Kolom/Pedestal STG-4 Top slab STG-4

scaffolding 25-Oct
4 29-Oct 29-Oct 26-Oct 26-Oct 25-Oct 24-Oct 27-Oct 26-Oct
Bekisting Slab 26-Oct 02-Nov
Pembesian 31-Oct 14-Nov
3 22-Oct 22-Oct 19-Oct 19-Oct 18-Oct 17-Oct 20-Oct 19-Oct
Acc. siku+embeded 04-Nov 17-Nov
Bekisting dinding 07-Nov 14-Nov
2 15-Oct 15-Oct 12-Oct 12-Oct 11-Oct 10-Oct 13-Oct 12-Oct
Acc. Pipe sleeper 16-Nov 28-Nov
Pengecoran 29-Nov 30-Nov
1 08-Oct 02-Oct 05-Oct

1 2 3 4 5 6 7 8