Project Siam denso Ph4 Expansion

Subject : Cutting Zone Alarm Step of work at Chemical storage

1 Denso facility team announce a public to notify all employees that there is a fire alarm system.
2 Close sound all Zone alarm at FCP by SDM staff
3 To test for confirm correct zone at chemical storage
4 Shutdown FCP by SDM staff
5 Disconnect the this zone and install the resistor at L and C terminal. About 30Min.
6 Open system of FCP by SDM staff
7 Test by continuas test cable loop zone to correct
8 to confirm correct zone
9 to cut separate area demolist area chemical building and reconnect (see attached sheet)
10 Shutdown FCP by SDM staff
11 to connect L and C wire of zone chemical storage building to FCP terminal
12 Test alarm for confirm correct
re alarm system.
Meeting on the demolition of the chemical building Since the construction team had to dismantle the
But it is necessary to dismantle the smoke detection system first
Talked with Khun thanet as follows
submit a step of operation, inform Khun thanet as attached

On 11Oct2019 , Denso facility team announce a public to notify all employees that there is a fire alarm

Close sound all Zone alarm at FCP by SDM staff


To test for confirm correct zone at chemical storage
Shutdown FCP by SDM staff
Disconnect the this zone and install the resistor at L and C terminal. About 15Min.
Open system of FCP by SDM staff
Test by continuas test cable loop zone to correct
to confirm correct zone
to cut separate area demolist area chemical building and reconnect (see attached sheet)
Shutdown FCP by SDM staff
to connect L and C wire of zone chemical storage building to FCP terminal
m had to dismantle the roofing sheet on October 12.

that there is a fire alarm system.