You are on page 1of 20

SECOND DIVISION 2000 Lease Contract

G.R. No. 198075 September 4, 2013 Two (2) days before the lease incorporated in the Deed of Donation
and Amended Deed of Donation was set to expire, or on 23 May 2000,
FKI and respondent executed another contract of lease ( 2000 Lease
KOPPEL, INC. (formerly known as KPL AIRCON, INC.), Petitioner,
Contract )15 covering the subject land. In this 2000 Lease Contract,
vs.
FKI and respondent agreed on a new five-year lease to take effect on
MAKATI ROTARY CLUB FOUNDATION, INC., Respondent.
the 26th of May 2000, with annual rents ranging from ₱4,000,000 for
the first year up to ₱4,900,000 for the fifth year. 16 The 2000 Lease
DECISION Contract also contained an arbitration clause enforceable in the event
the parties come to disagreement about the" interpretation,
application and execution" of the lease, viz :
PEREZ, J.:

19. Governing Law – The provisions of this 2000 Lease Contract shall
This case is an appeal1 from the Decision2 dated 19 August 2011 of be governed, interpreted and construed in all aspects in accordance
the Court of Appeals in C.A.-G.R. SP No. 116865. with the laws of the Republic of the Philippines.

The facts: Any disagreement as to the interpretation, application or execution of


this 2000 Lease Contract shall be submitted to a board of three (3)
The Donation arbitrators constituted in accordance with the arbitration law of the
Philippines. The decision of the majority of the arbitrators shall be
binding upon FKI and respondent.17 (Emphasis supplied)
Fedders Koppel, Incorporated (FKI), a manufacturer of air-
conditioning products, was the registered owner of a parcel of land
located at Km. 16, South Superhighway, Parañaque City (subject 2005 Lease Contract
land).3 Within the subject land are buildings and other improvements
dedicated to the business of FKI.4
After the 2000 Lease Contract expired, FKI and respondent agreed to
renew their lease for another five (5) years. This new lease (2005
In 1975, FKI5 bequeathed the subject land (exclusive of the Lease Contract )18 required FKI to pay a fixed annual rent of
improvements thereon) in favor of herein respondent Makati Rotary ₱4,200,000.19 In addition to paying the fixed rent, however, the 2005
Club Foundation, Incorporated by way of a conditional donation.6 The Lease Contract also obligated FKI to make a yearly " donation " of
respondent accepted the donation with all of its conditions. 7 On 26 money to the respondent.20 Such donations ranged from ₱3,000,000
May1975, FKI and the respondent executed a Deed of for the first year up to ₱3,900,000for the fifth year.21 Notably, the 2005
Donation8 evidencing their consensus. Lease Contract contained an arbitration clause similar to that in the
2000 Lease Contract, to wit:
The Lease and the Amended Deed of Donation
19. Governing Law – The provisions of this 2005 Lease Contract shall
be governed, interpreted and construed in all aspects in accordance
One of the conditions of the donation required the respondent to lease with the laws of the Republic of the Philippines.
the subject land back to FKI under terms specified in their Deed of
Donation.9 With the respondent’s acceptance of the donation, a lease
agreement between FKI and the respondent was, therefore, Any disagreement as to the interpretation, application or execution of
effectively incorporated in the Deed of Donation. this 2005 Lease Contract shall be submitted to a board of three (3)
arbitrators constituted in accordance with the arbitration law of the
Philippines. The decision of the majority of the arbitrators shall be
Pertinent terms of such lease agreement, as provided in the Deed of binding upon FKI and respondent.22 (Emphasis supplied)
Donation , were as follows:

