Energi Listrik (24 Jam) Energi Listrik (24 Jam) Pemanfaatan Uap Oleh

Power Plant Gross Net Pembangkit

KWH KWH t
KRH – Unit 1 (PGE) 289605 252165.643069 2588.266
Buangan ke Rock GPP Shutdown Import SGSS Shutdown
Muffler (Hour) Energy (Hour)

USton hr KWH hr
0 0 0 0
Keterangan
Jam Awal Gangguan Jam Akhir Gangguan
(HH:mm) => gunakan (HH:mm) => gunakan Derating
PLTP Status Gangguan tanda petik satu (') tanda petik satu (') (MW)
sebelum mengetik jam sebelum mengetik jam

KRH – Unit 1 (PGE) FD1 (Forced Derating Im10:00 10:00 19.49


Lokasi Gangguan Penyebab Gangguan Keterangan

SGS Sumur produksi


SUMUR TKS Tekanan Jalur Suhu Jalur Trotle Valve Opening Flow Rata2

barg barg deg C % t/hr


TLG 3-1 11 10 184.12 100
TLG 3-2 23.4 0 0 100
KRH 4-1 7.23 5.75 164.4 100
KRH 5-1 7.22 5.93 164 45
KRH 5-2 0.13 0.04 54.08 0
Flow Total 24 Jam Pressure Upstream Differential Pressure Status Sumur

t barg barg
Operation
Shut In
Operation
Operation
Shut In
Keterangan

Temperature calculated
Temperature calculated

Pengukuran Reservoar, TKS Sumur drop


Flow Rata2 FlowJam
Total 24
SUMUR TKS Tekanan Jalur Suhu Jalur pH

barg barg deg C t/hr t


KRH 2-1 -0.9 12.9 39.59
KRH 6-1 6
Fluida yang Diinjeksikan Status Sumur Keterangan

Cold Brine Operation Cold Brine & Condensate Reinjection (Flow Meter perlu kalibrasi)
Hot Brine Operation Tidak ada Press,Temp dan Flow indicator
er perlu kalibrasi)
SUMUR TKS Status Sumur Keterangan
barg
KRH 4-2 0 Shut In NO PRESSURE GAUGE
KRH 4-3 39.4 Shut In
KRH 5-3 25 Shut In
Trotle Valve Opening
SEPARATOR Tekanan Suhu Level Brine (%) Brine (%)
barg deg C % %
KRH 4 5.8 163.7 60 100
KRH 5 5.7 163.5 10 100
KRH 6 6.3 166 10 100
Trotle Valve Opening Steam Flow Rata2 Brine Flow Rata2
Steam (%)
% t/hr t/hr
100
100
100 62.04
Suhu
INTERFACE POINT Tekanan Interface Point Interface SCRUBBER Tekanan Scrubber
Point
barg deg C barg
Interface KRH Unit 1 5.819 162.7 Scrubber KRH Unit 1 5.761
Suhu Scrubber

deg C
162.7
AREA Rencana Realisasi Kemarin Temuan Kemarin
Karaha