Estimate the quantity of P.C.C (1:4:8) in foundation and under layer of floors from the
given drawings. Also calculate total number of cement bags in P.C.C (1:4:8).
Solution
center to center length of L1 = (4.5/12)’ + 12’ + (9/12)’ + 12’ + (9/12)’ + 5’ + (4.5/12)’ = 31.25’
center to center length of L2 = (4.5/12)’ + 5’ + (4.5/12)’ = 5.75’
center to center length of S1 = (4.5/12)’ + 10.75’ + (4.5/12)’ = 11.5’
center to center length of S2 = (4.5/12)’ + 5’ + (4.5/12)’ = 5.75’