Item Rate

M40 Grade concrete 5300


TMT 8mm including etc.(labour 2*350/panel) +(10m/panel)=30MT @4800
MS plain Dowel of dia.25mm490/10^6 x0.3x7.85x12000 50,000
Threaded lifty arrangement 7000 Nos.of female 100 Nos of male 20
Total
Mould making cost including rubber pad ( if prov.) MS base Ms mould ,demoulding system 10% of total
Transportaion of panel including (10000) 25km of lead. 10,000
Leveling of base ( avg 20mm) using C:S mix .including levelling of mix ,rolling of mix 400kg
Hydra For unloading the panels + placing 4500/day
3 labours per hydra 350/day
Grouting of dowel joints 12000x0.15x0.05x0.1 1000/cu.m
Post tensioning of panels including PT wire 10,00,000 for pre tens.including wedges & barrel 70000/MT
Qty Amount
700 cu.m 3710000
1930000
13.9 MT 692370
7100 142000
6474370
647437
88 88,000
140 56,000
20 90,000
60 21,000
9 9,000
10 700000
14560177