Project Time Schedule

Project: Osmani Memorial Auditorium


Sl No Description of Works Client Scope 5-Nov 6-Nov 7-Nov 8-Nov 9-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov

7 Templating

8 Wall Bracket Fitting

9 Guide Rail Mounting

12 Scaffold Remove, Motor Setting

13 Motor Align, Rope, Cabin Setting

14 Door Frame Fitting

16 Wiring, LOP, COP

19 Slow Speed,

20 High Speed Test, Commissioning

Total working days - 12 days.