Professional Documents
Culture Documents
INSTRUCTIONS
1. IMMEDIATELY AFTER THE COMMENCEMENT OF THE EXAMINATION, YOU SHOULD CHECK THAT
THIS TEST BOOKLET DOES NOT HAVE ANY UNPRINTED OR TORN OR MISSING PAGES OR ITEMS, ETC.
IF SO, GET IT REPLACED BY A COMPLETE TEST BOOKLET.
2. You have to enter your Roll Number on the Test Booklet in the Box provided
alongside. DO NOT write anything else on the Test Booklet.
3. This Test Booklet contains 50 items (questions). Each item comprises four responses (answers). You will select the
response which you want to mark on the Answer Sheet. In case, you feel that there is more than one correct response,
mark the response which you consider the best. In any case, choose ONLY ONE response for each item.
4. You have to mark all your responses ONLY on the separate Answer Sheet provided. See directions in the Answer
Sheet.
6. Before you proceed to mark in the Answer Sheet the response to various items in the Test Booklet, you have to fill in
some particulars in the Answer Sheet as per instructions sent to you with your Admission Certificate.
7. After you have completed filling in all your responses on the Answer Sheet and the examination has concluded, you
should hand over to the Invigilator only the Answer Sheet. You are permitted to take away with you the Test Booklet.
8. Sheets for rough work are appended in the Test Booklet at the end.
03. An activity will take 5 weeks to complete precedence relationship details are given the
07. Consider the following statements w.r.t 09. In a project network, the permissible delay
charts. of a particular activity without affecting the
1. Linked bar chart can show the start of succeeding activity is known as
precedence relationship between the (a) Total float
activities. (b) Free float
2. Time scale is required to construct bar (c) Independent float
hart. (d) Interference float
3. Length of the bar chart need not be
equal to the project duration. 10. The weekly demand is 20 units, ordering
Which of the above statements are correct? cost is Rs. 200 per order, carrying cost is
(a) 1 and 2 only Rs. 2 per unit per month. The Economic
(b) 2 and 3 only order Quantity (EOQ) is
(c) 1 and 3 only (a) 131 units (b) 100 units
(d) 1, 2 and 3 (c) 1040 units (d) 231 units
08. Consider the following statements with 11. In which financial analysis the rate of discount is
respect to project scheduling tools. not pre specified?
1. No dummy activity is required in the (a) Net Present Value
construction of activity – on – Node (b) Benefit/Cost ratio
(AON) diagram. (c) Internal rate of return
2. Two different activities can be shown by (d) (Benefit – Cost) Value
connecting two events directly.
12. WBS is used in planning to
3. Event is a state of commencement or
1. Estimate duration of the project
completion of an activity.
2. Estimate cost of the project
4. In bar charts, arrow link can be used to
Select the correct answer using the codes
connect the activities.
given below.
Which of the above statement are correct?
(a) 1 only
(a) 1, 2 and 3 only
(b) 2 only
(b) 1, 3 and 4 only
(c) both 1 and 2
(c) 2, 3 and 4 only
(d) neither 1 nor 2
(d) 1, 2, 3 and 4
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar|Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally|Kolkata|Ahmedabad | Kothapet
:4: General Studies & Engineering Aptitude
13. Which of the following types of 16. For a project, who are the important
organisations are not suitable for Minor stakeholders?
works ? 1. Customer
1. Functional organisation 2. Supplier
2. Project organisation 3. Investor
3. Matrix organisation 4. Competitor
Select the correct answer using the codes Select the correct answer using the codes
given below. given below.
(a) 1 and 2 only (b) 2 and 3 only (a) 1, 2 and 3 only
(c) 1 and 3 only (d) 1, 2 and 3 (b) 1, 2 and 4 only
(c) 2, 3 and 4
14. In a matrix organisation who is responsible (d) 1, 3 and 4 only
for skill improvement of employees
17. A machine costs Rs 32,000 by constant rate
1. Project manager
declining Balance method of depreciation,
2. Functional manager
its salvage value after an expected life of
Select the correct answer using the codes
3 years is Rs 4,000. The rate of depreciation
given below.
is
(a) 1 only
(a) 0.25 (b) 0.30
(b) 2 only
(c) 0.40 (d) 0.50
(c) both 1 and 2
(d) neither 1 nor 2
18. For projects and major projects which of the
following types of organisations are suitable
15. Project execution plan(PEP) is the reference
1. Functional organisation
document for project manager. For quick
2. Matrix organisation
reference, its summary document is used.
