You are on page 1of 30
Name of work NOTE : “The following points should be cleared in the report and covering letter while submitting the detailed plans and estimates to the Collector. * 'a) Whether the road is included in the revised 1961-81 Road Development Plan. b) Whether the earth work is done during scarcity programme/Under E.G.S. earlier. ¢) The funds required for taking up the items of work urider non E.G.S. component from D.P.0.C. ) The ratio of EGS / Non EGS component worked out. Provisions for land acquisition is not done in this estimate. However, it shall be done whenever necessary. a) The items of carting of materials shall be included under Part - B - I! - (Materials) E.G.S. Com- structions contained under Govt.Cir- (P.W. & H) Dept. No. EGS-3779/(1889)-Desk-29 dated 12.10.79 b) Ifthe Metals available already broken under scarcity or under EGS al the quarries inthe vicinity, the provision shall be made for carting only. ‘The rate for labour items provided in the Schedule of Rates for EGS works shall be followed. The rates shall be provided as perthe GSR. Items not provided in the schedule of rates for EGS work with 10 % reduction. For other items the rates shall be as per G.S.R. of the District 5. __Theprovision for murum blanketing 80mm. Over size metal need not be made in non B.C.Scll Area. ‘The soll should also be provided using the saine soil instead of murum. | MRE ETT SSA TS ES (4) ORIGINAL: — Technical Sanction No. : Gate Se Administrative Approval No, Date: ee E.G.S. (P.W.) DIVISION, GONDIA ORIGINAL ESTIMATES Name of work : iGoniein: of See a ee Tahsi| ______ District: Bhandara_—_ Length km, Amounting of estimate Re. . _ Asper 1981-2001 Road Development Plan Serial No. Page No. Asper Annual Plan Serial No. of Proforma ________ Page No. ‘Technical Sanction No. EE/EGSI9_9 Dated / 19__ Amount for Rupees Administrative Approved No. TJEN.SJAAI Dated =f 19 Amount for Rupees : Sr.No, Particulars Page 1 Face Sheets 1103 2. 3: 4, 6 7. 8. 9. 10. " 12, 13, 14, 15, 16. Fa = ae po INDEX Contiticates Check List General Abstract General Report Abstract ‘Abstract for EGS Component Abstract of non-EGS Component EGS Component Measurement ‘Measurements for transportation of materials CSR Rates for 1991-92 Rates for loading, unloading, stacking & transportation of materials for 1991-92 for: Rate Analysis Quarry Chan Type / CIS of Road common CSR, 4105 6107 Bt08 91010 111012 131016 171017 181021 2210.22 2310.23 2410.24 2510.25 2610 26 271027 (3) ESTIMATES xecutlve Engineer E.G.S. (P.W.) Division, Gondia, Division Estimate No. : JEEEGS) 9__9_ ' Sanctioned Estimate No. Date:__/__/199__ Sanctioned. a ‘. \ Rs Fund head a Mejor head Under the higad 2505 Community Development Scheme / Employment Guarante® Scheme to Five Vear Plan, Minor head Service head Executive Engineer Department head E..S(P.W) Dn,, Gondia, Estimate framed in the office of the Executive Engineer, EGS(PW)Division, Gondia of the probable expenditure that will be incurred on the construction 5 Rs ‘Administratvely approved under No. Date Techuically sanctioned under No.” Date Estimate prepared by Shei: Estimate Checked by Shei: Call or Authority GENERAL DESCRIPTION 1 (Attached separately) ‘Sub-Divisional Officer Executive Engines: E.G.S.P.W.Sub Division E.G.S.(P.W,)Division Gondia (4) Name of work : CERTIFICATE 1 Certified that the estimate is framed on the basis of the Schedule of the rates for E.G.S. Works and Current Schedule of Rates for the year 1987-68 for Bhandara District. 