o w frames.
Special care w a s taken with the specification
for this steelwork.
A m o c k - u p w a s made to study the details
and test the system against rain penetration.
A s a result of the tests, modifications had to
be made to meet the architectural require-
ments and still ensure adequate corrosion
protection. T h e specification adopted w a s
1 5 0 microns of bronze metal spray over 1 0 0
microns of zinc metal spray, sealed with a
clear acrylic sealer.

Credits:
Architects:
S o u t h Africa Public W o r k s Department,
Architectural Department
Quantity surveyors:
Southby, B i h l , Detert & Slade
Consulting electrical engineers:
Bidermann, Finn, Beekhuizen & Partners
Mechanical services:
South Africa Public W o r k s Department,
M e c h a n i c a l Department
Main contractors:
S t o c k s - F u t u r u s ( P t y ) Ltd. 2 - a consortium
between S t o c k s and S t o c k s ( P t y ) Ltd. and
Futurus.
T h e author is indebted to the many individuals
w h o formed part of the team w h i c h made this
project a s u c c e s s : firstly, to the relationship
w h i c h existed throughout between the
architect responsible, Mrs H. Lenddorff, the
consulting engineers, the P W D engineers
and the quantity surveyors, out of w h i c h it
w a s possible to create a tower of quality;
secondly, to those members of Ove A r u p &
Partners w h o participated tirelessly on the
project, particularly J a n Heynike for his
contribution to the development of the basic
concept and to the engineers w h o executed it,
Vincent Diesel, R o n Finkelstein, H. Scott and
the late Fred H o o g e n d i j k ; thirdly, to Mr V.
Chasteau for his contribution in advising on
and carrying out the w i n d tunnel t e s t i n g ;
finally to the contractors, and particularly
Dr. W. V a n c e , for the excellent relationship
w h i c h prevailed on site and the enthusiastic
manner in w h i c h challenging problems were
met and overcome.
Central Bank, Dublin
Architects: Stephenson & Associates
T h e A s s o c i a t i o n of Consulting Engineers of
Ireland has given its 1 9 8 0 Excellence A w a r d
for a structural project to the Central Bank,
Dame St. Frank Lydon of Ove Arup &
Partners Ireland, consulting engineers for the
project, accepted the A w a r d at the annual
dinner of the Association on 7 M a r c h .
T h e main building is an eight storey, 4 5 m
high structure and measures 4 5 m • 4 5 m on
plan. It is set towards the north of the site
overlooking a landscaped piazza fronting
onto D a m e Street. T w o ancillary buildings
are also incorporated on the site. One of these
a c c o m m o d a t e s the staff dining facilities. T h e
other is a reconstruction of a listed 19th
century building w h i c h stood on the site
prior to this development. There is a t w o
storey underground car park covering most
of the site to accommodate 1 3 0 cars.
T h e principal feature of the building design
of engineering interest is the superstructure
w h i c h is suspended from the top of t w o
reinforced concrete service cores. Other
aspects of the building construction, the use
of slip forming to construct the concrete
service cores and the lifting into position of
complete floors assembled at ground level,
are also unusual features.
— :

I T


w ,

Pi

i
:
o

£ •

You might also like