PEMERINTAH PROVINSI KALIMANTAN TIMUR

DINAS PEKERJAAN UMUM PENATAAN RUANG DAN PERUMAHAN RAKYAT


Alamat : Jalan Tengkawang No. 1 Samarinda Kalimantan Timur Kode Pos 75125
Fax. No. (0541) 275666 Fax. (0541) 275997
Website :http//dpupkaltimprov.go.id email : dpupr.sekumum@gmail.com

LAPORAN KEMAJUAN FISIK MINGGUAN

KEGIATAN : PERENCANAAN, PENGAWASAN DAN PENGELOLAAN SUMBER DAYA AIR KONSULTAN


PEKERJAAN : PENGENDALIAN BANJIR SISTEM LOA JANAN DAN RAPAK DALAM KOTA SAMARINDA NO. KONTRAK // ADD 01 : 602/Bid-SDA/KPA/368/VI/2019 // 602/Bid-SDA/KPA/572.C/VIII/2019
NO. KONTRAK AWAL // ADD 1 : 602/Bid-SDA/KPA/354.D/VI/2019 // 602/Bid-SDA/KPA/475.A/VII/2019 TANGGAL KONTRAK // ADD 01 : 27 Juni 2019 // 14 Agustus 2019
NILAI KONTRAK / NILAI ADD1 : Rp 3.420.151.779,00 / Rp 3.420.151.779,00 PERIODE : 25 November 2019 S/D 01 Desember 2019
TANGGAL KONTRAK : Selasa, 25 Juni 2019 MINGGU : KE - 21 ( DUA PULUH SATU )
WAKTU PELAKSANAAN : 180 ( SERATUS DELAPAN PULUH ) HARI KALENDER

