(Architectural) importance
Project:ALKHUWAILDI villas - Project No. 22761 High
Date of issue 02-12-2019 Mid
Revision No. 0 Low
V.E.
4 Amend line type scale of all hidden lines which indicate arches & void
opening
OO2 Missed Drawings & Details
Detail of Pergola in front of living hall& Car parking shed details.
Wall sections, i.e. (main entrance), (pergola), Garbage room), …
Arches & opening between rooms.
Kitchen & Pantry details
Waterproofing details
Landscape & green area details
Typical door details
Aluminum typical details
Wardrobe schedule & Details
Waterproofing & exposed floor above basement
Stone cladding detail
Ladder detail.
Sky light details.
Clarify the differ in level +0.30 (near protection fence & level at parking (-
1 0.02 or +0.03) , i.e. (provide slope ≈ 2% from protection fence toward
parking) or (provide step at end of parking).
OO3 A001 Settingout
Plan 2 Provide all roof levels.
3 Provide SRI ratio as per DM.
4 Refer to comments (Drg. A101 ), (3 Drg. A-405)
1 Resolve the gap at ceiling of Wash & WC & stair void.
4 Provide reference to window between dining & Kitchen and provide detail at
Sch. of windows.
5 Clarify partition & door into pool deck along grid C, grid E, & grid 6
6 Clarify the line with curved corners from gate door to window W1 beside
OO4 A101 Ground entrance steps, i.e. (step so provide level +0.15)
7 Cancel duct at corner of kitchen at grids 4,E
Architectural Page 1 of 7
Review Comments Report Comment
(Architectural) importance
Project:ALKHUWAILDI villas - Project No. 22761 High
Date of issue 02-12-2019 Mid
Revision No. 0 Low
V.E.
9 Indicate levels of parking, all outdoor areas, (noting pool deck level is +0.45,
parking levels are -0.02 & +0.03 as per site plan).
10 Shift laundry door to allow provide architrave.
1 Coordinate with Str. & Mech. Eng. to shift duct at grids 4,E into pantry &
avoid projection in bedroom-1.
2 Provide similar duct of above comment at pantry at grids 4,C
1 Provide number to glass opening along grid 2 & provide detail at Doors &
Windows schedule.
2 Coordinate height of wall along grid D (1.90 as shown in section B) with sky
light as per section A.
OO6 A104 Roof floor
3 Indicate all ducts at roof.
4 Provide SRI ratio as per DM.
5 Provide slope to drain.
6
Amend Mismatch elevations with plans, i.e. (projected wall beside ladder),
1 (windows of bathroom at ground & first at elev 2 & 4), (kitchen door at
ground)
Review height of glass window & doors noting bedrooms at front elevation
2 designed with large opening while living & dining at back elevation with
smaller opening.
A201 3 Draw the pergola at side elevations 2 & 4 (after grid 8).
OO7 to Elevations
A204 Provide finishes material of (pergola at elevation 3 between grids C,H)
4 (parking shed at elevation 2 & 4), (Columns at elev. 1 at grids A & G), (Walls
of maid at Elev. 1,2,4), ….
5 Review finish No. 2 around window of maid room at Elev.1 with stone at
perspective.
6 Provide levels of all parapets.
1 Coordinate level outside plot limit at Sec. A (+0.15) & at site plan (±0.00).
1 Amend section to indicate FFL & (provide upstand to avoid leaking into tank),
(provide concealed access with finish to match with flooring of pool deck).
O11 A405 U.G.Water T.
2 Amend location of section view at plan at access.
3 Amend location of access at section to match with plan.
1 Amend pool plan to comply with section noting the width of overflow to
pool edge ≈ 50 cm, & Review pool size accordingly
2 Provide overflow at both sides at section to match with plan.
O12 A405 Swimming 3 Provide Typ. Details of swimming pool sections.
Pool Details
4 Amend water level to +0.45 as per ground plan.
5 Provide dimensions & levels.
6 Amend drawing number.
1 Indicate garbage room doors at elevation & resolve door height.
O13 A406 Boundary wall 2 Provide sections at roller shutter gate.
3 Coordinate with Tech. Eng. to specify gate doors, i.e. H.D.G.I.
1 Amend drawing numbers.
2 Coordinate FC at bathrooms with bathroom details.
O14 A102 F. C. layout
3 Provide levels of FC.
4 Amend FC at kitchen to avoid small cut pieces.
1 Amend type of D1, i.e from aluminum swing door to solid wood hinged door.
Architectural Page 3 of 7
Review Comments Report
(Structural)
Project:ALKHUWAILDI villas - Project No. 22761
Date of issue 02-12-2019
Revision No. 0
Drg.
S. No. Drg. Title Comment Description
No.
OO1 General Note
refer to Arch general comment to reduce width of columns at grids (3,C),
1
(3,E) to 20 cm to avoid projection inside the rooms at Gr. & 1st.
OO6 S302 WT Sec. 2 Refer to Arch. Comments on swimming pool Drg. & amend section & plan
Structural Page 4 of 7
Comment
importance
High
Mid
Low
V.E.
Coordinated with MEP Engr and a place has been marked in layout to pass sleeves
Coordinated with MEP Engr and a place has been marked in layout to pass sleeves
Over Head water tank location has been amended in roof layout
provided details for CB1
Waiting for architectural dwgs. To be modified to modify Structural dwg.
Structural Page 5 of 7
Review Comments Report Comment
(Mechanical) importance
Project:ALKHUWAILDI villas - Project No. 22761 High
Date of issue 02-12-2019 Mid
Revision No. 0 Low
V.E.
AC
1 Coordinate with Str. Eng. ducts conflict with beam between grids 3,5 along
grid C & grid E.
OO2 101 Ground floor
Coordinate with Mech. Eng. ducts conflict with beam between grids 5,6
along grid B & grid F.
1 Coordinate with Str. Eng. ducts conflict with beam between grids 3,5 along
OO3 102 1st floor grid C & grid E.
103 Roof 1 Coordinate location of water tank with CU-GF-6
1 Coordinate detail of external column & external drop beam with Arch. &
OO4 U-VALUE Tech. Eng.
DR
1 Revise BDO & CO above living hall with CO, & note this pipe conflict with
O1O 108 Grd. H/L beams along grid C & grid E.
Water Supply
Ground Provide water point for green area on both sides of open shower.
LPG
O18 Ground floor 1 Provide Alu. Louver cabinet to fit gas cylinder.
Mech Page 6 of 7
Review Comments Report Comment
(Electrical) importance
Project:ALKHUWAILDI villas - Project No. 22761 High
Date of issue 02-12-2019 Mid
Revision No. 0 Low
V.E.
Light
1 Coordinate light fittings at bathrooms with FC layout.
2 Remove light fitting at void at mid of stair.
OO2 103 Ground floor
3 Review location of light above entrance steps.
Power