Assignment #1

Solution
Center to center length of L1 = (4.5/12)’+14’+ (9/12)’+14’+ (4.5/12)’ = 29.5’
Center to center length of S1= (4.5/12)’+12’+ (4.5/12)’= 12.75’
Center to center length of S2= (4.5/12)’+8’+ (4.5/12)’= 8.75’
Bricks:
Total quantity of brickwork = Brickwork in foundation + Brickwork in superstructure
=443.39+966 = 1409.39 cft
No of bricks required for 100 cft of brickwork = 1350 Nos.
No of bricks required for 810.1 cft of brickwork = 1409.39 x1350/100 = 19026 Nos.
Plain cement concrete (1:4:8)
Total quantity of P.C.C (1:4:8) = P.C.C (1:4:8) in foundation + P.C.C (1:4:8) under floors
=189.69+183 =372.7 cft
Dry material for 100 cft of cement concrete = 154 cft
Quantity of Cement in cft =154x1x372.7/(100x13) = 44.1 cft
Reinforced cement concrete (1:2:4)
Total quantity of reinforced cement concrete = 243.1 cft
Dry material for 100 cft of cement concrete = 154 cft
Quantity of Cement in cft =154x1x243.1/ (100x7) = 53.5 cft
Cement bags:
Total quantity of cement in P.C.C (1:4:8) and R.C.C (1:2:4) =44+53.5 = 94.5 cft
Volume of one cement bag = 1.25 cft.
No. of bags required for 94.5 cft cement =94.5/1.25= 75.6 = Approx. 76 bags
Steel bars:
Mild steel work as reinforcement @ 1% of R.C.C. = 243.1x.01= 2.43 cft
Weight = volume x density = 2.43 x 490 =1190.7 lbs. = 1190.7/2.2 kg = 541.2 kg