Curs 8 - Applications Networks
Curs 8 - Applications Networks
Solution
. Project network
Activities RT RL
(total slack time) (free slack time)
B 5 5
C 7 0
E 7 7
F 5 5
G 5 5
Gantt chart
Aplication 2
The following project is described in the table below:
Tabel 1
Activities Duration, Predecessor
(weeks)
A1 10 -
A2 5 A1
A3 10 -
A4 20 A1
A5 5 A2, A3
A6 10 A4, A5
A7 16 A2, A3
Draw a diagram with activities on arrows fully explained, knowing that the project
must be completed in a minimum of time and show the critical path.
The project manager found that in the 18 week from the start of the project all the
activities are in time planned, exept the activity A4, which is carried out at a rate of 30%.
What is the percentage should be performed A4 at this moment? Calculate the corrected
duration of A4, considering that there are no more delays. Draw the updated network
assuming the other activities remain according to the initial schedule, showing what are
the free slack of the activities in a Gantt chart.
Solution
Fig.1. Diagrama cu activităţi pe săgeţi
Updated network
.
Gantt chart
Aplication 3
In the table below are given the activities of a project with their duration:
Draw a diagram with activities on arrows fully explained, knowing that the project is
completed in 70 weeks and show the critical path.
The project manager found that in the week 49 from the start of the project all
activities are according to the schedule, except A6 and A9 activities, which are made at
the rate of 20% and 8% respectively. What is the percentage that had to be made at this
time? Calculate from this moment the corrected duration of these activities, considering
that there are no more delays. Draw the updated network, assuming all the other activities
remain according to the schedule. Show the free slacks of activities in a table.
Solution
Fig.6. Reţeaua proiectului
The reasoning is the same as the previous problem
Activity A6 lasts from 46 to 55 week with a duration of 10 weeks.
10 weeks ............... 100 %
1 week ............... 10%
4 weeks ............... 40%
The week 49 is the fourth week from the beginning of A6, so in this week this activity
should be completed at a rate of 40% ( 4 x 10), but it is completed at a rate of 20% ,
which means a delay of 20% (40 % -20 % ), which is equivalent to a duration of 2 week.
So A6 activity has a corrected duration of 12 weeks.
Activity A9 lasts from 46 to 70 week with a duration of 10 weeks.
25 weeks ............... 100 %
1 week ............... 4%
4 weeks ............... 16 %
The 49 week is the fourth since the start of A9, A9 work this week so had to be
completed at a rate of 16% ( 4 x 4), but it is completed at a rate of 8% , which means a
delay of 8 % (16 % -8 % ), which is equivalent to a period of two weeks, so A9 activity
has a corrected duration of 27 weeks.
Activities A2 A3 A4 A8 A6 A7
Free slack 0 30 8 40 0 5
Aplication 4
The table below shows the activities of a project.
Activities Duration, Predecessor
(weeks)
A 10 -
B 5 -
C 10 -
D 10 A, B
E 5 D
F 5 D
G 15 C
a) Draw and analyze a network on nodes for this project, assuming that it should be
completed in 30 weeks. The chart should include a single start node and a single end
node.
b) Identify which activities has free slacks and show its value.
Solution
a)
Aplication 5
The table below shows the activities of a project.
Aplication 6
The table below shows the activities of a project.
Activities Duration (weeks) Predecessor Human resources
A 10 - 1
B 10 - 2
C 5 A, B 2
D 10 C 2
E 20 B, C 3
Draw the network with activities on nodes fully explained, assuming that the work is
completed in minimum of time. Calculate the free and total slacks of the activities and
establish which is the initially level required of human resources and how can you reduce
the peak value of this level.
Solution
Network of the project
Activities with free slack is placed in order of increasing free slack on the graph.
Aplication 7
The table below shows the activities of a project
Activities Duration (weeks) Predecessor Human resources
A 15 - 2
B 10 - 3
C 10 A, B 3
D 20 C 4
E 25 B, D 3
Draw the network with activities on nodes, fully explained, assuming that the work is
completed in 75 weeks. Show the critical path. Determine the free slacks of the activities
and establish how must be the initially level human resources required in the project and
how can you reduce the peak value of this level.
Solution
Aplication 8
The following project is described in the table below:
Draw a diagram with activities on nodes fully explained, knowing that the project must
be completed in a minimum of time and show what is the critical path. Calculate the free
slack time of activities and draw the Gantt chart, showing the free slack time of each
activity.