2, Centitied that no scarcity metal is available within reasonable lead in the vicinity S. Certified that it has been ascertained from the competent authority of the imigation department that at the time of according administrative approval there is no Irrigation, Hydro, Water supply project in view, which could submerge/attect the work being administratively approved. ‘i Sub Divisional Offdicer/Engineer Executive Engines E.G.S.P.W, Sub Division E.G.S.(P.W,) Division, Gondia 6) Name of Work t ° CERTIFICATE 1 Certified that the 100 % arithmatical check has been exercvised in this office on the estimate under submission. 2, Corte that the project has been scrutinised and itis veritied that the various provisions made in this estimate are adequate and the entire proposal is considered to be technically sound. ‘Sub Divisional Otficer/Engineer Executive Engineer E.G.S.P.W. Sub Division E.G.S.(P.W,) Division, Gondia oo (6) CHECK LIST FOR PLANS AND ESTIMATE OF E.G.S. ROADS. WORKS. 1. Name of work : : Construction of- 2, Distric/Taluka/P.S. : Bhandara/- 3. Total Length in Ks. From 5 4, Category of roads stD. 5. Whether plans and estimates are :Yes ‘proposed according to prescribed standard of there-and as per category. 6. Whether road (V.R.standard)pases 2 YesiNo. through which B.S.Soll are is so ') Whether provisions of one additional : YesiNo. layers of 150mm thick excerisemental between the size metal layer and moorum, , blanketing is made according to couf-P.W.and H.Department circular No. Plan 1078(8068) D-30 of 17-1-80 and, iWhether provision of /15cms thick :YesiNo. moorum blanketing is made. 7. Whether Govt land for ullered width is 2YesiNo required for the category of road not available ? j) Whether provision is made in the Yes/No estimate for agquiricy the requisite land ? ii)Whether the land is likely to be obtained tree ‘of the cost of and whether revenue authorities rave assured in the respect. if and is required to be acquired © whether the fact is brought to the notice of collector in the wandering letter. 8, Whether allignment of the road full :Yes fills the geometrical and other standard prescribed for category of road. : ‘9. Whether the roads scru through water Yes/No course, 10.Whether the estimate provides to the :Yes labour vide Govt. Reso. No. 3979/1887 desk-29 of 11.10.79 and whether itis, accounted against 40% materials component. 2) 11. Whether there is any in complete road Yes/No work taken up in or E.G.S. available in the vaginity(within the redurs of 8.00kms) whether metaliing is stil to be provided tyes |) Whether this fact is brought to the Yes/No notice of Collector ? = 12. Whether there is any productive work. : Yes/No with in rodious of 8.00kms. which could £ be taken up in packing if so : ') Whether this facet has been brought :YesiNo to the notice of collector. 13. Whether the road proposed provides and another connection on to same village resulting in propes planning (Plvide Gout. letter no. EGS 1076 813 ENP-iiidt. 30-10-79 lapses and irrigeses and irrigaties to safe fix road work under E.G.S. if so whether this i brought to the notice of collector with a respect to drop the % Proposed. 