HARGA SATUAN JUMLAH HARGA KONTRAK ADD 01 MINGGU LALU MINGGU INI S/D MINGGU INI
NO. JENIS PEKERJAAN SAT
(RP.) (RP.) Kuantitas Bobot (%) Kuantitas Bobot (%) Kuantitas Bobot (%) Kuantitas Bobot (%) KETERANGAN
1 2 3 4 5 6 7 8 9 10 11 12 13
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Ls 10.000.000,00 10.000.000,00 1,00 0,32 0,5000 0,1608 - 0,5000 0,1608 50,00%
2 Pekerjaan SMK3 Ls 9.000.000,00 9.000.000,00 1,00 0,29 1,0000 0,2895 - 1,0000 0,2895 100,00%
3 Pemindahan Utilitas (PLN, PDAM, Dll) Ls 182.000.000,00 182.000.000,00 1,00 5,85 0,7700 4,5072 0,0433 0,2537 0,8133 4,7609 81,33%
JUMLAH 201.000.000,00 6,46 4,9575 0,2537 5,2112
II. PEKERJAAN KONSTRUKSI
1 SALURAN DRAINASE JL. HARLIN NAFSI SALURAN DRAINASE LEBAR
2 Galian Tanah Dibuang (Alat) M3 75.000,00 54.000.000,00 720,00 1,74 720,0000 1,7368 - 720,0000 1,7368 100,00%
3 Timbunan Tanah Mekanis M3 100.000,00 39.000.000,00 390,00 1,25 390,0000 1,2543 - 390,0000 1,2543 100,00%
4 Beton K-225 M3 1.500.000,00 509.400.000,00 339,60 16,38 339,6000 16,3835 - 339,6000 16,3835 100,00%
5 Bekisting M2 164.000,00 262.357.360,00 1.599,74 8,44 1.599,7400 8,4380 - 1.599,7400 8,4380 100,00%
6 Pembesian Kg 17.000,00 600.767.590,00 35.339,27 19,32 35.339,2700 19,3221 - 35.339,2700 19,3221 100,00%
7 Pancang Kayu Galam Pangkal 10-15 cm,L=3,75 m (Mekanis) Titik 65.000,00 46.995.000,00 723,00 1,51 723,0000 1,5115 - 723,0000 1,5115 100,00%
JUMLAH 1.512.519.950,00 48,65 48,6461 - 48,6461
III. PLAT PELAYANAN
1 Beton K-225 M3 1.500.000,00 63.000.000,00 42,00 2,03 34,5000 1,6644 6,0000 0,2895 40,5000 1,9539 96,43%
2 Pembesian Kg 17.000,00 106.060.170,32 6.238,83 3,41 5.124,7561 2,8020 891,2619 0,4873 6.016,0181 3,2893 96,43%
3 Bekisting M2 164.000,00 19.286.400,00 117,60 0,62 96,6000 0,5095 16,8000 0,0886 113,4000 0,5981 96,43%
JUMLAH 188.346.570,32 6,06 4,9759 0,8654 5,8413
IV SALURAN DRAINASE JL. PELITA LEBAR = 1.5 M
SALURAN DRAINASE
1 Galian Tanah Dibuang (Alat) M3 75.000,00 36.085.484,72 481,14 1,16 218,6999 0,5275 137,4685 0,3316 356,1684 0,8591 74,03%
2 Timbunan Tanah (Mekanis) M3 100.000,00 37.760.122,85 377,60 1,21 - - - - - 0,00%
3 Beton K-225 M3 1.500.000,00 263.340.000,00 175,56 8,47 107,8400 5,2026 16,6800 0,8047 124,5200 6,0073 70,93%
4 Pembesian M2 17.000,00 304.426.970,28 17.907,47 9,79 13.023,6137 7,1208 232,5645 0,1272 13.256,1782 7,2479 74,03%
5 Bekisting Kg 164.000,00 224.921.991,09 1.371,48 7,23 1.033,0595 5,4490 - 1.033,0595 5,4490 75,32%
6 Pancang Kayu Galam Pangkal 10-15 cm,L=3,75 m (Mekanis) Titik 65.000,00 30.225.000,00 465,00 0,97 213,0000 0,4453 59,0000 0,1233 272,0000 0,5686 58,49%
JUMLAH 896.759.568,93 28,84 18,7452 1,3868 20,1320
V PLAT PELAYANAN
1 Bongkaran Beton M3 30.000,00 202.500,00 6,75 0,01 3,3750 0,0033 - 3,3750 0,0033
2 Pembesian Kg 17.000,00 46.335.744,00 2.725,63 1,49 973,4400 0,5322 - 973,4400 0,5322 35,71%
3 Bekisting M2 164.000,00 7.990.080,00 48,72 0,26 17,4000 0,0918 - 17,4000 0,0918 35,71%
4 Beton K-225 M3 1.500.000,00 24.111.111,11 16,07 0,78 5,7407 0,2770 - 5,7407 0,2770 35,71%
JUMLAH 78.639.435,11 2,53 0,9042 - 0,9042
HARGA SATUAN JUMLAH HARGA KONTRAK ADD 01 MINGGU LALU MINGGU INI S/D MINGGU INI
NO. JENIS PEKERJAAN SAT
(RP.) (RP.) Kuantitas Bobot (%) Kuantitas Bobot (%) Kuantitas Bobot (%) Kuantitas Bobot (%) KETERANGAN
1 2 3 4 5 6 7 8 9 10 11 12 13
VI SALURAN DRAINASE JL. PELITA LEBAR = 1 M
SALURAN DRAINASE
1 Galian Tanah Dibuang (Alat) M3 75.000,00 7.200.000,00 96,00 0,23 - - - - - 0,00%
2 Timbunan Tanah (Mekanis) M3 100.000,00 7.776.000,00 77,76 0,25 - - - - - 0,00%
3 Beton K-225 M3 1.500.000,00 66.240.000,00 44,16 2,13 32,6400 1,5747 - 32,6400 1,5747 73,91%
4 Pembesian M2 17.000,00 81.588.616,30 4.799,33 2,62 4.799,3304 2,6241 - 4.799,3304 2,6241 100,00%
5 Bekisting Kg 164.000,00 51.684.053,33 315,15 1,66 315,1467 1,6623 - 315,1467 1,6623 100,00%
6 Pancang Kayu Galam Pangkal 10-15 cm,L=3,75 m (Mekanis) Titik 65.000,00 9.555.000,00 147,00 0,31 - - - - - 0,00%
JUMLAH 224.043.669,63 7,21 5,8610 - 5,8610
VII PLAT PELAYANAN
1 Bongkaran Beton M3 30.000,00 108.000,00 3,60 0,00 - - - - - 0,00%
2 Pembesian Kg 17.000,00 5.148.416,00 302,85 0,17 - - - - - 0,00%
3 Bekisting M2 164.000,00 413.280,00 2,52 0,01 - - - - - 0,00%
4 Beton K-225 m3 1.500.000,00 2.250.000,00 1,50 0,07 - - - - - 0,00%
JUMLAH 7.919.696,00 0,25 - - -
JUMLAH SELURUHNYA 3.109.228.890,00 100,00 84,0900 2,5058 86,5958
1 RENCANA S/D MINGGUAN INI 87,42 %
2 REALISASI S/D MINGGUAN 86,60 %
DEVIASI -0,82