The Assignment and Petitioner’s Refusal to Pay


1. The period of the lease is for twenty-five (25) years,10 or
until the 25th of May 2000;
From 2005 to 2008, FKI faithfully paid the rentals and " donations "due
it per the 2005 Lease Contract.23 But in June of 2008, FKI sold all its
2. The amount of rent to be paid by FKI for the first twenty- rights and properties relative to its business in favor of herein
five (25) years is ₱40,126.00 per annum .11 petitioner Koppel, Incorporated.24 On 29 August 2008, FKI and
petitioner executed an Assignment and Assumption of Lease and
The Deed of Donation also stipulated that the lease over the subject Donation25 —wherein FKI, with the conformity of the respondent,
property is renewable for another period of twenty-five (25) years " formally assigned all of its interests and obligations under the
upon mutual agreement" of FKI and the respondent.12 In which case, Amended Deed of Donation and the 2005 Lease Contract in favor of
the amount of rent shall be determined in accordance with item 2(g) petitioner.
of the Deed of Donation, viz:
The following year, petitioner discontinued the payment of the rent
g. The rental for the second 25 years shall be the subject of mutual and " donation " under the 2005 Lease Contract.
agreement and in case of disagreement the matter shall be referred
to a Board of three Arbitrators appointed and with powers in Petitioner’s refusal to pay such rent and "donation " emanated from
accordance with the Arbitration Law of the Philippines, Republic Act its belief that the rental stipulations of the 2005 Lease Contract, and
878, whose function shall be to decide the current fair market value of even of the 2000 Lease Contract, cannot be given effect because they
the land excluding the improvements, provided, that, any increase in violated one of the" material conditions " of the donation of the subject
the fair market value of the land shall not exceed twenty five percent land, as stated in the Deed of Donation and Amended Deed of
(25%) of the original value of the land donated as stated in paragraph Donation.26
2(c) of this Deed. The rental for the second 25 years shall not exceed
three percent (3%) of the fair market value of the land excluding the
improvements as determined by the Board of Arbitrators.13 According to petitioner, the Deed of Donation and Amended Deed of
Donation actually established not only one but two (2) lease
agreements between FKI and respondent, i.e. , one lease for the first
In October 1976, FKI and the respondent executed an Amended Deed twenty-five (25)years or from 1975 to 2000, and another lease for the
of Donation14 that reiterated the provisions of the Deed of Donation , next twenty-five (25)years thereafter or from 2000 to 2025. 27 Both
including those relating to the lease of the subject land. leases are material conditions of the donation of the subject land.

Verily, by virtue of the lease agreement contained in the Deed of Petitioner points out that while a definite amount of rent for the second
Donation and Amended Deed of Donation , FKI was able to continue twenty-five (25) year lease was not fixed in the Deed of Donation and
in its possession and use of the subject land.
Amended Deed of Donation , both deeds nevertheless prescribed premises and, therefore, the refusal to comply there with
rules and limitations by which the same may be determined. Such does not give rise to an action for unlawful detainer.47
rules and limitations ought to be observed in any succeeding lease
agreements between petitioner and respondent for they are, in
2. Assuming that the MeTC was able to acquire jurisdiction,
themselves, material conditions of the donation of the subject land. 28
it may not exercise the same until the disagreement
between the parties is first referred to arbitration pursuant
In this connection, petitioner cites item 2(g) of the Deed of Donation to the arbitration clause of the 2005 Lease Contract.48
and Amended Deed of Donation that supposedly limits the amount of
rent for the lease over the second twenty-five (25) years to only " three
3. Assuming further that the MeTC has jurisdiction that it
percent (3%) of the fair market value of the subject land excluding the
can exercise, ejectment still would not lie as the 2005 Lease
improvements.29
Contract is void abinitio.49 The stipulation in the 2005 Lease
Contract requiring petitioner to give yearly " donations " to
For petitioner then, the rental stipulations of both the 2000 Lease respondent is a simulation, for they are, in fact, parts of the
Contract and 2005 Lease Contract cannot be enforced as they are rent. 50 Such grants were only denominated as " donations
clearly, in view of their exorbitant exactions, in violation of the " in the contract so that the respondent—anon-stock and
aforementioned threshold in item 2(g) of the Deed of Donation and non-profit corporation—could evade payment of the taxes
Amended Deed of Donation . Consequently, petitioner insists that the otherwise due thereon.51
amount of rent it has to pay thereon is and must still be governed by
the limitations prescribed in the Deed of Donation and Amended Deed
In due course, petitioner and respondent both submitted their position
of Donation.30
papers, together with their other documentary
evidence.52 Remarkably, however, respondent failed to submit the
The Demand Letters Second Demand Letter as part of its documentary evidence.

