Design Team

S.No Screen Name Current Phase Design TarDesign star


1st Phase
1 Splash screen-1 Development 5-Jun 4-Jun
2 Splash screen-2 Development 5-Jun 4-Jun
3 Splash screen-3 Development 5-Jun 4-Jun
4 Sign in Development 6-Jun 6-Jun
5 Sign in with pattern Development 7-Jun 7-Jun
6 Forgot pattern Development 7-Jun 7-Jun
7 New pattern Development 8-Jun 8-Jun
8 New pattern confirmation Development 10-Jun 10-Jun
9 New pattern success Development 11-Jun 11-Jun
10 Sign in with pin Development 12-Jun 12-Jun
11 Forgot pin Development 13-Jun 13-Jun
12 New pin Development 14-Jun 14-Jun
13 New pin confirmation Development 17-Jun 17-Jun
14 New pin success Development 18-Jun 18-Jun
15 Dashboard Development 20-Jun 19-Jun
16 My profile Development 25-Jun 21-Jun
17 Menu Development 26-Jun 26-Jun

Delays (30th, 1st, 3rd and 4th)


2nd Phase
18 ePRAN Design 13-Aug 12-Aug
19 PoP Detail Design 16-Aug 14-Aug
20 PoP-SP Details Design 17-Aug 17-Aug
21 Contribution Design 21-Aug 19-Aug
22 Contribution (After OTP generation) Design 21-Aug 19-Aug
23 Contribution (After OTP submission) Design 21-Aug 19-Aug
24 Contribution Successful Design 21-Aug 19-Aug
25 Generate password Design 22-Aug 22-Aug
26 Log out /Rate Us Design 23-Aug 23-Aug
27 Notifications Design 24-Aug 24-Aug
29 Support (Log Grievance) Design 28-Aug 27-Aug
30 Support - Missed Call Service Design 28-Aug 27-Aug
31 Support - Call Us Design 28-Aug 27-Aug
32 Logout /Rate Us Design 29-Aug 29-Aug
40 Statement - Generate Statement Design 9-Sep 6-Sep
41 Statement - Download SOT Design 9-Sep 6-Sep
42 Statement - Contribution Receipt Design 9-Sep 6-Sep
43 Setting - Set MPIN Design 12-Sep 10-Sep
44 Setting - Set Pattern Design 12-Sep 10-Sep
45 Setting - Change password Design 12-Sep 10-Sep
46 Setting - Change Language Design 12-Sep 10-Sep
47 Setting - Update Contact Details Design 12-Sep 10-Sep
48 Setting - Help Design 12-Sep 10-Sep
40 Live Chat Design + Functionality

3rd Phase - Assigned to Narayana


28 Request Status View Design 26-Aug 26-Aug
34 Scheme Change Design 3-Sep 30-Aug
35 Tier-2 Withdrawal Design 3-Sep 30-Aug
37 One way switch Design 3-Sep 30-Aug
39 NAV Design 5-Sep 4-Sep
49 FATCA Design 13-Sep 13-Sep

For
21 Contribution
22 Contribution (After OTP generation)
23 Contribution (After OTP submission)
24 Contribution Successful
Design Team Product Android
Design eHTML Desgin Approved Target Start End Status

9-Aug 16-Aug 13-Aug 16-Aug Done✅


9-Aug 16-Aug 13-Aug 16-Aug Done✅
9-Aug 16-Aug 13-Aug 16-Aug Done✅
9-Aug 21-Aug 19-Aug 21-Aug Done✅
9-Aug 23-Aug 22-Aug 23-Aug Done✅
9-Aug 26-Aug 26-Aug 26-Aug Done✅
9-Aug 27-Aug 27-Aug 27-Aug Done✅
9-Aug 28-Aug 28-Aug 28-Aug Done✅
9-Aug 29-Aug 29-Aug 29-Aug Done✅
9-Aug 30-Aug 30-Aug 30-Aug Done✅
9-Aug 3-Sep 3-Sep 3-Sep Done✅
9-Aug 4-Sep 4-Sep 4-Sep Done✅
9-Aug 5-Sep 5-Sep 5-Sep Done✅
9-Aug 6-Sep 6-Sep 6-Sep Done✅
9-Aug 13-Sep 9-Sep 13-Sep Done✅
9-Aug 24-Sep 16-Sep 24-Sep Done✅
9-Aug 26-Sep 25-Sep 26-Sep Done✅

