Professional Documents
Culture Documents
Excavation Works
INDEX
1. PURPOSE
2. SCOPE
3. REFERENCE DOCUMENT
4. DEFINITION
5. RESPONSIBILITIES
5.1. Site Manager / Project Manager
5.2. Site HSE Manager / Site HSE Coordinator
5.3. HSE Supervisor / Engineer / Officer
5.4. Geotechnical Engineer / Field Engineer
5.5. Construction Superintendent / Supervisor
6. HSE ORGANIZATION
6.1. Working During Night Shift
6.2. Excavation Area
6.3. Patrolling Management
7. COMMUNICATION
8. CONTROL OF ACTIVITIES
8.1. Permit to Work
8.2. Equipment Inspection
8.3. Operators Inspection
8.4. PPE
8.5. Road Traffic Management & Flagmen
8.6. Specific Precaution During / After Adverse Weather Condition
8.7. Specific Precaution When Start Work at New Area
8.8. Excavation Type
8.9. Lake Dewatering
8.10. Hill Cutting
8.11. Rock Breaking
8.12. Blasting
8.13. Dumping
8.14. Surveying on Excavation Area
9. ENVIRONMENTAL PRECAUTIONS
10. EMERGENCY SITUATION
11. ATTACHMENT
11.1. Road Signs
11.2. PPE Signs
11.3. Safety Banner
11.4. Earth Work Permit
11.5. Discharging Permit
11.6. Basic Failure of Excavation
1. PURPOSE
To concern with HSE requirements on excavation work
To ascertain safety for people during excavation work and people
surrounding
To socialize and communicate excavation precautions
To avoid material breakdowns
To mitigate risks of excavation works
2. SCOPE
This procedure is applicable during Emily 1 Project. Contractors have to follow
mandatorily the company requirements in this document.
3. REFERENCE DOCUMENT
863013-02A–HSE-J-PL-0001 Project HSE Policy
863013-02A-HSE-A-PL-0001 Project Health & Safety Management
Plan
863013-02A-HSE-A-PL-0002 Project Environmental Management Plan
863013-02A-HSE-A-PL-0008 Project Medical Emergency Response
Plan
863013-02A-ENG-A-XL-0007 Karimun Yard Layout – Map of Optimized
Excavation Elevation General Plan and Section
863013-SAE-PQM-A-PL-0001 Project Execution and Organization Plan
APAC-PRO-HSE-018 Work Permit System
4. DEFINITIONS
m meter
6. HSE ORGANIZATIONS
6.1 WORKING DURING NIGHT SHIFT
During working at night, precautions to be implemented are:
1. Adequate lighting shall be provided
2. Trench area / Excavated area shall be covered with proper lighting
3. Barricade areas which have high potential risk during night shift
4. Lighting of equipments (i.e: rotary light, reverse light, head light) must be
proper in operating
5. Reverse alarm shall be functioned during operational
6. Additional PPE: High visibility vest and traffic flashlight
6.2 EXCAVATION AREA
Excavation areas are applied at area which is described on below drawings
1. Excavation shall start from highest level of excavated area. Temporary road
access for excavator and dump truck shall be built with safely slope and bench.
Ground Level
Pic 2. Excavation on deepest ground which arm is shortest than excavation level
2. Excavation on ground level shall have formation as below :
Ground Level
Wood
A
15 deg
Deepest Level
7. COMMUNICATIONS
In mean of communication on area / location, Radio is the mean of communication
way to be used.
Listed radio frequencies are:
Radio Of Owner Frequency
HSE & Medic Saipem 141.200
Construction Saipem 149.500
Security Saipem 147.500
Surveyor Saipem 148.500
Construction & HSE MA 144.200
Surveyor MA 144.400, 144.500
Dredging Construction SACNA 156.425
Dredging Surveyor SACNA 145.000
8. CONTROL OF ACTIVITIES
8.1. Permit to Work
Permit to work shall be registered a day before start work. The
requirement of excavation is refer to drawing, type of excavation,
equipment(s) to be used, and manpower involve on the specific of
excavation working.
The excavation complimentary permit refers to Work Permit
Procedure. In case of confined space working, Confined space
permit work shall be implemented.
Drawing shall be attached at permit to work.
Specific Requirement of Permit to Work will follow Permit to Work
Procedure. Permit to Work refer to APAC-PRO-HSE-018 - Work
Permit System
8.2. Equipment Inspection / Certification
All equipment shall be inspected, if needed by 3rd Party prior to
commencing of work. Equipment Certificates to be submitted to
Company prior to commencing work.
8.3. Operator’s Inspection Certification
Operator working for excavation shall have permit from Indonesia
government and Company Inspector. Operator Certificates shall
send to Company prior to commencing work.
8.4. PPE
Mandatory PPE s shall be worn are classified as below:
Designation PPE Shall Be Worn
Supervisor Helmet, Safety Shoes, Safety Glass, High
Visibility Vest*.
Excavator Operator Helmet, Safety Shoes, Safety Glass, High
Visibility Vest* , Ear plug***.
Flagman Helmet, Safety Shoes, Safety Glass, High
Visibility Vest, Flash Light, Flag Sign, Ear
plug***.
Surveyor & Assistant Helmet, Safety Shoes Boot Type, Safety
Surveyor Glass, High Visibility Vest*. Life Jacket**.
Note:
* Applied during working at night only
** Applied during working at water characteristic area
*** Applied during rock breaking activity
8.5. Road Traffic Management & Flagmen
During excavation work, 1(one) way traffic road access shall be
implemented.
Flagman shall be used
Flagmen shall be familiar and understand as well to communicate
with personnel in-charged.
Flagmen shall familiar with the route of operation
Traffic Sign shall be installed
8.6. Specific Precaution during / after adverse weather condition
During bad weather (i.e: rain, storm,) activity shall be stopped due
to stability of ground in low level and high potential probability of
getting stroke.
After adverse weather, soil condition to be checked for ground
stability by visual.
8.7. Specific Precaution when start works in a new area
All personnel shall participate to tool box meeting
All personnel shall aware the condition of new area. Figure of new
area shall be described by supervisor prior to commencing
excavation.
Put permit to work in place. Permit To Work Procedure refers to
APAC-PRO-HSE-018 - Work Permit System.
8.8. Excavation Type
8.8.1. Sloping
Standard solutions apply for below 2 m depth, provided that excavation is
in non-water bearing ground. In all other situations, designed solution must
be used.
Confined space permit shall be applied for trenches which have more than
2 m depth. Trenches which have 2 m depth shall be discussed further at
JSA.
Compacted Soil
Ground Level
Ladder
Pollution Protection:
Dewatering and discharging any water directly to environment surrounding or water
course is subject to written permit issued by the company
11. ATTACHMENT
11.1. Road Signs
CAUTION
Men Be care full of Soft
Working Ground
Under
Ground
Caution – Men Men Working Under Danger – Deep
Working on Ground Excavation
Equipment
NOTICE NOTICE
Life Vest shall High Visibility
Be worn Vest shall be worn