On 1 June 2009, respondent sent a letter (First Demand Letter)31 to Rulings of the MeTC, RTC and Court of Appeals
petitioner notifying the latter of its default " per Section 12 of the 2005
Lease Contract " and demanding for the settlement of the rent and "
On 27 April 2010, the MeTC rendered judgment53 in favor of the
donation " due for the year 2009. Respondent, in the same letter,
petitioner. While the MeTC refused to dismiss the action on the
further intimated of canceling the 2005 Lease Contract should
ground that the dispute is subject to arbitration, it nonetheless sided
petitioner fail to settle the said obligations. 32 Petitioner received the
with the petitioner with respect to the issues regarding the
First Demand Letter on2 June 2009.33
insufficiency of the respondent’s demand and the nullity of the 2005
Lease Contract.54 The MeTC thus disposed:
On 22 September 2009, petitioner sent a reply34 to respondent
expressing its disagreement over the rental stipulations of the 2005
WHEREFORE, judgment is hereby rendered dismissing the case x x
Lease Contract — calling them " severely disproportionate,"
x, without pronouncement as to costs.
"unconscionable" and "in clear violation to the nominal rentals
mandated by the Amended Deed of Donation." In lieu of the amount
demanded by the respondent, which purportedly totaled to SO ORDERED.55
₱8,394,000.00, exclusive of interests, petitioner offered to pay only
₱80,502.79,35 in accordance with the rental provisions of the Deed of
The respondent appealed to the Regional Trial Court (RTC). This
Donation and Amended Deed of Donation.36 Respondent refused this
offer.37 appeal was assigned to Branch 274 of the RTC of Parañaque City
and was docketed as Civil Case No. 10-0255.

On 25 September 2009, respondent sent another letter (Second


Demand Letter)38 to petitioner, reiterating its demand for the payment On 29 October 2010, the RTC reversed56 the MeTC and ordered the
of the obligations already due under the 2005 Lease Contract. The eviction of the petitioner from the subject land:
Second Demand Letter also contained a demand for petitioner to "
immediately vacate the leased premises " should it fail to pay such WHEREFORE, all the foregoing duly considered, the appealed
obligations within seven (7) days from its receipt of the letter. 39 The Decision of the Metropolitan Trial Court, Branch 77, Parañaque City,
respondent warned of taking " legal steps " in the event that petitioner is hereby reversed, judgment is thus rendered in favor of the plaintiff-
failed to comply with any of the said demands.40 Petitioner received appellant and against the defendant-appellee, and ordering the latter
the Second Demand Letter on 26September 2009.41 –

Petitioner refused to comply with the demands of the respondent. (1) to vacate the lease[d] premises made subject of the
Instead, on 30 September 2009, petitioner filed with the Regional Trial case and to restore the possession thereof to the plaintiff-
Court (RTC) of Parañaque City a complaint42 for the rescission or appellant;
cancellation of the Deed of Donation and Amended Deed of Donation
against the respondent. This case is currently pending before Branch
257 of the RTC, docketed as Civil Case No. CV 09-0346. (2) to pay to the plaintiff-appellant the amount of Nine
Million Three Hundred Sixty Two Thousand Four Hundred
Thirty Six Pesos (₱9,362,436.00), penalties and net of 5%
The Ejectment Suit withholding tax, for the lease period from May 25, 2009 to
May 25, 2010 and such monthly rental as will accrue during
On 5 October 2009, respondent filed an unlawful detainer the pendency of this case;
case43 against the petitioner before the Metropolitan Trial Court
(MeTC) of Parañaque City. The ejectment case was raffled to Branch (3) to pay attorney’s fees in the sum of ₱100,000.00 plus
77 and was docketed as Civil Case No. 2009-307. appearance fee of ₱3,000.00;

On 4 November 2009, petitioner filed an Answer with Compulsory (4) and costs of suit.
Counterclaim.44 In it, petitioner reiterated its objection over the rental
stipulations of the 2005 Lease Contract for being violative of the
material conditions of the Deed of Donation and Amended Deed of As to the existing improvements belonging to the defendant-appellee,
Donation.45 In addition to the foregoing, however, petitioner also as these were built in good faith, the provisions of Art. 1678of the Civil
interposed the following defenses: Code shall apply.