Kfinkart Voice Issues

7-Oct 7-Oct 7-Oct Done✅


9-Oct 9-Oct 9-Oct Done✅
10-Oct 10-Oct 10-Oct Done✅
14-Oct 11-Oct 14-Oct Done✅
16-Oct 15-Oct 16-Oct Done✅
22-Oct 17-Oct 22-Oct Done✅
25-Oct 23-Oct 25-Oct Done✅
30-Oct 29-Oct 30-Oct Done✅
31-Oct 31-Oct 31-Oct Done✅
1-Nov 1-Nov 1-Nov Done✅
6-Nov 4-Nov Done✅
7-Nov 7-Nov Done✅
8-Nov 8-Nov Done✅
same as 26th row Done✅
11-Nov 11-Nov Done✅
13-Nov 12-Nov Done✅
14-Nov 14-Nov Done✅
15-Nov 15-Nov 15-Nov Done✅
18-Nov 18-Nov 18-Nov Done✅
19-Nov 19-Nov 19-Nov Done✅
20-Nov 20-Nov 20-Nov Done✅
21-Nov 21-Nov 21-Nov Done✅
22-Nov 22-Nov 22-Nov Done✅
Done Done Done✅

26-Nov 24-Nov
23-Nov 20-Nov Done✅
14-Nov 11-Nov Done✅
19-Nov 15-Nov Done✅
10-Nov 5-Nov Done✅
29-Nov 27-Nov Done✅

For iOS
iOS QA UAT
Start Date End Date QA Start Date QA End Date UAT Start Date

13-Aug 16-Aug
13-Aug 16-Aug
13-Aug 16-Aug
19-Aug 21-Aug
22-Aug 23-Aug
26-Aug 26-Aug
27-Aug 27-Aug
28-Aug 28-Aug
29-Aug 29-Aug
30-Aug 30-Aug
3-Sep 3-Sep
4-Sep 4-Sep
5-Sep 5-Sep
6-Sep 6-Sep
9-Sep 13-Sep
16-Sep 24-Sep
25-Sep 26-Sep

System Slow

7-Oct 7-Oct
9-Oct 9-Oct
10-Oct 10-Oct
14-Oct 11-Oct
16-Oct 15-Oct
22-Oct 17-Oct
25-Oct 23-Oct
30-Oct 29-Oct
31-Oct 31-Oct
1-Nov 1-Nov
6-Nov 4-Nov
7-Nov 7-Nov
8-Nov 8-Nov
same as 26th row
11-Nov 11-Nov
13-Nov 12-Nov
14-Nov 14-Nov
15-Nov 15-Nov
18-Nov 18-Nov
19-Nov 19-Nov
20-Nov 20-Nov
21-Nov 21-Nov
22-Nov 22-Nov
6-Jan 6-Jan

13-Dec 9-Dec
20-Dec 16-Dec
26-Dec 23-Dec
31-Dec 30-Dec
3-Jan 2-Jan
28-Nov 25-Nov

Induction
10-Jan 7-Jan
16-Jan 13-Jan
20-Jan 17-Jan
22-Jan 21-Jan
UAT Development
UAT End Date Live Date
S.Nopng namfeedback
1 Dashboalast 5 contributions--to add S
2 dashboardc colors to be changed
3 cureent value, cost value, withdrawal and profit to be displayed
4 10 digits for current value, cost val and profit
6 Adding a Total Tab
7 Include commas everywhere
12 address, bank, scheme, nominee, nodal office details
13 icon change for nod ofc and => POP + SP
8 Remove word Scheme
9 in contr, contr date should be displayed as 08-Jan-2019
10 Set total in place of tot contr.
11 In tab bar, set contribute in place of contribution
14 remove rate us
5 Remove as on in top of pie chart
15
16
17
type status
spelling Done✅
syamala to give color codes Done✅
backend

syamala to get back Later


backend

Done✅
Done✅
Done✅
Done✅
Done✅