ANS : Point 1,2,3 - LA tanks fabrication/ purchase is still to be finalized.

ANS : We have already received it from Mr Bakshi.

ANS : Waiting for price negotiation for raising the PO.

ANS : Point 1,2,3 - LA tanks fabrication/ purchase is still to be finalized.

ANS : Nitin sir had asked Rajesh to get it from Mr Mahendra shah ( Baroda)

ANS : Rajesh has already made it and hard copy has been submitted to Nitin sir,Still there will be changes
as the LA tank design is yet to be finalized.

ANS : Quotes price and qty has be analysed by Architect.Contractor will start from Monday.

ANS : Quotes price and qty has be analysed by Architect.Contractor will start from Monday.

ANS : Point 1,2,3 - LA tanks fabrication/ purchase is still to be finalized.

ANS : We have already received it from Mr Bakshi.

ANS : Will start after completing shed roofs and AA foundation.

ANS : Will look after taking final decision from Nitin sir.
ANS : Still awaiting approval of application from Alibaug office.However we will get the new agreement
copy on Tuesday.By the time approval comes we will be ready with the agreement.Also we will have to
finalize the UG tank position so that tapping from main outside line can be planned accordingly.

ANS : Waiting for the reply from Mahendra gujjarji regarding the decision taken by Mr More and the Sarpanch. I spoke with Gujjarji today.He
has assured to revert in a couple of days as the Leaders are busy with election schedule.We will have to upload the test report from licensed
electric contractor to complete the online application process.

No clearance required.

No clearance required.

Will need a few days more.

Already got.

Will report after collecting all details.