FROM TO LENGTH (m) SIZE (mm²) IAMP R

TRANSFORMER SERVICE DROP 25 50 50 0.012


SERVICE DROP PB (MAIN) 20 500 500 0.018
PB (MAIN) PB1 15 3.5 28.44 2
PB (MAIN) PB2 15 3.5 20.11 2
PB (MAIN) PB3 15 3.5 24.87 2
PB (MAIN) PB4 15 3.5 10.78 2
PB (MAIN) PB5 20 3.5 28.4325 2
PB (MAIN) PB6 20 3.5 20.11 2
PB (MAIN) PB7 20 3.5 24.87 2
PB (MAIN) PB8 20 3.5 10.78 2
PB (MAIN) PB9 25 3.5 28.4325 2
PB (MAIN) PB10 25 3.5 20.11 2
PB (MAIN) PB11 25 3.5 25.63 2
PB (MAIN) PB12 25 3.5 7.82 2

IFAULT=(1/PUT+PUT+PUSDPBMAIN)(VA BASE/VBASE) OHZ=(Z/305)(L)


IFAULT=(1/0.05+2.8868+7.7474×10¯⁹)(100KVA BASE/3(400)) OHZ=(0.05/305)(15)
IFAULT=0.04915 OHZ=2.4590×10¯³

PUMAIN-PB1=(OHZ/KV²)(KVA BASE/1000)
PUMAIN-PB1=(2.4590×10¯³/230²)(100KVA BASE/1000)
PUMAIN-PB1=4.6484×10¯⁹

IFAULT=(1/PUT+PUT+PUSDPB1)(VA BASE/VBASE)
IFAULT=(1/0.05+2.8868+4.6484×10¯⁹)(100KVA BASE/3(400))
IFAULT=0.04915

PBMAIN-PB2=(OHZ/KV²)(KVA BASE/1000)
PUMAIN-PB2=(2.4590×10¯³/230²)(100KVA BASE/1000)
PUMAIN-PB2=4.6484×10¯⁹

IFAULT=(1/PUT+PUTSD+PBMAINPB2)(VA BASE/VBASE)
IFAULT=(1/0.05+2.8868+4.6484×10¯⁹)(100KVA BASE/3(400))
IFAULT=0.04915

PBMAIN-PB3=(OHZ/KV²)(KVA BASE/1000)
PBMAIN-PB3=(2.4590×10¯³/230²)(100KVA BASE/1000)
PBMAIN-PB3=4.6484×10¯⁹

IFAULT=(1/PUT+PUTSD+PBMAINPB3)(KVA BASE/1000)
IFAULT=(1/0.05+2.8868+4.6484×10¯⁹)(100KVA BASE/3(400))
IFAULT=0.04915
PBMAIN-PB4=(OHZ/KV²)(KVA BASE/1000)
PBMAIN-PB4=(2.4590×10¯³/230²)(100KVA BASE/1000)
PBMAIN-PB4=4.6484×10¯⁹