3. Project organisation
It is called as
Select the correct answer using the codes
(a) Project planning
given below.
(b) Project schedule
(a) 1 and 2 only (b) 2 and 3 only
(c) Project charter
(c) 1 and 3 only (d) 1, 2 and 3
(d) None of these
19. Which of the following is not purpose of 21. Which of the following are quantitative
WBS in project planning? techniques of risk analysis?
(a) To roughly estimate time and cost of 1. Decision tree analysis
project 2. Brainstorming
(b) Facilitate and improve the decision 3. Expected Monetary Value (EMV)
making on procurement of resources 4. Monte Card Simulation
(c) Relate activities under particular trade Select the correct answer using the codes
specialisations to help in organising for given below.
staff (a) 1, 2 and 3 only
(d) Coordinate regarding milestone events (b) 1, 2 and 4 only
across trade specialisations to improve (c) 2, 3 and 4 only
the synergy between the trades. (d) 1, 3 and 4 only
20. Which of the following are correct regarding 22. Which of the following techniques may help
work breakdown structure (WBS)? avoid biased decisions while rating sub-
1. WBS is a hierarchical tree structure of contractors in a project?
deliverables and tasks. (a) Letter of intent
2. WBS is a tool that quantifies the scope (b) Oral contract
of the work. (c) Weighting system
3. WBS is a checklist that ensures (d) Bidder conference
consistency and completeness of the
project. 23. Which of the following is a document which
Select the correct answer using the codes describes how the project management team
given below. will implement quality policy?
(a) 1 and 2 only (a) Quality audit
(b) 1 and 3 only (b) Quality assurance plan
(c) 2 and 3 only (c) Quality commitment
(d) 1, 2 and 3 (d) Quality management plan
24. In a project some issue arises. The project 27. To reduce the likelihood of risk which
manager tries to know more details about strategy can be implemented?
the issue. It is (a) Active risk acceptance
1. Team management approach (b) Passive risk acceptance
2. Team leadership approach (c) Risk mitigation
Which of the above statements are correct? (d) Risk avoidance
(a) 1 only (b) 2 only
(c) Both 1 and 2 (d) Neither 1 nor 2 28. Which of the following statements is/are
correct?
25. Which of the following is correct statement 1. Training is risk avoidance strategy
regarding Earned Value Analysis (EVA) 2. Imposing penalty is passive risk
diagram? acceptance
Cumulative cost Select the correct answer using the codes
given below.
AV PV (a) 1 only
EV (b) 2 only
(c) Both 1 and 2
(d) Neither 1 nor 2
Weeks
Today
(a) PV cannot be assessed beyond today 29. In the termination stage what is not to be
(d) PV cannot be more than EV if AV is Select the correct answer using the codes
30. Which of the following is/are done by investment will generate cash inflows of 13
customer in functional audit during product lakhs. If the discount rate is 10%, what is the
acceptance review? project’s NPV (in lakhs)?
1. Check whether installation is done (a) 2.11 (b) –3.03
2. Check whether training (necessary) is (c) 2.32 (d) –2.76
given
34. Consider these statements with regard to
Select the correct answer using the codes
GERT (Graphical Evaluation and Review
given below.
Technique)
(a) 1 only (b) 2 only
1. It uses probabilistic approach to network
(c) Both 1 and 2 (d) Neither 1 nor 2
logic.
31. Microsoft Company produces a single 2. It uses probabilistic approach to time
article. Following cost data is given about its estimate of activities.
product: 3. It can be used for R&D projects.
Selling price per unit - Rs.40 Which of the above statements is/are
Marginal cost per unit - Rs.24 correct?
Fixed cost per annum - Rs.16000 (a) 1 only (b) 2 only
Calculate the break even sale (in rupees) (c) 1 and 2 only (d) 1, 2 and 3
(a) 40000 (b) 1000
35. Consider the following statements.
(c) 2000 (d) 10000
1. Milestone charts are modification over
32. In _______ contract amount paid to the original bar chart.
contractor is on basis of work performed at 2. Milestone represents a certain key event
site and unit price quoted against each item which marks completion of certain
of work by the contractor. portion of the activity.
