Professional Documents
Culture Documents
Quality Management
Homework Assignment 1
Submitted by :
Group 4
Anand Singh (r0777287)
Amarin Neuville
Pranav Bhaskar Bhoyar
Ravi Ranjan
Sudeep Nayak
0|Page
Quality Management Homework Assignment 1
Kindly refer the Excel file named “QM homework 1 group 4” for detailed computation.
(1) The lots allotted to the group for evaluation are as below (refer sheet “Lots Assigned”):
7 20 26 34 43 62 82 165 183 198
We apply the following parameters and calculate total cost in each case:
Case 1 : Single sampling plan, with n = 50; c = 1.
Case 2 : Double sampling plan, with n1 = 30; c1 = 0; r1 = 2; n2 = 24; c2 = 1.
Case 3 : Continuous sampling plan, with h1 = -1.08; h2 = 1.12; s=0.055.
For lots accepted by the respective sampling plans : Cost of sampling process (K1) is
incurred for all the lots. Defective units which remain undetected during sampling will
incur cost K2. Other defective units that were detected during the sampling process
are discarded and not used in assembly.
1|Page
Quality Management Homework Assignment 1
The summary of Single sampling process is provided below (refer sheet “Single Sampling”):
7 49 1 ACCEPT
20 47 3 REJECT
26 45 5 REJECT
34 48 2 REJECT
43 46 4 REJECT
62 50 0 ACCEPT
82 49 1 ACCEPT
165 45 5 REJECT
183 49 1 ACCEPT
198 47 3 REJECT
We reject a lot if number of defective units is found out to be greater than 1 (c).
According to the decision to accept or reject a lot, the cost has been calculated as below:
2|Page
Quality Management Homework Assignment 1
7 29 1 Undecided
20 28 2 Reject
26 30 0 Accept
34 27 3 Reject
43 28 2 Reject
62 28 2 Reject
82 30 0 Accept
165 26 4 Reject
183 29 1 Undecided
198 28 2 Reject
We accept a lot if number of defective units is found out to be lesser than or equal to 0 (c 1)
and reject the lot if number of defective units is found out to be greater than or equal to 2
(r1). For any other count of defective units we move to step 2 of double sampling for the lot.
Step 2: For the second set of units to be sampled, 24 units (n2) were chosen at random. The
list was created using Random number generator (refer sheet “Units being Sampled”). It has
been summarised below:
The summary of second step of Double sampling for the undecided lots are as below:
7 1 Undecided 0 1 Accept
183 1 Undecided 1 2 Reject
3|Page
Quality Management Homework Assignment 1
We reject a lot if total number of defective units after evaluating both the samples is found
out to be greater than 1 (c2).
According to the decision to accept or reject a lot, the cost has been calculated as below
(detailed computation in attached excel file):
Cost of Cost of
Defects Cost of processing
Lot Final Sampling Sampling Total Cost
found while (for accepted lots)
numbers Results Step 1 Step 2 (EUR)
assembling (EUR)
(EUR) (EUR)
7 Accept 30 24 1 150 204
20 Reject 30 0 NA 0 30
26 Accept 30 0 12 1800 1830
34 Reject 30 0 NA 0 30
43 Reject 30 0 NA 0 30
62 Reject 30 0 NA 0 30
82 Accept 30 0 6 900 930
165 Reject 30 0 NA 0 30
183 Reject 30 24 NA 0 54
198 Reject 30 0 NA 0 30
4|Page
5|Page
Continuous sampling
20
Quality Management
15
7
20
26
10
34
43
62
82
Figure 1
165
183
5 198
Number of Defectives
AQL Plot
RQL Plot
0
1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52 55 58 61 64 67 70 73 76 79 82 85 88 91 94 97 100 103 106 109 112 115 118 121 124 127 130 133 136 139 142 145 148 151 154 157 160 163 166 169 172 175 178 181 184 187 190 193 196 199
-5
Homework Assignment 1
Quality Management Homework Assignment 1
The column Defects found while assembling in the table above is calculated by subtracting the
number of defective units identified in the sampling process before reaching a accept decision
from the total number of defective pieces that existed in that lot. Only these unidentified
defective units in the lots incur the additional cost K2 based on our assumptions.
(2) Based on the cost calculations done for each sampling policy, the results are tabulated below
(refer sheet “Result Summary”):
Single Sampling Double Samplig Continuous
Lot number cost cost sampling cost
(EUR) (EUR) (EUR)
7 200 204 320
20 50 30 48
26 50 1830 1161
34 50 30 52
43 50 30 5
62 1550 30 1257
82 800 930 3
165 50 30 67
183 500 54 488
198 50 30 25
Total cost incurred 3350 3198 3426
We notice here that Double Sampling is the most economical policy in this case. However this
cannot be considered as a dominant logic because the cost computation depends on various
factors which may change from case to case basis.
The overall cost may change depending on the following factors:
i. Difference in the decision taken for various lots (accepted/rejected) by applying
various sampling policies
ii. The magnitude of cost of inspecting a lot and cost of processing a defective piece.
We notice here that even though some of the lots face the same final decision through each
policy, still there are some lots that are being treated differently. The difference in total cost
pertaining to any sampling varies greatly as per the acceptance or rejection of the lot. This
also further depends on the magnitude of cost involved in sampling procedure and cost of
correcting defective products. Since these factors varies according to circumstances so does
the overall cost incurred in different Sampling logics. Thus the results might vary if we would
have taken a different set of lots for inspection.
6|Page
Quality Management Homework Assignment 1
(3) Considering the AQL to be 5%, we get the following decision for each lot (refer sheet “Result
Summary”):
Hindsight
No. of Non- No. of Defective
Lot (AQL<=5% [i.e.
Defective units units
10 units])
7 198 2 Accept
20 190 10 Accept
26 188 12 Reject
34 186 14 Reject
43 184 16 Reject
62 190 10 Accept
82 194 6 Accept
165 182 18 Reject
183 196 4 Accept
198 192 8 Accept
A lot is rejected in case there are more than 10 (five percent) defective units.
On comparing the result with each sampling policy we observe the following table:
Lot Hindsight Single Double Continuous
(AQL<=5%) Sampling Sampling Sampling
Lot 7, 20, 34, 43, 165, 198 : The same decision is taken through all the sampling
policies.
Lot 26 : Though it should have been rejected but the decision is taken to accept the
lot in Double and continuous sampling.
Lot 62 : Though it should have been accepted but the decision is taken to reject the
lot in Double sampling.
7|Page
Quality Management Homework Assignment 1
Lot 82 : Though it should have been accepted but the decision is taken to reject the
lot in Continuous sampling.
Lot 183 : Though it should have been accepted but the decision is taken to reject the
lot in Double sampling.
We notice in this case that the best results were obtained using Single sampling method. The
number of correct evaluations made in each policy have been summarised below:
However this cannot be considered as a dominant logic because the effectiveness of sampling
logic will depend on various factors like the parameters (n, c, n1, c1, n2, c2 etc.) taken into
consideration for each type of sampling, the units being randomly selected, and the decided
AQL level. The actual defect percentage in the lots is one of the major influencers for
determining which sampling process would be best suited for the lot. Double sampling or its
extreme version continuous sampling is more effective when the given lot has very low or
very high defect percentage (i.e. <2% or >8 %) for lots with intermediate defect percentages
single sampling is the better choice. As these factors vary so could the final decision for each
lot.
8|Page