IFAULT=(1/PUT+PUTSD+PBMAINPB4)(KVA BASE/1000)
IFAULT=(1/0.05+2.8868+4.6484×10¯⁹)(100KVA BASE/3(400))
IFAULT=0.04915

OHZ=(Z/305)(L)
OHZ=(0.05/305)(20)
OHZ=3.2787×10¯³

PBMAIN-PB5=(OHZ/KV²)(KVA BASE/1000)
PBMAIN-PB5=(3.2787×10¯³/230²)(100KVA BASE/1000)
PBMAIN-PB5=8.9459×10¯⁹

IFAULT=(1/PUT+PUTSD+PBMAINPB5)(VA BASE/VBASE)
IFAULT=(1/0.05+2.8868+8.9459×10¯⁹)(100KVA BASE/3(400))
IFAULT=0.049147

PBMAIN-PB6=(OHZ/KV²)(KVA BASE/1000)
PBMAIN-PB6=(3.2787×10¯³/230²)(100KVA BASE/1000)
PBMAIN-PB6=8.9459×10¯⁹

IFAULT=(1/PUT+PUTSD+PBMAINPB6)(KVA BASE/1000)
IFAULT=(1/0.05+2.8868+8.9459×10¯⁹)(100KVA BASE/3(400))
IFAULT=0.049147

PBMAIN-PB7=(OHZ/KV²)(KVA BASE/1000)
PBMAIN-PB7=(3.2787×10¯³/230²)(100KVA BASE/1000)
PBMAIN-PB7=8.9459×10¯⁹

IFAULT=(1/PUT+PUTSD+PBMAINPB7)(VA BASE/VBASE)
IFAULT=(1/0.05+2.8868+8.9459×10¯⁹)(100KVA BASE/3(400))
IFAULT=0.049147

PBMAIN-PB8=(OHZ/KV²)(KVA BASE/1000)
PBMAIN-PB8=(3.2787×10¯³/230²)(100KVA BASE/1000)
PBMAIN-PB8=8.9459×10¯⁹

IFAULT=(1/PUT+PUTSD+PBMAINPB8)(VA BASE/VBASE)
IFAULT=(1/0.05+2.8868+8.9459×10¯⁹)(100KVA BASE/3(400))
IFAULT=0.049147

OHZ=(Z/305)(L)
OHZ=(0.05/305)(25)
OHZ=4.0984×10¯³

PBMAIN-PB9=(OHZ/KV²)(KVA BASE/1000)
PBMAIN-PB9=(4.0984×10¯³/230²)(100KVA BASE/1000)
PBMAIN-PB9=1.1182×10¯⁹

IFAULT=(1/PUT+PUTSD+PBMAINPB9)(VA BASE/VBASE)
IFAULT=(1/0.05+2.8868+1.1182×10¯⁹)(100KVA BASE/3(400))
IFAULT=0.0341

PBMAIN-PB10=(OHZ/KV²)(KVA BASE/1000)
PBMAIN-PB10=(4.0984×10¯³/230²)(100KVA BASE/1000)
PBMAIN-PB10=1.1182×10¯⁹

IFAULT=(1/PUT+PUTSD+PBMAINPB10)(VA BASE/VBASE)
IFAULT=(1/0.05+2.8868+1.1182×10¯⁹)(100KVA BASE/3(400))
IFAULT=0.0341

PBMAIN-PB11=(OHZ/KV²)(KVA BASE/1000)
PBMAIN-PB11=(4.0984×10¯³/230²)(100KVA BASE/1000)
PBMAIN-PB11=1.1182×10¯⁹

IFAULT=(1/PUT+PUTSD+PBMAINPB11)(VA BASE/VBASE)
IFAULT=(1/0.05+2.8868+1.1182×10¯⁹)(100KVA BASE/3(400))
IFAULT=0.0341

PBMAIN-PB12=(OHZ/KV²)(KVA BASE/1000)
PBMAIN-PB12=(4.0984×10¯³/230²)(100KVA BASE/1000)
PBMAIN-PB10=1.1182×10¯⁹

IFAULT=(1/PUT+PUTSD+PBMAINPB10)(VA BASE/VBASE)
IFAULT=(1/0.05+2.8868+1.1182×10¯⁹)(100KVA BASE/3(400))
IFAULT=0.0341
X VD %VD IFAULT PUT= (5%/100)=0.05
0.055 0.2307 0.1003 2.8868
0.046 1.6196 0.7042 0.04195
0.068 2.7989 1.2169 0.04195
0.068 1.9792 0.8605 0.04195 IFAULT T-SD= (1/PUT+PUW)(VA BASE/VBASE)
0.068 2.4476 1.0642 0.04195 Where VBASE= 3(400)
0.068 1.0609 0.4613 0.04195 IFAULT T-SD= (1/0.05+7.7474×10¯⁹)(100 KVA BASE/3(400))=2.8868
0.068 3.7310 1.6222 0.049147 PUSB-PB= (OHZ/KV2)(KVA BASE/1000)
0.068 2.6389 1.1473 0.049147 PUSB-PB= (4.0984×10¯³/2302)(100KVA BASE/1000)
0.068 3.2635 1.4189 0.049147 PUSB-PB= (OHZ/KV2)(KVA BASE/1000)
0.068 1.4146 0.6150 0.049147 PUSB-PB= 7.7474×10¯⁹
0.068 4.6638 2.0277 0.0341
0.068 3.2986 1.4342 0.0341
0.068 4.2041 1.8279 0.0341
0.068 1.2827 0.5577 0.0341
OHZ=(Z/305)(L) PUW=(OHZ/KV2)(KVA BASE/1000)
OHZ=(0.05/305)(25) PUW=(4.0984×10¯³/2302)(100KVA BASE/1000)
OHZ=4.0984×10¯³ PUW=7.7474×10¯⁹

A BASE/VBASE)

10¯⁹)(100 KVA BASE/3(400))=2.8868

02)(100KVA BASE/1000)