EMILY 1 PROJECT

Excavation Works
INDEX

1. PURPOSE
2. SCOPE
3. REFERENCE DOCUMENT
4. DEFINITION
5. RESPONSIBILITIES
5.1. Site Manager / Project Manager
5.2. Site HSE Manager / Site HSE Coordinator
5.3. HSE Supervisor / Engineer / Officer
5.4. Geotechnical Engineer / Field Engineer
5.5. Construction Superintendent / Supervisor
6. HSE ORGANIZATION
6.1. Working During Night Shift
6.2. Excavation Area
6.3. Patrolling Management
7. COMMUNICATION
8. CONTROL OF ACTIVITIES
8.1. Permit to Work
8.2. Equipment Inspection
8.3. Operators Inspection
8.4. PPE
8.5. Road Traffic Management & Flagmen
8.6. Specific Precaution During / After Adverse Weather Condition
8.7. Specific Precaution When Start Work at New Area
8.8. Excavation Type
8.9. Lake Dewatering
8.10. Hill Cutting
8.11. Rock Breaking
8.12. Blasting
8.13. Dumping
8.14. Surveying on Excavation Area
9. ENVIRONMENTAL PRECAUTIONS
10. EMERGENCY SITUATION
11. ATTACHMENT
11.1. Road Signs
11.2. PPE Signs
11.3. Safety Banner
11.4. Earth Work Permit
11.5. Discharging Permit
11.6. Basic Failure of Excavation
1. PURPOSE
 To concern with HSE requirements on excavation work
 To ascertain safety for people during excavation work and people
surrounding
 To socialize and communicate excavation precautions
 To avoid material breakdowns
 To mitigate risks of excavation works

2. SCOPE
This procedure is applicable during Emily 1 Project. Contractors have to follow
mandatorily the company requirements in this document.

3. REFERENCE DOCUMENT
 863013-02A–HSE-J-PL-0001 Project HSE Policy
 863013-02A-HSE-A-PL-0001 Project Health & Safety Management
Plan
 863013-02A-HSE-A-PL-0002 Project Environmental Management Plan
 863013-02A-HSE-A-PL-0008 Project Medical Emergency Response
Plan
 863013-02A-ENG-A-XL-0007 Karimun Yard Layout – Map of Optimized
Excavation Elevation General Plan and Section
 863013-SAE-PQM-A-PL-0001 Project Execution and Organization Plan
 APAC-PRO-HSE-018 Work Permit System

4. DEFINITIONS

PROJECT Emily 1 Project

HSE Health, Safety & Environment

ERP Emergency Response Plan

MERP Medical Emergency Response Plan

PT. Perseroan Terbatas , Corporation

m meter

JSA Job Safety Analysis


5. RESPONSIBILITIES
5.1 SITE MANAGER / PROJECT MANAGER
 To ensure the effectiveness of procedure
 To build management plan in accordance with the purpose of this document

5.2 PROJECT HSE MANAGER / SITE HSE COORDINATOR


 To control the effectiveness of implemented procedure
 To update necessary document related with the procedure

5.3 HSE SUPERVISOR / ENGINEER / OFFICER


 To maintain implementation of procedure in place
 To ensure technical requirement is on specification
 To update information of any discrepancies in implementation to Site HSE
Coordinator / Project HSE Manager
 To administer all related documentation in place

5.4 GEOTECHNICAL ENGINEER / FIELD ENGINEER


 To render as technical structures designer
 To advice HSE personnel on soil conditions following specific soil calculation
 To provide technical data of soil condition if needed by personnel

5.5 CONSTRUCTION SUPERINTENDENT / SUPERVISOR


 To supervise the implementation of HSE requirements for excavation work
 To implement Permit to Work System which cover excavation activities on
site
 To control communities of personnel surrounding excavated area ,ensuring
as per this safe condition
 To make sure the all personnel are working with the procedure
 To advice Contractors to mandatory safety control measure
 To state that new area of excavation in safe condition to be worked
 To state that dumping area is well compacted and equipment can operate
above designated soil

6. HSE ORGANIZATIONS
6.1 WORKING DURING NIGHT SHIFT
During working at night, precautions to be implemented are:
1. Adequate lighting shall be provided
2. Trench area / Excavated area shall be covered with proper lighting
3. Barricade areas which have high potential risk during night shift
4. Lighting of equipments (i.e: rotary light, reverse light, head light) must be
proper in operating
5. Reverse alarm shall be functioned during operational
6. Additional PPE: High visibility vest and traffic flashlight
6.2 EXCAVATION AREA
Excavation areas are applied at area which is described on below drawings

Pic 1. Excavation Drawing

Excavation Technical Specification Requirements:

1. Excavation shall start from highest level of excavated area. Temporary road
access for excavator and dump truck shall be built with safely slope and bench.

Ground Level

Pic 2. Excavation on deepest ground which arm is shortest than excavation level
2. Excavation on ground level shall have formation as below :

Ground Level

Wood
A

15 deg

Deepest Level

Pic 3. Position of excavator and safety slope angle

3. Minimum slope degree shall be 15o


4. Swing rotation area shall be cleared from personnel
5. Long arm shall be used during excavation area is more than standard arm
6. Wood shall be provided in front of track to avoid collapsed in case excavate on
soft ground

6.2.1 Patrolling Management


Patrol will be implemented in order to monitor the effectiveness of excavation
working. Patrol will be implemented by daily basis and conducted by both of
HSE personnel and Construction personnel.