1. The MeTC was not able to validly acquire jurisdiction SO ORDERED.57


over the instant unlawful detainer case in view of the
insufficiency of respondent’s demand.46 The First Demand The ruling of the RTC is premised on the following ratiocinations:
Letter did not contain an actual demand to vacate the
1. The respondent had adequately complied with the 19. Governing Law – The provisions of this 2005 Lease Contract shall
requirement of demand as a jurisdictional precursor to an be governed, interpreted and construed in all aspects in accordance
unlawful detainer action.58 The First Demand Letter, in with the laws of the Republic of the Philippines.
substance, contains a demand for petitioner to vacate when
it mentioned that it was a notice " per Section12 of the 2005
Any disagreement as to the interpretation, application or execution of
Lease Contract."59 Moreover, the issue of sufficiency of the
this 2005 Lease Contract shall be submitted to a board of three (3)
respondent’s demand ought to have been laid to rest by the
arbitrators constituted in accordance with the arbitration law of the
Second Demand Letter which, though not submitted in
Philippines. The decision of the majority of the arbitrators shall be
evidence, was nonetheless admitted by petitioner as
binding upon FKI and respondent.69 (Emphasis supplied)
containing a" demand to eject " in its Answer with
Compulsory Counterclaim.60
The arbitration clause of the 2005 Lease Contract stipulates that "any
disagreement" as to the " interpretation, application or execution " of
2. The petitioner cannot validly invoke the arbitration clause
the 2005 Lease Contract ought to be submitted to arbitration.70 To the
of the 2005 Lease Contract while, at the same time, impugn
mind of this Court, such stipulation is clear and is comprehensive
such contract’s validity.61 Even assuming that it can,
enough so as to include virtually any kind of conflict or dispute that
petitioner still did not file a formal application before the
may arise from the 2005 Lease Contract including the one that
MeTC so as to render such arbitration clause
presently besets petitioner and respondent.
operational.62 At any rate, the MeTC would not be
precluded from exercising its jurisdiction over an action for
unlawful detainer, over which, it has exclusive original The application of the arbitration clause of the 2005 Lease Contract
jurisdiction.63 in this case carries with it certain legal effects. However, before
discussing what these legal effects are, We shall first deal with the
challenges posed against the application of such arbitration clause.
3. The 2005 Lease Contract must be sustained as a valid
contract since petitioner was not able to adduce any
evidence to support its allegation that the same is Challenges Against the Application of the
void.64 There was, in this case, no evidence that respondent Arbitration Clause of the 2005 Lease
is guilty of any tax evasion.65 Contract

Aggrieved, the petitioner appealed to the Court of Appeals. Curiously, despite the lucidity of the arbitration clause of the 2005
Lease Contract, the petitioner, as well as the MeTC, RTC and the
Court of Appeals, vouched for the non-application of the same in the
On 19 August 2011, the Court of Appeals affirmed66 the decision of
instant case. A plethora of arguments was hurled in favor of bypassing
the RTC:
arbitration. We now address them.

WHEREFORE , the petition is DENIED . The assailed Decision of the


At different points in the proceedings of this case, the following
Regional Trial Court of Parañaque City, Branch 274, in Civil Case No.
arguments were offered against the application of the arbitration
10-0255 is AFFIRMED.
clause of the 2005 Lease Contract:

xxxx
1. The disagreement between the petitioner and
respondent is non-arbitrable as it will inevitably touch upon
SO ORDERED.67 the issue of the validity of the 2005 Lease Contract.71 It was
submitted that one of the reasons offered by the petitioner
in justifying its failure to pay under the 2005 Lease Contract
Hence, this appeal.
was the nullity of such contract for being contrary to law and
public policy.72 The Supreme Court, in Gonzales v. Climax
On 5 September 2011, this Court granted petitioner’s prayer for the Mining, Ltd.,73 held that " the validity of contract cannot be
issuance of a Temporary Restraining Order68 staying the immediate subject of arbitration proceedings " as such questions are "
implementation of the decisions adverse to it. legal in nature and require the application and interpretation
of laws and jurisprudence which is necessarily a judicial
function ." 74
OUR RULING

