CoG

COG
Retail Locations Qty X Y DIST WGT.DIST
RL1 425 100 80 29.00 12327
RL2 320 86 40 23.89 7644
RL3 220 20 60 57.16 12575
965 32546

CoG Coordinates 77.119 62.176


Weber Method
Weber
Retail Locations Qty X Y Dist Wgt Dist
RL1 425 100 80 17.55 7,457
RL2 320 86 40 26.31 8,418
RL3 220 20 60 69.56 15,304
965 Total Wgt Dist 31,179

Weber - Coordinates 89 66 (use Solver)


Comparison
Weber CoG
Retail Locations Qty X Y Dist WgtDist Dist
RL1 425 100 80 29.00 12,327 17.54
RL2 320 86 40 23.89 7,644 26.31
RL3 220 20 60 57.16 12,575 69.56
965 Total Wgt Dist 32,546 Total Wgt Dist

Weber - Coordinates 77 62 (use Solver) Average Distance Weber=


CoG Coordinates 89.297 66.098 Average Distance COG=
CoG
WgtDist
7,457
8,418
15,304
31,179

69.65
77.70
Weber Method (2)
Site Coordinates SO1
Retail Locations Qty X Y Site Option X Y Dist
RL1 425 100 80 SO1 60 50 89.44
RL2 320 86 40 SO2 70 75 47.71
RL3 220 20 60 SO3 41 55 72.11
965 Total Wgt Dist

WEBER CO. 89.30 66.1

WEBER
DIST
17.5
26.3
69.6
SO1 SO2 SO3
Wgt Dist Dist Wgt Dist Dist Wgt Dist
38,013 30.41 12,926 64.08 27,233
15,266 38.48 12,315 47.43 15,179
15,864 52.20 11,484 21.59 4,749
69,144 Total Wgt Dist 36,725 Total Wgt Dist 47,161

WEBER
TOTL.DIST
7457
8418
15304
31179
Goal = Selecting Best Facility Location
Input Range

Pairwise comparisons among objectives Normalized matrix


Distance Distance
Matrix "A" Land Cost Wage Rate
from Plant from Retail
Land Cost 1 2 2 3
Distance from Plant 1/2 1 1 2
Distance from Retail 1/2 1 1 3
Wage Rate 1/3 1/2 1/3 1

Pairwise comparisons among sites based on land cost Normalized matrix


Site 1 Site 2 Site 3
Site 1 1 2 4
Site 2 1/2 1 2
Site 3 1/4 1/2 1

Pairwise comparisons among sites based on distance from plant Normalized matrix
Site 1 Site 2 Site 3
Site 1 1 1/2 1/3
Site 2 2 1 1/3
Site 3 3 3 1

Pairwise comparisons among sites based on distance from retail Normalized matrix
Site 1 Site 2 Site 3
Site 1 1 1/2 1/2
Site 2 2 1 3
Site 3 2 1/3 1

Pairwise comparisons among sites based on wages Normalized matrix


Site 1 Site 2 Site 3
Site 1 1 3 2
Site 2 1/3 1 1/2
Site 3 1/2 2 1
Calculations Results

Weights (w) Determining highest Site Scores Overall scores


Distance Distance
Land Cost Wage Rate
from Plant from Retail
Site 1
Site 2
Site 3

Scores

Scores

Scores

Scores
Results

0.0000
Remarks
For more Information,
email: gtech.ic@gmail

Please Like Us our Facebo

https://www.faceboo
more Information, Help and yours Valueable feedback please
ail: gtech.ic@gmail.com

or
ase Like Us our Facebook Page:

https://www.facebook.com/gtech.ic
Obj. Function
Z= $ 10,708

Inputs - Costs, Capacities, Demands

Demand Region - Prod. & Transportation Cost


Supply Region Fixed Cost ($)
DR1 DR2 DR3 DR4 DR5
SR1 81 92 101 13 115 9000
SR2 117 77 108 98 100 6750
SR3 102 105 95 119 111 9750
SR4 115 125 90 59 74 6150
SR5 142 100 103 105 71 6000
Demand 12 8 14 16 7

Decision Variables

Demand Region
Supply Region Plants
DR1 DR2 DR3 DR4 DR5
SR1 12 8 0 0 0 1
SR2 0 0 0 0 0 0
SR3 0 0 0 0 0 0
SR4 0 0 0 0 0 0
SR5 0 0 0 0 0 0

Constraints

Supply Region Excess Capacity


SR1 0
SR2 0
SR3 0
SR4 0
SR5 0

DR1 DR2 DR3 DR4 DR5


Unmet Demand 0 0 14 16 7
Key:

Formula Cell
Input Cell
Supply Region
SR
DR Demand Region
1 Open
0 Closed
Capacity

20
20
20
20
20