HARGA SATUAN JUMLAH HARGA KONTRAK ADD 01 MINGGU LALU MINGGU INI S/D MINGGU INI
NO. JENIS PEKERJAAN SAT
(RP.) (RP.) Kuantitas Bobot (%) Kuantitas Bobot (%) Kuantitas Bobot (%) Kuantitas Bobot (%) KETERANGAN
1 2 3 4 5 6 7 8 9 10 11 12 13
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Ls 10.000.000,00 10.000.000,00 1,00 0,32 0,5000 0,1608 - 0,5000 0,1608 50,00%
2 Pekerjaan SMK3 Ls 9.000.000,00 9.000.000,00 1,00 0,29 1,0000 0,2895 - 1,0000 0,2895 100,00%
3 Pemindahan Utilitas (PLN, PDAM, Dll) Ls 182.000.000,00 182.000.000,00 1,00 5,85 0,7700 4,5072 0,0433 0,2537 0,8133 4,7609 81,33%
JUMLAH 201.000.000,00 6,46 4,9575 0,2537 5,2112
II. PEKERJAAN KONSTRUKSI
1 SALURAN DRAINASE JL. HARLIN NAFSI SALURAN DRAINASE LEBAR
2 Galian Tanah Dibuang (Alat) M3 75.000,00 54.000.000,00 720,00 1,74 720,0000 1,7368 - 720,0000 1,7368 100,00%
3 Timbunan Tanah Mekanis M3 100.000,00 39.000.000,00 390,00 1,25 390,0000 1,2543 - 390,0000 1,2543 100,00%
4 Beton K-225 M3 1.500.000,00 509.400.000,00 339,60 16,38 339,6000 16,3835 - 339,6000 16,3835 100,00%
5 Bekisting M2 164.000,00 262.357.360,00 1.599,74 8,44 1.599,7400 8,4380 - 1.599,7400 8,4380 100,00%
6 Pembesian Kg 17.000,00 600.767.590,00 35.339,27 19,32 35.339,2700 19,3221 - 35.339,2700 19,3221 100,00%
7 Pancang Kayu Galam Pangkal 10-15 cm,L=3,75 m (Mekanis) Titik 65.000,00 46.995.000,00 723,00 1,51 723,0000 1,5115 - 723,0000 1,5115 100,00%
JUMLAH 1.512.519.950,00 48,65 48,6461 - 48,6461
III. PLAT PELAYANAN
1 Beton K-225 M3 1.500.000,00 63.000.000,00 42,00 2,03 34,5000 1,6644 6,0000 0,2895 40,5000 1,9539 96,43%
2 Pembesian Kg 17.000,00 106.060.170,32 6.238,83 3,41 5.124,7561 2,8020 891,2619 0,4873 6.016,0181 3,2893 96,43%
3 Bekisting M2 164.000,00 19.286.400,00 117,60 0,62 96,6000 0,5095 16,8000 0,0886 113,4000 0,5981 96,43%
JUMLAH 188.346.570,32 6,06 4,9759 0,8654 5,8413
IV SALURAN DRAINASE JL. PELITA LEBAR = 1.5 M
SALURAN DRAINASE
1 Galian Tanah Dibuang (Alat) M3 75.000,00 36.085.484,72 481,14 1,16 218,6999 0,5275 137,4685 0,3316 356,1684 0,8591 74,03%
2 Timbunan Tanah (Mekanis) M3 100.000,00 37.760.122,85 377,60 1,21 - - - - - 0,00%
3 Beton K-225 M3 1.500.000,00 263.340.000,00 175,56 8,47 107,8400 5,2026 16,6800 0,8047 124,5200 6,0073 70,93%
4 Pembesian M2 17.000,00 304.426.970,28 17.907,47 9,79 13.023,6137 7,1208 232,5645 0,1272 13.256,1782 7,2479 74,03%
5 Bekisting Kg 164.000,00 224.921.991,09 1.371,48 7,23 1.033,0595 5,4490 - 1.033,0595 5,4490 75,32%
6 Pancang Kayu Galam Pangkal 10-15 cm,L=3,75 m (Mekanis) Titik 65.000,00 30.225.000,00 465,00 0,97 213,0000 0,4453 59,0000 0,1233 272,0000 0,5686 58,49%
JUMLAH 896.759.568,93 28,84 18,7452 1,3868 20,1320
V PLAT PELAYANAN
1 Bongkaran Beton M3 30.000,00 202.500,00 6,75 0,01 3,3750 0,0033 - 3,3750 0,0033
2 Pembesian Kg 17.000,00 46.335.744,00 2.725,63 1,49 973,4400 0,5322 - 973,4400 0,5322 35,71%
3 Bekisting M2 164.000,00 7.990.080,00 48,72 0,26 17,4000 0,0918 - 17,4000 0,0918 35,71%
4 Beton K-225 M3 1.500.000,00 24.111.111,11 16,07 0,78 5,7407 0,2770 - 5,7407 0,2770 35,71%
JUMLAH 78.639.435,11 2,53 0,9042 - 0,9042
HARGA SATUAN JUMLAH HARGA KONTRAK ADD 01 MINGGU LALU MINGGU INI S/D MINGGU INI
NO. JENIS PEKERJAAN SAT
(RP.) (RP.) Kuantitas Bobot (%) Kuantitas Bobot (%) Kuantitas Bobot (%) Kuantitas Bobot (%) KETERANGAN
1 2 3 4 5 6 7 8 9 10 11 12 13
VI SALURAN DRAINASE JL. PELITA LEBAR = 1 M
SALURAN DRAINASE
1 Galian Tanah Dibuang (Alat) M3 75.000,00 7.200.000,00 96,00 0,23 - - - - - 0,00%
2 Timbunan Tanah (Mekanis) M3 100.000,00 7.776.000,00 77,76 0,25 - - - - - 0,00%
3 Beton K-225 M3 1.500.000,00 66.240.000,00 44,16 2,13 32,6400 1,5747 - 32,6400 1,5747 73,91%
4 Pembesian M2 17.000,00 81.588.616,30 4.799,33 2,62 4.799,3304 2,6241 - 4.799,3304 2,6241 100,00%
5 Bekisting Kg 164.000,00 51.684.053,33 315,15 1,66 315,1467 1,6623 - 315,1467 1,6623 100,00%
6 Pancang Kayu Galam Pangkal 10-15 cm,L=3,75 m (Mekanis) Titik 65.000,00 9.555.000,00 147,00 0,31 - - - - - 0,00%
JUMLAH 224.043.669,63 7,21 5,8610 - 5,8610
VII PLAT PELAYANAN
1 Bongkaran Beton M3 30.000,00 108.000,00 3,60 0,00 - - - - - 0,00%
2 Pembesian Kg 17.000,00 5.148.416,00 302,85 0,17 - - - - - 0,00%
3 Bekisting M2 164.000,00 413.280,00 2,52 0,01 - - - - - 0,00%
4 Beton K-225 m3 1.500.000,00 2.250.000,00 1,50 0,07 - - - - - 0,00%
JUMLAH 7.919.696,00 0,25 - - -
JUMLAH SELURUHNYA 3.109.228.890,00 100,00 84,0900 2,5058 86,5958
1 RENCANA S/D MINGGUAN INI 87,42 %
2 REALISASI S/D MINGGUAN 86,60 %
DEVIASI -0,82

MENGETAHUI, DIPERIKSA DIBUAT OLEH,


KOORDINATOR LAPANGAN KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
PERENCANAAN, PENGAWASAN DAN PENGELOLAAN PT. ARISTA GEMILANG KONSULINDO CV. ANQI JAYA
SUMBER DAYA AIR

SUJADI ANDI SADDAM SAID, ST PURNOMO RUSLAN, ST


NIP. 19670826 200604 1 005 INSPECTOR PELAKSANA LAPANGAN