Client : SPVB

Subject : Separate power route for HP compressor


Contractor : TDH Viet Nam
ESTIMATION SCHEDULE OF INSTALLATION WORK
Oct Nov Dec
Remark
No. Description 5 10 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

I Equipment & material delivery schedule Delivery on Site

1 Busway system
Delivery on Site
2 Power panel (DB-COMP-2)
Delivery on Site
3 Capacitor panel
Delivery on Site
4 Cable & trunking & Other

II Installation work

1 Preparation work & safety traning

2 Opening hole for new busway at electrical room

3 Foundation for panel

4 Support for busway

5 Support for cable rack

6 Cable rack installation Request Power turn-off

7 Panel installation
Request Power turn-off
8 Busway installation
Temporary cable connection to DB_COMP for runing
9 Cable connection work for HP4, HP6
Request Power turn-off by each Panel (discussion later)
8 Cable connection work for Capacitor panel

9 Test & Commisioning

III Handover work

1 Handover document

2 TDH internal inspection


COC sign
3 SPVB inspection

4 Defect work

5 Training & handover