2. The petitioner cannot validly invoke the arbitration clause


Independently of the merits of the case, the MeTC, RTC and Court of
of the 2005 Lease Contract while, at the same time, impugn
Appeals all erred in overlooking the significance of the arbitration such contract’s validity.75
clause incorporated in the 2005 Lease Contract . As the Court sees
it, that is a fatal mistake.
3. Even assuming that it can invoke the arbitration clause
whilst denying the validity of the 2005 Lease Contract ,
For this reason, We grant the petition. petitioner still did not file a formal application before the
MeTC so as to render such arbitration clause
Present Dispute is Arbitrable Under the operational.76 Section 24 of Republic Act No. 9285 requires
Arbitration Clause of the 2005 Lease the party seeking arbitration to first file a " request " or an
Agreement Contract application therefor with the court not later than the
preliminary conference.77
Going back to the records of this case, it is discernable that the dispute
between the petitioner and respondent emanates from the rental 4. Petitioner and respondent already underwent Judicial
stipulations of the 2005 Lease Contract. The respondent insists upon Dispute Resolution (JDR) proceedings before the
the enforce ability and validity of such stipulations, whereas, RTC.78 Hence, a further referral of the dispute to arbitration
petitioner, in substance, repudiates them. It is from petitioner’s would only be circuitous.79 Moreover, an ejectment case, in
apparent breach of the 2005 Lease Contract that respondent filed the view of its summary nature, already fulfills the prime
instant unlawful detainer action. purpose of arbitration, i.e. , to provide parties in conflict with
an expedient method for the resolution of their
dispute.80 Arbitration then would no longer be necessary in
One cannot escape the conclusion that, under the foregoing this case.81
premises, the dispute between the petitioner and respondent arose
from the application or execution of the 2005 Lease Contract .
Undoubtedly, such kinds of dispute are covered by the arbitration None of the arguments have any merit.
clause of the 2005 Lease Contract to wit:
First. As highlighted in the previous discussion, the disagreement
between the petitioner and respondent falls within the all-
encompassing terms of the arbitration clause of the 2005 Lease grounds of fraud and oppression attendant to the execution of the
Contract. While it may be conceded that in the arbitration of such addendum contract and the other contracts emanating from it, and
disagreement, the validity of the 2005 Lease Contract, or at least, of that the complaint should have been filed with the regular courts as it
such contract’s rental stipulations would have to be determined, the involved issues which are judicial in nature.
same would not render such disagreement non-arbitrable. The
quotation from Gonzales that was used to justify the contrary position
Such argument is misplaced and respondent cannot rely on the
was taken out of context. A rereading of Gonzales would fix its
Gonzales case to support its argument.90 (Emphasis ours)
relevance to this case.

