Professional Documents
Culture Documents
Korosi Di Water Cooling
Korosi Di Water Cooling
Korosi Di Water Cooling
Water-Cooling System
By H. B. Lloyd
(Workington Iron and Steel Co.)
The author describes the techniques and designs employed to provide a practical solution to the
corrosion problems of a blast furnace water-cooling system based on a soft-water supply. He discusses,
among other things, the water-cooling system, the external pipework and the stave coolers.
THE length of a blast furnace cam cooler is usually flush with the inside
paign, from the time that the furnace face of the furnace wall, but the
is put on blast until it is finally blown tuyere itself protrudes about 9 to
out, is normally expected to be about 12 in. into the furnace. The tuyeres
five years. During this period the and the tuyere coolers normally each
nature of the repairs which it is prac have independent water feeds from
ticable to carry out are strictly limited. the lower ring mains.
The furnace is lined with refractory In some designs of furnace, the
bricks, the effective cooling of which hearth is above ground level and some
is generally considered to be one of the cooling is achieved simply by spraying
major influences on the life of the water on to the hearth jacket. Where
furnace. The almost universal method the hearth is below ground level, heat
employed1 is the circulation of large passes through the hearth jacket to
quantities of water, and it will be the surrounding earth. Stave coolers
appreciated that the requirement is are mounted within this hearth jacket;
for a steady and uninterrupted flow these consist of massive iron castings
for the entire campaign. Corrosion 12 to 18 ft. long and about 2 to 4 ft.
(or deposition) cannot, therefore, be wide by 6 in. thick. Mild steel pipes
tolerated. are cast into these in order to provide
The cooling-water system may be waterways for cooling. A typical
divided into three parts: arrangement is shown in Fig. 2. It
will be noted that the external con
(1) The stack and bosh. nections for the coolers come out at
(2) The tuyeres. the top. However, in the case of the
(3) The hearth. cooler plates which go below the
Fig. 1 shows a typical arrangement. tapping hole and the slag notch, the
Usually the water is supplied from coolers are not accessible at the top
two circular ring mains, one about and arrangements have to be made
half-way up the furnace stack and one of slightly conical copper castings to bring the connections out from the
at a lower level. Cast copper plates which have hollow walls. Water is front of the cooler plate.
are mounted in pockets in the stack circulated through the annular hollow In the case of the plant with which
and these are normally connected in space and normally each tuyere has its the writer is concerned, the cooling
series of six to twelve plates, the top own feed from the lower of the two water is obtained from a fast-flowing
plate of each series being connected to ring mains. The tuyere is inserted river. The water is recirculated
the ring main. into the furnace through a circular through a pond which is the source of
The tuyeres through which the blast copper cooler, usually known as a water for a number of cooling systems
air is blown into the furnace consist tuyere cooler or jumbo. The tuyere and which is usually some 30°F. above
atmospheric temperature. It is very
TABLE 1 soft and contains much dissolved
C o m p a r i s o n of Rate of Flow of Cooling Water in a 20-ft. H e a r t h - D i a m e t e r oxygen and is consequently highly
Blast Furnace corrosive. Typical analysis of the
(Rate of flow, gallons per minute) water shows:
April April March , April August October pH value ... ... 7.0-7.5
Cooler 1951 1952 1953 1954 1955 1956 Calcium hardness ... 20-60 p.p.m.
g.p.m. g.p.m. g.p.m. g.p.m. g.p.m. g-P-m. Total hardness (in terms
Upper stack ... ... 500 442 407 361 255 204 of CaCO 3 )
Lower stack ... ... 532 417 305 235 554 438 Extreme range ... 30-90 p.p.m.
Bosh ... ... ... 485 367 266 173 182 163 Normal range ... 35-45 p.p.m.
Breast ... ... ... 228 219 156 90 54 50 Chlorides (in terms of
Tuyere ... ... 738 517 425 313 274 192 NaCl) ... ... 25-45 p.p.m.
Jumbo ... ... 778 640 469 329 176 86 Sulphates (in terms of
Stave ... ... ... 1,293 843 581 315 295 431
Miscellaneous... ... 100 75 70 65 36 33 Na.SO 4 ) ... ... 20-45 p.p.m.
... Dissolved oxygen (at
Total ... 4,654 3,520 2,679 1,881 1,826 1,597 77°F.) ... ... 5.0-5.8 mL/litre
Change o f Address
Rediweld Ltd. announce that they
have changed their address from
17 Crompton Way, Crawley, Sussex,
to 17/27 Kelvin Way, Crawley, Sussex.
224 C O R R O S I O N T E C H N O L O G Y July 1957