7. COMMUNICATIONS
In mean of communication on area / location, Radio is the mean of communication
way to be used.
Listed radio frequencies are:
Radio Of Owner Frequency
HSE & Medic Saipem 141.200
Construction Saipem 149.500
Security Saipem 147.500
Surveyor Saipem 148.500
Construction & HSE MA 144.200
Surveyor MA 144.400, 144.500
Dredging Construction SACNA 156.425
Dredging Surveyor SACNA 145.000
8. CONTROL OF ACTIVITIES
8.1. Permit to Work
 Permit to work shall be registered a day before start work. The
requirement of excavation is refer to drawing, type of excavation,
equipment(s) to be used, and manpower involve on the specific of
excavation working.
 The excavation complimentary permit refers to Work Permit
Procedure. In case of confined space working, Confined space
permit work shall be implemented.
 Drawing shall be attached at permit to work.
 Specific Requirement of Permit to Work will follow Permit to Work
Procedure. Permit to Work refer to APAC-PRO-HSE-018 - Work
Permit System
8.2. Equipment Inspection / Certification
 All equipment shall be inspected, if needed by 3rd Party prior to
commencing of work. Equipment Certificates to be submitted to
Company prior to commencing work.
8.3. Operator’s Inspection Certification
 Operator working for excavation shall have permit from Indonesia
government and Company Inspector. Operator Certificates shall
send to Company prior to commencing work.
8.4. PPE
Mandatory PPE s shall be worn are classified as below:
Designation PPE Shall Be Worn
Supervisor Helmet, Safety Shoes, Safety Glass, High
Visibility Vest*.
Excavator Operator Helmet, Safety Shoes, Safety Glass, High
Visibility Vest* , Ear plug***.
Flagman Helmet, Safety Shoes, Safety Glass, High
Visibility Vest, Flash Light, Flag Sign, Ear
plug***.
Surveyor & Assistant Helmet, Safety Shoes Boot Type, Safety
Surveyor Glass, High Visibility Vest*. Life Jacket**.
Note:
* Applied during working at night only
** Applied during working at water characteristic area
*** Applied during rock breaking activity
8.5. Road Traffic Management & Flagmen
 During excavation work, 1(one) way traffic road access shall be
implemented.
 Flagman shall be used
 Flagmen shall be familiar and understand as well to communicate
with personnel in-charged.
 Flagmen shall familiar with the route of operation
 Traffic Sign shall be installed
8.6. Specific Precaution during / after adverse weather condition
 During bad weather (i.e: rain, storm,) activity shall be stopped due
to stability of ground in low level and high potential probability of
getting stroke.
 After adverse weather, soil condition to be checked for ground
stability by visual.
8.7. Specific Precaution when start works in a new area
 All personnel shall participate to tool box meeting
 All personnel shall aware the condition of new area. Figure of new
area shall be described by supervisor prior to commencing
excavation.
 Put permit to work in place. Permit To Work Procedure refers to
APAC-PRO-HSE-018 - Work Permit System.
8.8. Excavation Type
8.8.1. Sloping
Standard solutions apply for below 2 m depth, provided that excavation is
in non-water bearing ground. In all other situations, designed solution must
be used.
Confined space permit shall be applied for trenches which have more than
2 m depth. Trenches which have 2 m depth shall be discussed further at
JSA.

8.8.2. Wide / Large areas


When a trench becomes very wide, the struts themselves become long,
and bend due to their own weight. The bending reduces the compressive
forces than can be resisted. A competent temporary works designer must
perform a proper structural analysis.
8.9. Lake Dewatering
 Dewatering is important in areas that have high ground water tables, or
which do not have adequate drainage. Dewatering shall be done at the
beginning of and during construction when it is necessary to lower the
ground water table. Pumping need to be maintained to keep utility ditches
and cofferdams dry until all work is completed.
 Dewatering must be done so that the velocity of the discharged water doesn’t
scouring of the receiving area.
8.10. Dumping
 Toolbox Talk to all personnel shall be conducted including supervisor
 Install proper and adequate lighting for crossroad area
 Driver and Flagman shall be well trained
 Temporary road access shall be developed with enough soil strength

8.10.1. Dumping at Temporary Road Area

Pic. 6 Soil Formed at Temporary Road


 Cross of Road shall be in curve formed.

8.10.2. Dumping at Reclamation Area


 During dumping, truck shall be on compacted road on both of the
wheels.
 Barricade shall be developed to avoid equipment sink.
Barricade for reversed truck

Compacted Soil

Pic 7. Truck Position during dumping

8.14. Surveying on Excavation Area


 Ladder shall be used during come on to lower ground which length
more than depth of excavated area.
 Warning sign shall be installed on top of ground during surveying.
In case of small excavation area, buddy system between person
underground and on ground shall be implemented as sign
elimination
 Surveyor’s electrical tool shall be water proof

Man working under ground level sign

Ground Level

Ladder

Pic 8. Surveying on underground


9. ENVIRONMENTAL PRECAUTION
Pollution Prevention:
 Ensure all the equipments are inspected/checked and no leakage (event wet-
spot)
 Spill kits (any kind of absorbent; saw dust, rag/napkin) should be on place
 Refuel and maintenance of machinery are prohibited at the work site
 If emergency refuel is required, a mobile dip tray must be prepared

Pollution Protection:
Dewatering and discharging any water directly to environment surrounding or water
course is subject to written permit issued by the company

10. EMERGENCY SITUATION


In case of emergency, ERP and MERP will be applied.

11. ATTACHMENT
11.1. Road Signs

CAUTION
Men Be care full of Soft
Working Ground
Under
Ground
Caution – Men Men Working Under Danger – Deep
Working on Ground Excavation
Equipment

11.2. PPE Signs

NOTICE NOTICE
Life Vest shall High Visibility
Be worn Vest shall be worn

Life Vest Shall be High Visibility Vest


Worn Shall be Worn
11.3. Safety Banner

Ear Plug Protection

11.6. Basic Failure of Excavation