114. Whether the road is question is YesiNo included in the blue print plan of District tor E.G.S. and aproved by Commities: ¥ ‘Sub-Divisional Officer/Engineer Executive Engineer i EG S.PW. Sub-Division E.G.SP.W.Division Goncia, Name of work : Construction of a tem E.G.S. component Non-EGS * Unskilled Skilled ‘component: 1 General tlems As per detailed abstract attached = Earth work -do- MM Supplying Material -co- !V Transportation of materials -do- V Spreading and compaction -do- VI Miscellaneous items -6o- Vil Add for fixed items -do- > es ‘Add 5% contingencies Total Add 2% work charged Estl. charges Total Rs. i) Total cost of E.G.S. work Rs Rs = Rs ji) Percentage of unskilled and skilled component | ) Total cost of Non E.G.S, work Rs. . Total:- . otal E.G.S.P_W. Sub-Division | ‘Sub-Divisional Officer/Engineer | Executive Engineer E.G.S.P.W. Division Gondia (9) GENERAL -REPORT Name of work This detailed estimate amounting to Rs. & estimated cost (including E.G.S. component of Rs, : . and Non-EGScomponent of is has been prepared to cover the cost of consti of, h Authority Collector Bhandara District Necessity ‘ ‘There is a pressing demand to star E.G.S, works in the pocket in which this work les itis therefore proposed to ‘ake up this work under E.G.S. provided there is a guarantee of funds to deal with Non EGS component Name of villages connected with 4 Population Alignment As per 1981-2001 plan,the alignment is proposed in Such a way as 10 avoid land acquisition as for as possible. | Provisions : The estimate Is prepared in two parts (1) EGS ‘component and (2) Non EGS component. 1) EGS. Component :-The portion of estimate includes general items, earth work metal breaking at quarry, spreading and compaction, miscellaneous items and fixed items of supplying arinking water to labourers, sharpening charge tiring charges aid and medicines, and other amenities as also cchaukidar for looking after T.& P.and materials at site, 2) Non E.6.S. Component t {60% unskilled and 40% skiled involved the total 40% skilled Component can not accomodate all the skilled items like 4’ {ransportation involving heavy cost in E.G.S. component such component are required to be considered under Non E.G.S, component. This portion of estimate included transportation of already broken metal and moorum and supplier. Rates ‘Specifications ‘Sub-civisional Otficer/Engineer E.G.S.P.W. Sub-Division (10) Provisions:- Following provisions are made in the estimate. a) Earth work :- Average 0.60m. embankment from borrow pits {or village road standard having road width of 60m. Top layer f 0.20m. thickness shall be compacted with power roller . ') Surtacing:- 0.5m. thick moorum blanketing (compacted) of 3.30m. width (for B.C. soil reaches) oversize metal soling 0.15m. thick (compacted) of 3.30m. width and 0.075m. thick (compacted)size métalling of 3.0m. width. ) Side berms:- 0.15m. thick (compacted)width moorum having width of 0.15m. on both sides. 9) Other items:- Provisions of general items like site clearance survey work temperory shade purchase of petiy ‘materials and other charges required for E.G.S.work has been made in the estimate .Also provisiopn of village ‘name board km, stones,200m.stones,boundry siones are made in the estimate. ‘The rates adopted are as per E.G.S.,C.S.R.for the items which are not in the E.G.S.C.S.R.,D.S.R.rates have been adopted . Provisional rates are also adopted for the items which are not included either in E.G.S.C,S.R.orin D.S.R.. ‘The work shall be executed strictly cording to the standard specifications and guidelines for E.G.S.works given from time to time by the Govt. Executive Engineer E.G.S.