2. The water should be filled up to 250 ~300mm lower than the roof panel.
3. All tanks and each compartment where tanks are sub-divided shall be filled with clean water
after erection and left standing under test for a period of not less than twenty four (24) hours,
during which time, all joints shall be inspected and no loss/leakage of water shall occur.
4. Each side of a compartmented tank shall be tested separately with the other compartment
empty of water, to ensure the integrity of the dividing full height partition.
6. In the event that a leak occurs, the tank shall be drained, the leak repaired to the satisfaction of
the client’s representative, ENGINEER or other consultant as appropriate, and the test procedure
repeated.