ID Task Name Duration Start Finish Apr '17 May '17 Jun '17 Jul '17 Aug '17

Start Finish Apr '17 May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17 Dec '17 Jan '18 Feb '18 Mar '18
3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 5 12
1 Negotiation & Tender award 5,2 wks Mon 10/04/17Mon 15/05/17
2 Contract 4 days Tue 16/05/17 Fri 19/05/17
3 Purchase order 1 wk Mon 22/05/17Fri 26/05/17
4 Downpayment 2 wks Mon 29/05/17Fri 9/06/17
5 Receipt of engineering can samples 0 days Tue 20/06/17 Tue 20/06/17 20/06
6 Confirmation of specifications 0 days Tue 20/06/17 Tue 20/06/17 20/06
7 Ex-works delivery (incl FAT) 26,4 wks Mon 12/06/17Tue 12/12/17
8 Packaging & shipment 6,5 wks Wed 13/12/17Fri 26/01/18
9 Custom clearance & on-site arrival 0,7 wks Fri 26/01/18 Wed 31/01/18
10 Mechanical and electrical installation 2 wks Thu 1/02/18 Wed 14/02/18
11 Commissioning & Start-up 2 wks Thu 15/02/18 Wed 28/02/18
12 Performance test & SAT 2 days Thu 1/03/18 Fri 2/03/18
13
14 Remarks:
15 JBT cannot be held responsible for delays in the planning due to:
16 Delays in order confirmation & Downpayment
17 Incomplete/faulty specifications (for example can, cover, seam, product
specifications)
18 Delays in receipt of samples (engineering samples / FAT samples)
19 Delays in design/layout/specification approvals. Response should be
received in 5 days period
20 Scope changes after order confirmation
21 Special requests regarding FAT (currently 1 day in Belgium in foreseen
for FAT completion)
22 Custom clearance issues
23 Inland transport delays
24 Unfinished civil works
25 Unfinished piping works and CIP preparation
26 Any obstruction for putting equipment in position
27 Absence of hoisting and lifting equipment
28 Missing utility provisions (electricity, gas, air, …)
29 Delays in raw material supply (can, cover, product)
30 Raw material quality problems (for example: damaged cans out of JBT
scope)
31 Absence of required resources from customer’s side.
32 Delay in connecting the equipment to the utilities
33 Other factors that are in customer scope / not in JBT scope.
34 Any delay caused by the above may reflect in a delay in the overall planning.
35 Equipment deliveries may be partial
36 The SAT-results will be accepted when fulfilling the 3 performance criteria
per contract: filling accuracy, speed and efficiency. Other (minor)
acceptance criteria may not delay the acceptance of the SAT.
37 Indolakto to allow partial shipment
38 Indolakto to allow CMBTech to deliver ex works anytime in November and
December
39 Indolakto to allow CMBTech to start the installation after equipment arrival
40 Indolakto to allow CMBTech to complete the installation before the above
installation chart

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: 170523 - Project schedule Split External Tasks Inactive Summary Manual Summary Progress
Date: Tue 23/05/17 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only