(P.W,) Division Gondia, ABSTRACT es of ‘Sr. Items of work Qnty. | Rate | Per | Total | Unskil] Skit No. NI. Amt. | led led T. compo] compo- 2 nent, | nent 4) 2) 3) 4) 5) 6) 7) 8) 1. | Site Clearance 034 | Sqm. 0=42 2. Chain & Compass Survey Km. 3. Earth work for banking 6=18 | Cum. 7=08 ¢ 34 Additional lead of 10 m. 1=40 | Cum. 1562 | - ¢ 4. ‘Compaction of E/Work cum. 5. Supply of 80 mm metal 5.1 Additional lead of 10 m. 1240 | Cum. 1-62 6. ‘Supply of 40 mm metal Cui, 6.1| Additional lead of 10 m. | 1=40 | cum. 1=62 . " 7. | Supplying moorum 6-76 7=80 ‘ 8. | Transportation of S/Moorum Cum. 9. | Supply & Transportation of sand ‘Cum, 10. ‘Spreading 80 mm + 40 mm, 3-50 | Cum. 2) 4) " 14. 15, 16. IZ. 18. 19, 20. 20.a 20.b] 20.0 20.4 20. 204 ‘Spreading moorum & Sand Compaction of oversize metal ‘Compaction of Size metal ‘Compaction of moorum ‘Compaztion of size width E.G.S. Name Boards KM.Stones 200 m Metre Stones & Boundary stones Village name Boards Providing amenities to Labourg Drinking water 5% Sharpening Charges 1% of unskilled portion Hire charges 15% First Ald & Medicines 0.5% Chaukidar 2% Hutting accomodation 2% TOTAL GRAND TOTAL Percentage of skilled & unskilled 2080 3226 295=00 324=50 315=00 346-50 190-00 209-00 190-00 209-00 170=00 187=00 110.00 121.00 cum, 100 Sqm. Ls. Each Each Each ‘Sub-divisional OtficerrEngineer E.G.S.P.W. Sub-Division No, (13) ABSTRACT OF E.G.S. COMPONENT + Sn Item of work Quniy, Unskilled Skilled Rate | Per | Amt NTT Rate Amt, 2) 3) 4» [9 [6 7 8) 9) 1) 2) 3.a) 3b) 4) GENERAL ITEMS Site clearance including cutting {ess than 30 em girth bushes woods| removing vegetation etc. complete (C.S.R. EGS 1/39/333) Crying out detailed chain and ‘compass survey including reconn- sissance survey for preparation of plans and estimates. (Survey CSR I.No. 1 & 2) EARTH WORK” Providing earth work in embank- ‘ment in soll & soft moorum form cutting in borrow pits, laying breaking clods spreading and disposing of the required line; grade and section as directed within| 10m, lead and lft of 1.0 m, ‘Soil with soft moorum not more than 25% (EGS CSR |. No. IA/24 and No. 14/29) Soll with soft moorum 25% to 50% (EGS CSR No. |-8/24 and No. 14/24_ Additional lead of 10 m, Compacting earth work in embank- ‘ment (Machinery charges) for top 20 cm. layer only) 12000 Sqm. Kms. Cum. Cum, cum, Cum, 6n18 7=08 Cum, ‘Cum, 41-40 1-62 |Cum, Cum, Kms. Cum, 1) 2) 3) 4) 5) | 6) 8) 9) So) 6) | 8) | 9) SUPPLYING MATERIALS ‘Supplying 80 mm (about 3/4") size trapigranite/quarizite metal at quarry including collecting rubble at quarry, breaking and stacking within 10 m. lead and 1.0 m. it Additional for lead ‘Supplying 40 mm (about 1/2") trap Jgranite/quantzite/goiss metal at quarry including collecting rubble at quarry, breaking and stacking within 10 m, lead and 1.0 m: lift (CSR I. No. 16/3.36) ‘Add for additional lead of 10 m. (EGS.CSAR,, 1/22) ‘Supplying moorum at quarry including stacking within 1.0 m, lead} and 1.0 m. lift ‘Transportation of moorum including loading unloading & stacking at toad side etc. complete. Km. 1 Km. 2 km.3 Km. 4 ‘Supply of sand conveying including loading unloading & stacking at side etc. complete Km.1 Km2. km3 Km cum, Cum. Cum. cum, Cum, 32566 37-56 1=40 1262 39-66 45-60 1240 1262 6-76 7=80 Cum! cum] Cum| cum| Cum, 2) 10) 11) 12) 13) 14) 15) 16) 7) SPREADING AND COMPACTION Spreading 80 mmv40 mm metal from road side stacks including section- ing complete ‘Spreading moorum and sand ‘Compacting the subgrade sooing oversize metal, sand, soft moorum