Second. Petitioner may still invoke the arbitration clause of the 2005
In Gonzales, a complaint for arbitration was filed before the Panel of
Lease Contract notwithstanding the fact that it assails the validity of
Arbitrators of the Mines and Geosciences Bureau (PA-MGB) seeking
such contract. This is due to the doctrine of separability. 91
the nullification of a Financial Technical Assistance Agreement and
other mining related agreements entered into by private parties.82
Under the doctrine of separability, an arbitration agreement is
considered as independent of the main contract.92 Being a separate
Grounds invoked for the nullification of such agreements include fraud
contract in itself, the arbitration agreement may thus be invoked
and unconstitutionality.83 The pivotal issue that confronted the Court
regardless of the possible nullity or invalidity of the main contract.93
then was whether the PA-MGB has jurisdiction over that particular
arbitration complaint. Stated otherwise, the question was whether the
complaint for arbitration raises arbitrable issues that the PA-MGB can Once again instructive is Cargill, wherein this Court held that, as a
take cognizance of. further consequence of the doctrine of separability, even the very
party who repudiates the main contract may invoke its arbitration
clause.94
Gonzales decided the issue in the negative. In holding that the PA-
MGB was devoid of any jurisdiction to take cognizance of the
complaint for arbitration, this Court pointed out to the provisions of Third . The operation of the arbitration clause in this case is not at all
R.A. No. 7942, or the Mining Act of 1995, which granted the PA-MGB defeated by the failure of the petitioner to file a formal "request" or
with exclusive original jurisdiction only over mining disputes, i.e., application therefor with the MeTC. We find that the filing of a
disputes involving " rights to mining areas," "mineral agreements or "request" pursuant to Section 24 of R.A. No. 9285 is not the sole
permits," and " surface owners, occupants, claim holders or means by which an arbitration clause may be validly invoked in a
concessionaires" requiring the technical knowledge and experience pending suit.
of mining authorities in order to be resolved. 84 Accordingly, since the
complaint for arbitration in Gonzales did not raise mining disputes as
contemplated under R.A. No. 7942 but only issues relating to the Section 24 of R.A. No. 9285 reads:
validity of certain mining related agreements, this Court held that such
complaint could not be arbitrated before the PA-MGB.85 It is in this SEC. 24. Referral to Arbitration . - A court before which an action is
context that we made the pronouncement now in discussion: brought in a matter which is the subject matter of an arbitration
agreement shall, if at least one party so requests not later that the pre-
trial conference, or upon the request of both parties thereafter, refer
Arbitration before the Panel of Arbitrators is proper only when there is
a disagreement between the parties as to some provisions of the the parties to arbitration unless it finds that the arbitration agreement
contract between them, which needs the interpretation and the is null and void, inoperative or incapable of being performed.
[Emphasis ours; italics original]
application of that particular knowledge and expertise possessed by
members of that Panel. It is not proper when one of the parties
repudiates the existence or validity of such contract or agreement on The " request " referred to in the above provision is, in turn,
the ground of fraud or oppression as in this case. The validity of the implemented by Rules 4.1 to 4.3 of A.M. No. 07-11-08-SC or the
contract cannot be subject of arbitration proceedings. Allegations of Special Rules of Court on Alternative Dispute Resolution (Special
fraud and duress in the execution of a contract are matters within the ADR Rules):
jurisdiction of the ordinary courts of law. These questions are legal in
nature and require the application and interpretation of laws and
jurisprudence which is necessarily a judicial function. 86 (Emphasis RULE 4: REFERRAL TO ADR
supplied)
Rule 4.1. Who makes the request. - A party to a pending action filed
The Court in Gonzales did not simply base its rejection of the in violation of the arbitration agreement, whether contained in an
complaint for arbitration on the ground that the issue raised therein, arbitration clause or in a submission agreement, may request the
i.e. , the validity of contracts, is per se non-arbitrable. The real court to refer the parties to arbitration in accordance with such
consideration behind the ruling was the limitation that was placed by agreement.
R.A. No. 7942 upon the jurisdiction of the PA-MGB as an arbitral body
. Gonzales rejected the complaint for arbitration because the issue Rule 4.2. When to make request. - (A) Where the arbitration
raised therein is not a mining dispute per R.A. No. 7942 and it is for agreement exists before the action is filed . - The request for referral
this reason, and only for this reason, that such issue is rendered non- shall be made not later than the pre-trial conference. After the pre-trial
arbitrable before the PA-MGB. As stated beforehand, R.A. No. 7942 conference, the court will only act upon the request for referral if it is
clearly limited the jurisdiction of the PA-MGB only to mining made with the agreement of all parties to the case.
disputes.87
(B) Submission agreement . - If there is no existing arbitration
Much more instructive for our purposes, on the other hand, is the agreement at the time the case is filed but the parties subsequently
recent case of Cargill Philippines, Inc. v. San Fernando Regal enter into an arbitration agreement, they may request the court to refer
Trading, Inc.88 In Cargill , this Court answered the question of whether their dispute to arbitration at any time during the proceedings.
issues involving the rescission of a contract are arbitrable. The
respondent in Cargill argued against arbitrability, also citing therein
Gonzales . After dissecting Gonzales , this Court ruled in favor of Rule 4.3. Contents of request. - The request for referral shall be in the
arbitrability.89 Thus, We held: form of a motion, which shall state that the dispute is covered by an
arbitration agreement.

Respondent contends that assuming that the existence of the contract


and the arbitration clause is conceded, the CA's decision declining A part from other submissions, the movant shall attach to his motion
referral of the parties' dispute to arbitration is still correct. It claims that an authentic copy of the arbitration agreement.
its complaint in the RTC presents the issue of whether under the facts
alleged, it is entitled to rescind the contract with damages; and that The request shall contain a notice of hearing addressed to all parties
issue constitutes a judicial question or one that requires the exercise specifying the date and time when it would be heard. The party
of judicial function and cannot be the subject of an arbitration making the request shall serve it upon the respondent to give him the
proceeding. Respondent cites our ruling in Gonzales, wherein we held opportunity to file a comment or opposition as provided in the
that a panel of arbitrator is bereft of jurisdiction over the complaint for
declaration of nullity/or termination of the subject contracts on the
immediately succeeding Rule before the hearing. [Emphasis ours; R.A. No. 876 Section 7. Stay of civil action. - If any suit or proceeding
italics original] be brought upon an issue arising out of an agreement providing for
the arbitration thereof, the court in which such suit or proceeding is
pending, upon being satisfied that the issue involved in such suit or
Attention must be paid, however, to the salient wordings of Rule 4.1.It
proceeding is referable to arbitration, shall stay the action or
reads: "a party to a pending action filed in violation of the arbitration
proceeding until an arbitration has been had in accordance with the
agreement x x x may request the court to refer the parties to arbitration
terms of the agreement: Provided, That the applicant for the stay is
in accordance with such agreement."
not in default in proceeding with such arbitration.[Emphasis supplied]

