Civil Work
33\11 KV S\S
4 Order of 5MVA T\F 2 Nos , 11KV VCB, 33 KV VCB, Control Panel ,capistar Bank and
other associated materials have been placed with the concerning firm and likely to reach
Diwali as the inspection is due
33KV Line
Errection of Pcc poles started but due to stiff resistance from farmers work has been stopped and
will be started again after cutting of crops and the field will be vacant
11 KV line
Pcc pole of 3No outgoing feeders were erected errection of remaining 1 no outgoing feeder will be
done after cutting of crops