layers upto 0.15 m. depth compac- ted with power roller including art- ficial watering with all leads of water complete. (the item includes mach- inery charges for 3.30 m. width) ‘Compacting metal layer of 0.075 m, thickness and 30 m. width by power roller, including necessary labour materials, ariticial watering with all lead of water, (The item includes all ‘machinery charges.) ‘Compacting moorum 0.15m. thick= ess (compacted) with power including artificial watering complete upto 40m. width blankeiting, (CSRI No. ) ‘Compacting moorum side width with power roller including artificial watering complete VRIODR: MISCELLANEOUS, Providing EGS Name Boards, information boards on site of work (Rate provisional) Providing & fixing RECM-150 grade mile / Km. stones of standard size and shape including fixing in a block of standard sizes of C.C, 1:4:8 painting etc. complete. ‘Sq.m| 3-50 4-08 3-26 20-00|.. 33-00 32000 35=20 20=90 20=00 22-00 cum, Sqm] 100 ‘Sqm, 100 Sam. Ls. Cum! 291.50 | 71a 188=1 171= 188-1 180-1 198m Sqm 100 Sqm. 100 ‘Sqm. 100 Sqm. 1 2) 3) 4) 5) 6) 8) [9 18) 19) 20) a) ») 3 a U) Providing & Fixing RCCM-350 grade boundary stones in a block of standard size of C.C. 1:48, white washing etc. complete. Providing village name boards on M.S. angle as per drawing including painting and lettering complete. (Rate provisional) Providing amenities to the tabours and other items under skilled ‘components :- Supplying drinking water to labours at site of work and an langhar 5% ‘Sharpening charges of tools, used by labours @ 1% of the cost of unskilled portion. Hiring charge for tools and plants. @ 1.5% of the cost of unskilled ‘component, Providing first aid and prescribed medicines @ 0.5% of the cost of unskilled portion, Provision of Chaukidar for looking after | & P & materials @ 2% of the cost of unskilled portion. Hutting accomodation for labours and T & P articles and provision of petty materials such as lime, coir string, paint etc. @ 2% of the cost of unskilled portion. Ls. 110-1 121200) Total Rs. ‘Sub Divisional Otticer/Engineer E.G.S.P.W. Sub Division Name of work : ABSTRACT FOR NONE.G.S. COMPONENT Sr. ems of work km] Quantity Rate | Per | Amount No. No. ‘TRANSPORTATION OF MATERIALS| 1) | Conveying 8omnvaomin metal 1 Cum, Cum. from quarry to road side including Joading, unloading and stacking 2 Cum. cum, al road side complete (As per Rate Analysis) 3 Cum. Cum, 4 Cum, cum. 5 cum, ‘| cum, 2) | Conveying moorum 1 Cum, Cum. from quarry to road side including oading, unloading and stacking 2 ‘cum. ‘Cum. al road side complete (As per Rate Analysis) 3 Cum, Cum. 4 Cum, Cum, 5 Cum, cum. 8) | Supplying sand including 1 Cum, ‘cum. conveying loading, unloading and slacking at road side complete 2 Cum, Cum, (As per Rate Analysis) 5 3 cum, Cum, 4 cum. Cum ie [5 cum. cum, Total Rupees Sub-Divisional Officer E.G.S-P-E. Sub Division (18) Name of work ; E.G.S. COMPONENT MEASUREMENT SEN Hem of work No. Length Bredih_ Depth Contents 1) Site clearance including cutting trees less than 30 cm girth bushes woods » removing vegetation etc. complete x 1000 x 1200 =Sqm 2) Crying out detailed chain and ‘compass survey including reconn- sissance survey for preparation of plans and estimates. =Kms, EARTH WORK, 9) Providing earth work in embank- ‘ment in soil & soft moorum form Cutting in borrow pits, laying breaking clods spreading and disposing of the required line; grade and section as directed within 410 m. tead and iit of 1.0 m. | 3.2) Soll with soft moorum not more than 25% 3.6) Soil with soft moorum 25% to 50% |) For banking VR 1000 xAAOO 960 - zi i for side wiath TTS OU GEOocG z 2 for camber Tee x 1000 x 0.48 - ! —— 1 ‘Add for additional lead of 10 m, i beyond initial 10 m. lead i 4) Qnty 1/4 of above i) Wem of work. Length Bredth Depth Sr.No. 4) , . 