Back-up Computation

ITEM NO. Discription


103(6)a Pipe Culverts and Drain Excavation Length Width Thickness
104(2)a Embankment from Borrow
201(1) Aggregate Base Course
311(1)b1 PCC Pavement (Unreinforced)
Length (m) Width (m) Thickness (m)
AREA 1 - Cross Drainage between Sports
14.50 2.10 0.25
Complex and San Nicolas Church

AREA 2 -Cross Drainage between BFP


22.50 2.10 0.30
and San Nicolas Church

AREA 3 - Cross Drainage between BFP


9.00 2.10 0.25
and Pasil Public Market

AREA 4 - Cross Drainage between Public


10.00 2.15 0.25
Market and Meat Shop

AREA 5 - Cross Drainage betwee San Nicolas


13.00 2.10 0.30
Church and Rose Pharmacy

Total Volume
Vol. (cu.m)
30.45 0.25 7.6125
7.6125
47.25 0.3 14.175
18.9 0.25 4.725
21.5 0.25 5.375
14.175
27.3 0.3 8.19

4.725

5.375

8.19

40.0775