You are on page 1of 3

AL RUSSEL- L

Project : Private villa (B+G+1+P)


LOCATION BERKET AL AWAMIR
PAYMENT 61500 QAR (5%)
STAGE:01
SL.NO DESCRIPTION OF WORK MAN POWER QTY

1
Finish the
foundation,Raft,Retaining Walls
and Neck columns. Finish all
Water proofing Works and
Protection under ground.

STAGE:02
SL.NO DESCRIPTION OF WORK MAN POWER QTY
AL RUSSEL- LUSSAIL

AMOUNT TOTAL METERIAL REQUIRED QTY PRICE(APROXIMATE)


WHITE WOOD 25 20
POLYTHENE SHEET 10 50
PLY WOOD 15MM 22 70
PLY WOOD 18MM 175 70
WHITE WOOD 50X75 300 20
TIE ROD, CLAMB 2500
STATIONARY 5000
WATER PROOFING SHEET 40 100
PROTECTION BOARD 2000
BLOCKS,CEMENT & SAND 1750
CONCRETE & STEEL AL RUSSEL WILL PROVIDE (132650QAR)

AMOUNT TOTAL METERIAL REQUIRED QTY PRICE(APROXIMATE)


PLY WOOD 75 70
WHITE BOARD 50 20
JACK 400 10
POLYTHENE SHEET 5 50
STATIONARY
CONCRETE & STEEL
Date:02/12/2019

TOTAL(QAR)
500
500
1540
12250
6000
2500
5000
4000
2000
1750

36040

TOTAL(QAR)
5250
1000
4000
250
50000