June July
Week 1 2 3 4 5 6 7 8
Demand Forecast 30 30 30 30 40 40 40 40
Customer Orders 33 20 10 4 2
End Inventory 31 1 41 11 41 1 31 61 Negative values here mean we need to produce
Master ProductionMPS
Schedule 70 70 70 70 We need to consider the lead time for these batches
Beggining MPS 70 70 70 70 Actual beggining of production taking into account the lead time
Inventory available
ATP
to promise 11 56 68 70 70 Atp is the sume of customer order until next MPS
Policies
Available Inventory 52 Lot for Lot LFL
The batch size is 60 We only produce in batches of 60 Fixed size lot FOQ This is FOQ
Lead Time 1 week
Question 1 No, it is not possible because ATP is 16 which is less than the order.
Question 2 Yes, because the ATP for week 4 is more than what the order is.