ESTIMATE FOR RESECTIONING OF MURALA DISTY RD.

0+000
TO 41+556 TAIL.

ABSTRACT OF QUANTITY AND COST.

Sr No. Descriptons Unit Rate Quantity Amount

Earthwork in excavation of drains, irrigation channels


through excavator / drag lines in all kind of soil and
conditions(dry,wet, slush,daldal and under water)
1 including its disposal and prepartion of working pad 1000 2185.00 99220 216796
for operation of machinery

(Rate includes 100 ft lead).


Ch = 3, P = 33, Item No.
52.
Uprooting Sarkanda growth and disposal within 100
2 ft. (30 m) 100 73.10 60114 43943
Ch = 3, Item No. 48.

TOTAL = 260739
Add PST 16% = 41718
Grand Total = 302457

Sub-Engineer Sub Divisional Officer


Chillianwala Section Sohawa Sub Division UJC
Mandi Bahauddin

Certified that I am satisfied about the necessity, its correctness and provision made in the
estimate.

Sub Divisional Officer


Sohawa Sub Division UJC
Mandi Bahauddin

Certified that I have inspected the site and satisfied myself about the correctness of estimate
by visual inspection.

EXECUTIVE ENGINEER
GUJRAT DIVISION UJC
GUJRAT
16
ESTIMATE FOR RESECTIONING OF MURALA DISTY RD.0+000 TO 41+556 TAIL.

Uprooting Sarkanda growth and disposal within 100 ft

Sr.No RD. side Contants.


1 11+000-12+000 L 3 ft x 400 = 1200 Sft
R 2 ft x 200 = 400 Sft
2 12+000-13+000 L 3 ft x 400 = 1200 Sft
R 2 ft x 300 = 600 Sft
3 13+000-14+000 L 3 ft x 350 = 1050 Sft
R 0 ft x 0 = 0 Sft
4 14+000-15+000 L 3 ft x 300 = 900 Sft
R 0 ft x 0 = 0 Sft
5 15+000-16+000 L 3.5 ft x 250 = 875 Sft
R 0 ft x 0 = 0 Sft
6 21+000-22+000 L 2 ft x 250 = 500 Sft
R 3 ft x 350 = 1050 Sft
7 22+00-23+000 L 4 ft x 500 = 2000 Sft
R 5 ft x 600 = 3000 Sft
8 23+000-24+000 L 4.5 ft x 800 = 3600 Sft
R 4 ft x 750 = 3000 Sft

TOTAL = 19375 Sft

Sub-Engineer Sub Divisional Officer


Chillianwala Section Sohawa Sub Division UJC
Mandi Bahauddin