(a) Lump-sum (b) Cost plus percentage 3. Relation among milestones of different
(c) Item rate (d) Percentage rate activities is indicated.
Which of the statements are true in
33. A certain investment will require an
milestone chart context?
immediate cash outflow of 30 lakhs. At the
(a) 1 and 3 only (b) 1 and 2 only
end of each of the next three years, the
(c) 2 and 3 only (d) 1, 2 and 3
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar|Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally|Kolkata|Ahmedabad | Kothapet
:8: General Studies & Engineering Aptitude
36. ABC analysis divides an organization's on- 40. Project objectives are constraint by
hand inventory into three classes based upon 1. Time required for completion of the
(a) Annual demand project.
(b) Unit price of item 2. Project cost required for project
(c) Total annual item cost completion.
(d) Scarcity of item 3. Performance requirements of the
project.
37. In PERT analysis the time estimate of Which of the above statements is/are
activities correspond to correct?
(a) Normal distribution (a) 1, 2 and 3 (b) 1 and 3 only
(b) Poisson’s distribution (c) 2 and 3 only (d) 1 only
(c) -distribution
(d) Binomial distribution 41. The cross-section strip footing is shown
below:
38. In the time cost optimization, using CPM
method for network analysis, the crashing of
the activities along the critical path is done
starting with the activity having.
(a) Longest duration
(b) highest cost slope
(c) Least cost slope
(d) shortest duration Elevation (All the dimensions are in ‘mm’)
0.30 m
39. In a project life cycle, the maximum risk to
the stakeholders is in
(a) Concept phase
0.30 m 4.60 m
(b) Planning phase
(c) Commissioning phase
(d) Implementation phase 5.60 m
Plan
The quantity of 150 thick PCC (1 : 3 : 6) 44. For an activity 101 – 201 in AOA network,
required for footing(in cubic meter) is activity times and duration as shown below.
(a) 2.88 cu.m. Between total float, interference float and
(b) 19.2 cu.m. independent float, which one of the
(c) 3.8 cu.m. following is the correct sequence in the
(d) 22.4 cu.m. decreasing magnitude order?
46. Consider these statements with regard to (b) Both Statement (I) and Statement (II) are
Accident statistics objectives: individually true but statement (II) is not the
1. To help in evaluating the relative need correct explanation of statement (I)
for taking accident prevention measures (c) Statement (I) is true but Statement (II) is false
in different departments of an (d) Statement (I) is false but Statement (II) is true
establishment.
2. To help in making an appraisa1 of the 47. Statement (I): Multiple break-even points
progress of an accident prevention are possible in break even chart.
campaign and making people safety- Statement (II): Break even chart is one of
conscious. the sensitivity analysis techniques.
3. To provide encouragement when
methods used for the prevention of 48. Statement (I): Strength, weakness,
accidents are successful. opportunity, and threats analysis (SWOT
4. To enable comparisons to be made. analysis) is a qualitative risk analysis
Which of the above statements are correct? technique.
(a) 1, 2 and 3 only Statement (II): In qualitative assessment,
(b) 1, 2 and 4 only probability and consequence are not
(c) 2, 3 and 4 only numerically estimated, but are evaluated
(d) 1, 2, 3 and 4 using qualifiers.
Directions: Each of the next Four (4) items 49. In the context of critical path in a network,
consists of two statements, one labelled as the consider the following statements:
‘Statement (I)’ and the other as ‘Statement (II)’. Statement (I): A critical path in a network
You are to examine these two statements carefully cannot have any dummy activity.
and select the answer to these items using the Statement (II): The duration of the critical
codes given below: path in a network indicates the minimum
Codes: feasible time for completing the project.
(a) Both Statement (I) and Statement (II) are
individually true and Statement (II) is the
correct explanation of Statement (I)
50. In the context of crashing of activities in Statement (II): An activity that has
project scheduling, consider the following maximum cost slope is considered first for
statements: crashing.
Statement (I): Critical activities are crashed
to reduce the project duration.
Detailed solutions for this test will be uploaded on our website on 24-11-2019 at 2.00 pm.
This test results will be available on our website on 29-11-2019 at 6.00 pm.
https://www.aceenggacademy.com/ese-2020-offline-test-solutions-results/
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar|Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally|Kolkata|Ahmedabad | Kothapet