In using the word " may " to qualify the act of filing a " request " under
R.A. No. 9285
Section 24 of R.A. No. 9285, the Special ADR Rules clearly did not
intend to limit the invocation of an arbitration agreement in a pending
suit solely via such "request." After all, non-compliance with an Section 24. Referral to Arbitration. - A court before which an action is
arbitration agreement is a valid defense to any offending suit and, as brought in a matter which is the subject matter of an arbitration
such, may even be raised in an answer as provided in our ordinary agreement shall, if at least one party so requests not later that the pre-
rules of procedure.95 trial conference, or upon the request of both parties thereafter, refer
the parties to arbitration unless it finds that the arbitration agreement
is null and void, in operative or incapable of being performed.
In this case, it is conceded that petitioner was not able to file a
[Emphasis supplied]
separate " request " of arbitration before the MeTC. However, it is
equally conceded that the petitioner, as early as in its Answer with
Counterclaim ,had already apprised the MeTC of the existence of the It is clear that under the law, the instant unlawful detainer action
arbitration clause in the 2005 Lease Contract96 and, more should have been stayed;101 the petitioner and the respondent should
significantly, of its desire to have the same enforced in this have been referred to arbitration pursuant to the arbitration clause of
case.97 This act of petitioner is enough valid invocation of his right to the 2005 Lease Contract . The MeTC, however, did not do so in
arbitrate. Fourth . The fact that the petitioner and respondent already violation of the law—which violation was, in turn, affirmed by the RTC
under went through JDR proceedings before the RTC, will not make and Court of Appeals on appeal.
the subsequent conduct of arbitration between the parties
unnecessary or circuitous. The JDR system is substantially different
The violation by the MeTC of the clear directives under R.A. Nos.876
from arbitration proceedings.
and 9285 renders invalid all proceedings it undertook in the ejectment
case after the filing by petitioner of its Answer with Counterclaim —
The JDR framework is based on the processes of mediation, the point when the petitioner and the respondent should have been
conciliation or early neutral evaluation which entails the submission of referred to arbitration. This case must, therefore, be remanded to the
a dispute before a " JDR judge " who shall merely " facilitate MeTC and be suspended at said point. Inevitably, the decisions of the
settlement " between the parties in conflict or make a " non-binding MeTC, RTC and the Court of Appeals must all be vacated and set
evaluation or assessment of the chances of each party’s aside.
case."98 Thus in JDR, the JDR judge lacks the authority to render a
resolution of the dispute that is binding upon the parties in conflict. In
The petitioner and the respondent must then be referred to arbitration
arbitration, on the other hand, the dispute is submitted to an
pursuant to the arbitration clause of the 2005 Lease Contract.
arbitrator/s —a neutral third person or a group of thereof— who shall
have the authority to render a resolution binding upon the parties. 99
This Court is not unaware of the apparent harshness of the Decision
that it is about to make. Nonetheless, this Court must make the same
Clearly, the mere submission of a dispute to JDR proceedings would
if only to stress the point that, in our jurisdiction, bona fide arbitration
not necessarily render the subsequent conduct of arbitration a mere
agreements are recognized as valid;102 and that laws,103 rules and
surplusage. The failure of the parties in conflict to reach an amicable
regulations104 do exist protecting and ensuring their enforcement as a
settlement before the JDR may, in fact, be supplemented by their
matter of state policy. Gone should be the days when courts treat
resort to arbitration where a binding resolution to the dispute could
otherwise valid arbitration agreements with disdain and hostility, if not
finally be achieved. This situation precisely finds application to the
outright " jealousy,"105 and then get away with it. Courts should instead
case at bench.
learn to treat alternative means of dispute resolution as effective
partners in the administration of justice and, in the case of arbitration
Neither would the summary nature of ejectment cases be a valid agreements, to afford them judicial restraint.106 Today, this Court only
reason to disregard the enforcement of the arbitration clause of the performs its part in upholding a once disregarded state policy.
2005 Lease Contract . Notwithstanding the summary nature of
ejectment cases, arbitration still remains relevant as it aims not only
Civil Case No. CV 09-0346
to afford the parties an expeditious method of resolving their dispute.

