Professional Documents
Culture Documents
Also, you have identified many differences between your plan and the initial project objective in
terms of timing, budget, staffing, or other stated goals. If there were important goals that are not
consistent the the current plans, you met with your sponsorship and worked to remedy them
through constraints management and plan optimization. Lastly, you have summarized the data
and presented to your sponsor.
WHAT TO DO?
Now, you have to finalize your documentation.
1. Include an executive summary of the plan, as well as resource and cost analysis, schedule,
risk plans, and other pertinent information. Presenting great volumes of planning
information may be more distracting than helpful, so plan to bring detailed information
along mainly for reference.
2. If you will be negotiating project changes before setting a baseline, prepare to justify
necessary modifications with credible information, and develop two or more proposals
outlining realistic projects with solid business cases.
3. Set up a meeting with your sponsor, requesting sufficient time to discuss the project and
gain agreement in your plans. Before the meeting, practice your presentation with a team
member or two and encourage their criticism (Only the Project Manager will have a
meeting with the Sponsor). Following the planning process, you are the world authority
on your project; rehearse your presentation, and use your strengths: your project
experience, your background and skills, and your enthusiasm for the project.
4. When necessary, shift project objectives using fact-based negotiation and consensus-
building for your ideas Convince project sponsors and stakeholders to support a project
that makes sense and serves everyone’s interests.
5. Following presentation of the project plans, seek agreement on a specific deliverable, a
resource commitment, and a deadline, all consistent with a feasible plan.
6. Validate the plan and verify that the resulting objective is acceptable both to the project
sponsor and to your project team.
7. Confirm stakeholder support and use your baseline for stakeholder-expectation
management.
8. Set the baseline plan of record using your project plans.
a. Publish the final version of the project document.
b. Communicate plans and arrange for distribution to and access by the project
team, online if possible.
c. Save a baseline schedule if you are using a software tool for project management
(try accessing project management tools online, i.e. Trello)
d. Freeze all specifications, and begin integrating change control and scope change
control.
9. Use the project baseline for Project Plan Execution (FINAL PROJECT). Structure status
collection with it, and use it as the foundation for performance reporting.
10. Never change a baseline without using your change control processes, and keep track of
any modifications made during the project.
Make sure that you have refined the contents of the following sections:
Requirement Collection
Scope Definition
Work Breakdown Structure
Activity Definition, Sequencing, Resource Estimates, & Duration Estimates
Schedule Development
Cost Budgeting
Resource Leveling
Risk Identification and Management Planning
Qualitative and Quantitative Risk Analysis
Risk Response Planning
Project Plan Development
Option 1: Make:
Total Cost:
Option 2: Buy:
Total Cost:
Cost Difference:
Recommendation:
Change Request
Date
Project Name:
Date Request Submitted:
Title of Change Request:
Change Order Number:
Submitted by:
Change Category: Scope Schedule Cost Technology Other
Required approvals:
Name/Title Date Approve/Reject
Business Case for Project Name
Date
Project name:
.
5.0 Analysis of Options and Recommendation
10.0 Exhibits
Risk Management Plan
Date
Project Name:
1. Methodology
4. Risk Categories
6. Risk Documentation
Project Management Plan Version 1.0
Date
Project Name:
Introduction/Overview of Project
Project Organization
Management Processes:
Technical Processes:
Work to Be Performed
Schedule Information
Budget Information
2. Delivery of the Work: The Seller agrees to deliver to the Buyer the Work in form and
content acceptable to the Buyer on or before the dates outlined in Exhibit B of this
Agreement, time being of the essence to the Buyer.
3. Right to Terminate: If the Seller materially departs from the agreed-upon schedule or
if the Work is not satisfactory to the Buyer (based on reviews of drafts, market
conditions, and/or other criteria as determined by the Buyer), the Buyer may at its
option:
A. Allow the Seller to finish, correct, or improve the Work by a date specified by the
Buyer;
B. Terminate this Agreement by giving written notice to the Seller.
4. Payments: The Buyer will pay the Seller _________________ upon accepted
completion of the Work.
Buyer Seller
By: ________________________ ____________________________
Date: ________________________ ____________________________