5) - 6) 7 * ‘Compacting earth work in embank- ment (Machinery charges) for top 20 cm, layer only) i) For Banking » 1) For Gamber i ‘SUPPLYING OF MATERIALS ‘Supplying 80 mm (about 3/4") size trapigranite/quartzite gneiss metal at ‘quarry including collecting rubble at quarry, breaking and stacking complete. VR. ) ODA. i) Add for Additional lead of 10 m. ‘Supplying 40 mm (about 1/2") trap Igranite/quartzite/gneiss metal at quarry including collecting rubble at quarry, breaking and stacking complete, VR. » ODR. i) _ Add for additional lead of 10m. ‘Supplying moorum at quarry including stacking within 10 m. lead and 4.0 m. lift )— ForBlanketting VR. i) Foroversizemetal = (O.D.R. iy Forsize metal Ww) Forside norms vA. ODA. x 1000 x 2.00410.80 x 1000 x 0.48 x1000 x3.30 x 1000 x4.00 x 1000 x3.00 x 1000 x3.70 1000 x3.30 1000 -*4,00 3/8 Quantity x 1/3 Quantity x 1000222542. x0.20 x0.20 x0.10 x0.20 x0.20 x0.20 Bane ssTei2.78 0.20 (20) @) Sr.No. 8) 9) 10) 12) item of work No. Length Bredth Depth Contents ‘SPREADING AND COMPACTION Spreading 80 mn/40 mm metal from anty. same as per item 5 +6 road side stacks including section ing complete ‘Spreading moorum and sand from Qnty. same as per item 7 + 3 of Non EGS comonent road side stacks including section- ing complete Compacting the subgrade soiling oversize metal, sand, & soft moorum layers upto 0.15 m. depth compacted with power roller including artificial watering with 1/2 Km lead of water complete, VRIO.DR. for 3.30 mwidth ‘Compacting metal layer of 0.075 m. thickniess and 30 m, width by power roller, including necessary labour materials, artlicial watering with 1/2 Kmead of water complete VR/ODR ‘Compacting moorum of 0.15m. thickness (compacted) /RIODR ~ ore te artiticial watering with 1/2“ Km, lead of water complete. . Moorum blanketting . upto 4.0m width Sqm ‘Compacting moorum side width with power roller including arificial watering complete vivoDF x 1000 x2, 1875 (21) 4) lem of work No. Length Bredth Depth Contents Sr.No. MISCELLANEOUS 14) Providing EGS Name Boards,rate One item s board for information boards on site of work. % 15) Providing for fixing RCCM-150 grade Km. stones of standard size and shape including fixing in a « block of standard sizes of C.C, 1 Lainting etc. complete. 16) Providing & Fixing RCCM-350 grade boundary stones in a block of standard size of C.C. 1:48, white ‘washing etc. complete. 17) Providing village name board on M.S. angle as per drawing including painting ‘One Item and lettering with paint etc, complete. . ; } ec aii ii a MEASUREMENTS FOR TRANSPORTATION OF MATERIALS Sino. item of work Kim. No. Length Bredth Depth Contents Total_aty. of one Km = , Tota! Oty. _ Qty: of one Km= | ength of Road 1) Conveying 8ommv4omm metal 1 from quarry to road side including feading, unloading and stacking «2 at road side complete NOTE 3 Quantity as per item Nos. 5 & 6 of EGS component 4 5 2) Conveying moorumtrom quarry 1 to road side including loading, unloading and stacking 2 at road side complete NOTE: 3 ‘Quantity as per Item No.7 cof EGS component 4 5 3) Supplying of sand including conveying loading, unloading and