Professional Documents
Culture Documents
Information
To maximise the achievement of contractual outcomes and to continually improve contract performance, effectiv
contract management is required.
All unshaded (White) cells either get data from elsewhere in the Workbook or are not required.
Agencies may modify the Workbooks to suit individual or whole of Agency requirements. In using the Workbook
tools, an Agency acknowledges that it will retain ownership and responsibility for its maintenance, and the input
and management of all content including modifications.
Modifications should be undertaken with caution due to the formulas embedded in the worksheets.
Copies of the Contract Management Workbooks can be downloaded from the Department of Finance,
Government Procurement website under I manage a Contract - Resources.
More Information
Further information on contract management resources can be found on the Department of Finance's website.
Contract Management Advice
Advice on contract management practises or issues can be obtained by contacting the Capability and
Development team by email: ProcEducation@finance.wa.gov.au
Version 01-12-14
end of introduction
Contract Management Workbook - Period Contract
Work Area:
Contract Manager:
1. Contract Overview
Contract No. & Title:
Awarded Total Contract Value: (for the full contract term inclusive of GST)
Contractor's
Contractor Telephone Email
Representative
2. Worksheet Index
List all the documents relevant to this contract and where filed (ie hard copy file, record manageme
Document Register
system etc). Add documents to the list as created.
Use to list the contractor/s details including the purchase order number.
Contractor Details
Keep details up to date.
Use to detail and manage the extension options. Options must be exercised or declined in accorda
Extension Options
with the contract terms and conditions and your Agency delegation schedule.
Use to detail any pricing and/or payment requirements (ie price schedule [keep up to date], price va
Pricing - Payment Details
mechanism, settlement discount, payment schedule).
Use to detail all the variations made to the contract. Variations must be done in accordance with th
Contract Variations
contract terms and conditions and your Agency delegation schedule.
Use to detail and manage the insurance requirements.
Insurance Details
Keep details up to date and keep evidence of current insurances.
Meetings Use to detail and monitor meetings. Agenda Proforma Meeting Action Items List
Reporting Use to detail and monitor the reporting requirements and to document the results / analysis.
Performance Use to detail and monitor the performance requirements and to document the results.
Use to detail the key risks and controls / actions identified for managing the contract.
Risks Register
Update and / or add risks and actions, as identified, during the contract term.
Use to document enquiries and issues raised and their resolution.
Enquiry - Issues Register
Highlight any significant enquiries - issues for consideration at review - renewal.
Review - Renewal IssuesUse to summarise / list the issues that need to be considered when reviewing / renewing the contra
Buyers Guide Use to track the updates to the buyers guide.
Transition Use to detail and monitor the transition in / out tasks and timetable.
rd management
ned in accordance
nalysis.
Work Area:
Contract Manager:
Documents
Contract Documents (be familiar with and have a good knowledge of the contract documents)
end of table
Return to Overview and Index
Contractor Details
Agency Name:
Work Area:
Contract Manager:
Contractor Name:
(legal entity & 'trading name' as applicable)
Address 1:
Address 2:
Address 3:
Contractor's Representative:
Position:
Telephone:
Email:
Facsimile:
ABN:
ACN:
Contractor Details
Agency Name:
Work Area:
Contract Manager:
Contractor Name:
(legal entity & 'trading name' as applicable)
Address 1:
Address 2:
Address 3:
Contractor's Representative:
Position:
Telephone:
Email:
Facsimile:
ABN:
ACN:
Extension Options
Agency Name:
Work Area:
Contract Manager:
Contractor:
Option 2
Option 3
Option 4
Contractor:
Option 2
Option 3
Option 4
Contractor:
Exercised Date Exercised or Value of Extension Option
Extension Due Date Status
(Yes / No) Declined inc GST*
Option 1
Option 2
Option 3
Option 4
Contractor:
Option 2
Option 3
Option 4
end of table
Return to Overview and Index
Work Area:
Contract Manager:
Version 01-12-14
end of table
Return to Overview and Index
Payments Made
Agency Name:
Work Area:
Contract Manager:
Date
Payment Amount Payment Details
Processed
end of table
Return to Overview and Index
Contract Variations
Agency Name:
Work Area:
Contract Manager:
Date Variation Current Total Contract Value New Total Contract Value inc
Contractor Name Variation No. Variation Description / Reason
Effective From inc GST GST
( Note: If a variation changes the price, contract term etc the Purchase Order may need to be updated) Only complete where the variation effects the contract value
Date Variation Current Total Contract Value New Total Contract Value inc
Contractor Name Variation No. Variation Description / Reason
Effective From inc GST GST
Version 01-12-14
File / RMS Reference
File / RMS Reference
end of table
Return to Overview and Index
Insurance Details
Agency Name:
Contractor Name Insurance Type Expiry Date Status Insurer Policy No. Insured Amount Exclusions
Version 01-12-14
urn to Overview and Index
end of table
Return to Overview and Index
Meetings
Agency Name:
Work Area:
Contract Manager:
Work Area:
Contract Manager:
Version 01-12-14
Enter Meeting Notice Required
(in Days)
end of table
Contract No. & Title:
Venue:
Date: Time:
Attendees
Agenda Items
1 Introduction
Notes:
Notes:
Action(s) Required:
Notes:
Action(s) Required:
4 Achievements
Notes:
Action(s) Required:
5 Challenges
Notes:
Action(s) Required:
6 Improvements
Notes:
Action(s) Required:
7 Other
Notes:
Action(s) Required:
8 Next Meeting
Venue:
ganisation
Return to Overview and Index
Work Area:
Contract Manager:
Contractor:
Action No. Description of Action Required Who When
Contractor:
Action No. Description of Action Required Who When
Agency Name:
Work Area:
Contract Manager:
Contractor:
Action No. Description of Action Required Who When
Contractor:
Action No. Description of Action Required Who When
Agency Name:
Work Area:
Contract Manager:
Version 01-12-14 e
Status
Status
Status
Status
end of table
Return to Overview and Index
Reporting
Agency Name:
Work Area:
Date
Contractor Name Report Type Date Due Status Report Analysis Comments Issues / Actions Requiring Follow Up
Received
Version 01-12-14
File/RMS Reference No.
end of table
Return to Overview and Index
Performance
Agency Name:
Work Area:
Contract Manager:
Specified Output / Service Agreed Performance Measures Contracted Performance Level Proposed Method of Measuring
(include both parties obligations)
Risks Register
Agency Name:
Work Area:
Contract Manager:
Work Area:
Contract Manager:
Version 01-12-14
When
When
end of table
Return to Overview and Index
Work Area:
Contract Manager:
Work Area:
Contract Manager:
Version 01-12-14
File/RMS Reference No.
File/RMS Reference No.
end of table
Return to Overview and Index
Version 01-12-14
end of table
Return to Overview and Index
Buyers Guide
Agency Name:
Work Area:
Contract Manager:
Contract No. & Title:
Date of
Update No. Changes in Update
Update
Version 01-12-14
Return to Overview and Index
end of table
Return to Overview and Index
Transition
Agency Name:
Work Area:
Contract Manager:
Name Position Organisation / Work Area Phone No. Email Status / Comments
add rows as needed
Version 01-12-14
Address
end of table