Summative test TLE 7/ 3RD QUARTER

November 15, 2019

competency easy average difficult Item total


placement
Lesson 1 – Prepare Construction Materials
and Tools
- Identify materials and tools applicable to a 1,2,3
specific construction job 4,5,6,7
8,9
10

1. Bill – a statement of payment due to goods and services


2. Damage – a destruction, injury, or harm to a person or thing
3. Quantity – a number, amount in size
4. Tool – a simple implement, as a hammer, saw, and spade chisel etc. used in work
5. Work – something made or accomplished
6 Implements manipulated by the hand to facilitate carpentry works.
A. Tools C. Equipment B. Materials D. Hardware
6. Sand fine gritty, substance found in the shore and desert
8 Hack sawfine toothed saw used to cut metals and pipes
9 Level bar tool used in checking vertical and horizontal position
10. Gravel - coarse aggregate

Summative test TLE 7/ 3RD QUARTER

November , 2019

competency easy average difficult Item total


placement
Lesson 1 – Prepare Construction Materials
and Tools
- Identify materials and tools applicable to a 1,2,3
specific construction job 4,5,6,7
8,9
10

Directions: Supply what is defined or described. Write your answer on your answer sheet.
_____________1. It is a thin cross laminated sheet of wood.
_____________2. This is made of metal used for fastening.
_____________3. It is a powdered substance mixed with water.
_____________4. It is a fine, dry, gritty substance mixed with water.
_____________5. It is a sawn timber.
_____________6. It is used for measuring long distances.
_____________7. It is used for driving and pulling out nails.
_____________8. It is a tool used for cutting along the grain.
_____________9. It is used for vertical alignment
. _____________10. It is a tool used to test the squareness of a stock.