stacking at road side complete : 1 3.00 For topping on W.8.M vroork = Lx —x1000x 322 x0.10 . Penne 2 “3.78 (23) CSR RATES OF 1991 - 92 Note = Lead Unit Rates of Lead Unit Rates of Km. 91-92 km, 91-92 00.50 Cum. 13.30 15.50 Cum 38.60 01.00 -do- 15.00 16.00 -do- 39.35 01.50 -do- 16.70 16.50 -do- 40.15 02.00 -do- 18.40 17.00 -do- 40.95 02.50 -do- 20.00 17.50 -do- 4175 03.00 -do- 2095 * 18.00 -do- 42.50 03.50 -do- 21/50 18.50 -do- 43.30 04.00 -do- 22.85 19.00 -do- 44.10 04.50 -do- 23.80 19.50 -do- 44.85 05.00 -do- 24.75 20.00 -do- 45.65 05.50 -do- 25.40 2050. -do- 46.35 06.00 -do- 26.00 21.00 -do- 47.05 06.50 -do- 26.65 21.50 -do- 47.70 07.00 -do- 27.25 22.00 -do 48.40 07.50 -do- 27.90 22.50 “do: 49.10 08.00 -do- 28.50 23.00 -do- 49.75 08.50 -do- 29.15 23.50 -do- 50.45 03.00 -do- 29.75 24.00 -do- 51.15 09.50 -do- 30.40 24.50 -do- 51.80 10.00 -do- 31.00 25.00 do. 52.50 10.50 -do- 31.70 25.50 -do- 53.00 11.00 -do- 32.40 26.00 -do- 53.55 11.50 -do- 33.10 26.50 -do- 54.05 12.00 -do- 33.80 27.00 -do- 54.60 12.50 -do- 34.40 27.50 -do- 55.10 13.00 ~do- 35.10 28.00 -do- 55.65 13.50 -do- 35.80 28.50 ~do- 56.15 14.00 -do- 36.50 29.00 -do- 56.70 1450 -do- 37.15 29.50 -do- 57.20 1.00 -do- 37.80 30.00 -do- 57.75 1) After kilometre 30 add for each subsequent kilometre from Km 30/0 to 60/0 2) Add for each subsequent kilometre from km 60/0 to 100/0 3) Add for each subsequent kilometre from km 100 and above Rs.1.05 per Kv? Ris.0.95 per kM? Rs.0.85 per knvM? ‘Above rates are not applicable for Transportation of R.C.C.Pipes, Collars and bulk bitumon for which Separate Rates for Transportation are provided. ++ Ratus of transportation of R.C.C.Pipes and Collars i) iy Lead upto 20 Kms, Lead from 20 Km to 50 Km Beyond 50 Kms. Ris.4.00/ KrwM.T, Rs.2.59/ Kr/M.T, Rs.2.10/KmM.T. Note ;- Above rates of Transportations of pipes and Collars does not include loading and unloading charges. (24) RATES FOR LOADING & UNLOADING STACKING & TR: MATERIALS FOR THE YEAR 91 - 92 FOR COMMON C.S.R. ‘ANSPORTATION OF Rates St Material Unit Ratesfor ——Ratestor Rates for transportation No. loading unloading for carriage including ——_stack- ofmaterials carriage of -—_ing a upto.alead materials upto of50 metres lead ot 40 metres. ens 3 4 5 6 7 1. Boulders Rub- Cum. 5.00 4.00 3.00 10% extra over the rates for : bles and transportation of metal, Masonry stones 2. Metal ot cum, 5.00 4.00 3100 As per schedule all sizes attached Moorumand Cum. 3.50 2.00 1.90 10% below the rates earth and fortransportation loose materia > of metal. : 4. Line Cum 7.50 5.50 2.20 30% below the rates for transportation of : metal 5. Shahabad/ Sqm. 0.25 0.25 10 1/5 the rates for . ‘Sikosa stone transportation of tlooring ‘metal : 6 Fuelwood& MT. 650 5.50 1.60 1/2of the rates tor Ballies transportation of metal 7. Cement Ma. 8.80 6.60 4.40 10% below the rates transportation of metal for delivery other than factory ke. stone/site, 8 Mild Stee! MI. 11.00 8.80 5.50 10% below the rates bars of all for transportation of sizes metal . 9. Timber cum. 6.50 4.40 2.10 30% below the rate ; for transportation of metal * 10. Maxphalt pack MT. 7.70 5.50 3.00 Same as per rates for transportation of metal for store delivery only. a) For delivery of pack tin from refinery - 1) 0.50/kvMT upto 100 kms, fi) 0.45/km/MT above 100kms (25) RATE ANALYSIS Sc] Materials | Km.No]Name of tead [_ Rate Total No. Quarry in km.| Conv-[ Load-| Unioad] Stack eying | ing | ing _|ing 4. | 80840mm | 1 5.00 | 4.00 [3.00 metal | 2 Ps = 4 | | | 5 e 2. | Moorum 1 2 : 3 * 4 ¢ 5 Sr. | Materials Km.NoName of Lead |_ Rate Total No. river! in Km. | Supply|Conv-| Load-] Unload] Stack- allah eying | ing | ing [ing 3. | Sand 10.00 3.50 | 2.00 2 10.00 3.50 | 2.00 3 10.00 3.50 | 2.00 . ‘ 4 10,00 3.50 | 2.00 + 5 30.00} . | 350 | 2.00 ‘Sub-Divisional Officer/Engineer E.G.S.P.W. Sub-Division (26) QUARRY Name of work, Construction of Length of Road Kms, CERTIFICATE i 4) Certified that the quarries held good quality and sufficient quantity of materials. Fg ) 4 3) Corton that quarry holds no religious place. Certified that distance are shown in quarry chart by shortest route. ‘Sub-Divisional Ottice/Engineer E.G.S.P.W, Sub-Division Name of work : Construction of . $ TYPE C/S OF ROAD VR/ODRIMDRIS.H.WAY/ ® +e mes noe) ins pram olsmet af ae ets GAne. sajde Bure OS™ ent: <9 Blaneeting “Ac: pen’ WIDTH FOR: 4. Land width Mtr, CunvAm for Banking 2. Road way Mir. %, EW Cumv/Rmt for Camber 3. Formation width Mr 8. Ew CunvRmt for Side burm. 4 ‘Side burms Mir, 9. Moorum CunvRmt for Blanketting 5. ‘Carriage way Mir, 10. Moorum Cumv/Amt (or OS Metal at. ‘Moorum Cunvrmt } tor Size Metal 12. Moorum ‘CunvAmt, a for Side Burm Prepared by : Checked by : ‘Sub-Divisional Officer/Engineer E.G.S.P.W. Sub-Division (ae Sed (28) RATE ANALYSIS FOR 80 mm & 40 mm METAL Se] Matenais Name of lead | _—_—sRale Total No. Quarry in km.| Conv-] Load- | UnloadiStack: eying | ing | ing [ing 1. | 608 40mm 050 /%3.30| 5.00] 4.00 | 3.00 26.30 metal 2 1.00|15.00| 5.00] 400 | 3.00] 27.00 3 1.501670] 5.00] 4.00 }3.00| 2870 4 2.00|18.40| 5.00] 400 }300| 30.40 5. 2502000] 5.00] 400 }300| 3200 6 3.00 | 20.95 |*5.00] 400 |3.00| 32.95 2. 350|2150| 5.00] 400 |300} 3350 8 4.00|2285/ 5.00 400 |3.00| 3485 450|23.80| 5.00| 400 |3.00} 35.0 10. 5.00|2475| 5.00] 400 }300] 3675 " 550 |25.40| 500] 4.00 |3.00| 37.40 12, 6.00 | 26.00] 5.00} 4.00 | 3.00] 38.00 13, 650|26.65| 5.00] 400 |3.00| 38.65 14 7.00 | 2725| 5.00] 4.00 | 3.00 39.25 15, 750 |2790| 5.00] 400 |3.00| 39.90 16. 8.00 |2850| 5.00] 400 | 3.00) 4050 17. 850 /2915| 5.00] 400 | 300] 41.15 18 9.00 |29.75| 500] 400 | 300) 41.75 19. 9.50} 30.40 | 5.00] 400 | 3.00) 42.40 20. 10.00 }31.00| 5.00} 4.00 | 3.00] 43.00 2. 1050 |31.70| 5.00 400 | 3.00 | 43.70 22. 11.00 |3240] 5.00] 400 }3.00] 44.40 23. 1150 |33.10| 5.00] 4.00 | 3.00] 45.10 24. 12.00 |3380| 5.00] 4.00 |3.00] 45.80 25. 12.50 |34.40| 5.00] 4.00 }3.00| 46.40 26. 13,00 /35.10| 5.00] 400300] 47.10 27. 13.50 |35.80| 5.00] 4.00 |3.00] 47.60 28. 14.00 |3650| 5.00] 4.00 | 3.00] 4850 2 1450 |3715| 5.00] 4.00 |3.00] 49.15 30. 15.00 |3780| 5.00] 4.00 |300] 49.80 Name of work: ‘Construction of Road RATE ANALYSIS FOR SAND Se] Materials | Nameot | Lead Rate Total No. River! in km| Supp- |Conv- |Load- | Unload] Stack- Nallah = lying eying [ing | i ‘Sand 0.50| 10.00 |11.97 | 3.50 27.45 4.00 | 10.00 |19.50 |.3.60 29.00 : 150 | 10.00 |15.03 | 3.50} 2.00 90.55 2.00] 10.00 |16.56 | 3.50| 2.00 |-- 32.05 2:50} 10.00 |18.00 | 350] 2.00 |-- 33.50 t 3.00] 10.00 |18.86 | 350} 200 |-- 34.35 3.50] 10.00 |19.35 | 350] 200 |. (34.85 4.00 | 10.00 |20.57 | 350} 200 |-- 36.05 4.50 | 10.00 |21.42 | 350| 2.00 36.90 5.00| 10.00 |22.28 | a50| 200 |... 37.80 5.50 10.00 |22.86 | 3.50| 200 |. 38.35 6.00 | 10.00 |23.40 | 3.50 38.90 650 | 10.00 |23.99 | 3.50 39.50 7.00 | 10.00 |24.53 | 3.50 40.05 750 | 10.00 |25.11 | 3.50 E ~40.60 8.00 | 10.00 |25.65 | 350] 2.00 |- 41.15 8.50 10.00 |26.24 | 350} 2.00 |-- 41.75

You might also like