This Court notes that, on 30 September 2009, petitioner filed with the
A pivotal feature of arbitration as an alternative mode of dispute
RTC of Parañaque City, a complaint107 for the rescission or
resolution is that it is, first and foremost, a product of party autonomy
cancellation of the Deed of Donation and Amended Deed of Donation
or the freedom of the parties to " make their own arrangements to
against the respondent. The case is currently pending before Branch
resolve their own disputes."100 Arbitration agreements manifest not
257 of the RTC, docketed as Civil Case No. CV 09-0346.
only the desire of the parties in conflict for an expeditious resolution
of their dispute. They also represent, if not more so, the parties’
mutual aspiration to achieve such resolution outside of judicial This Court recognizes the great possibility that issues raised in Civil
auspices, in a more informal and less antagonistic environment under Case No. CV 09-0346 may involve matters that are rightfully arbitrable
the terms of their choosing. Needless to state, this critical feature can per the arbitration clause of the 2005 Lease Contract. However, since
never be satisfied in an ejectment case no matter how summary it the records of Civil Case No. CV 09-0346 are not before this Court,
may be. We can never know with true certainty and only speculate. In this light,
let a copy of this Decision be also served to Branch 257of the RTC of
Parañaque for its consideration and, possible, application to Civil
Having hurdled all the challenges against the application of the
Case No. CV 09-0346.
arbitration clause of the 2005 Lease Agreement in this case, We shall
now proceed with the discussion of its legal effects.
WHEREFORE, premises considered, the petition is hereby
GRANTED . Accordingly, We hereby render a Decision:
Legal Effect of the Application of the
Arbitration Clause
1. SETTING ASIDE all the proceedings undertaken by the
Metropolitan Trial Court, Branch 77, of Parañaque City in
Since there really are no legal impediments to the application of the
relation to Civil Case No. 2009-307 after the filing by
arbitration clause of the 2005 Contract of Lease in this case, We find
petitioner of its Answer with Counterclaim ;
that the instant unlawful detainer action was instituted in violation of
such clause. The Law, therefore, should have governed the fate of the
parties and this suit:
2. REMANDING the instant case to the MeTC,
SUSPENDED at the point after the filing by petitioner of its
Answer with Counterclaim;

3. SETTING ASIDE the following:

a. Decision dated 19 August 2011 of the Court of


Appeals in C.A.-G.R. SP No. 116865,

b. Decision dated 29 October 2010 of the


Regional Trial Court, Branch 274, of Parañaque
City in Civil Case No. 10-0255,

c. Decision dated 27 April 2010 of the


Metropolitan Trial Court, Branch 77, of
Parañaque City in Civil Case No. 2009-307; and

4. REFERRING the petitioner and the respondent to


arbitration pursuant to the arbitration clause of the 2005
Lease Contract, repeatedly included in the 2000 Lease
Contract and in the 1976 Amended Deed of Donation.

Let a copy of this Decision be served to Branch 257 of the RTC of


Parañaque for its consideration and, possible, application to Civil
Case No. CV 09-0346.
G.R. No. 199650 June 26, 2013 of the project is 68.61% with an estimated value per
construction agreement signed is
₱27,880,419.52.9 (Emphasis supplied.)
J PLUS ASIA DEVELOPMENT CORPORATION, Petitioner,
vs.
UTILITY ASSURANCE CORPORATION, Respondent. On November 19, 2008, petitioner terminated the contract and sent
demand letters to Mabunay and respondent surety. As its demands
went unheeded, petitioner filed a Request for Arbitration10 before the
DECISION
Construction Industry Arbitration Commission (CIAC). Petitioner
prayed that Mabunay and respondent be ordered to pay the sums of
VILLARAMA, JR., J.: ₱8,980,575.89 as liquidated damages and ₱2,379,441.53
corresponding to the unrecouped down payment or overpayment
petitioner made to Mabunay.11
Before the Court is a petition for review on certiorari under Rule 45 of
the 1997 Rules of Civil Procedure, as amended, assailing the
Decision1 dated January 27,2011 and Resolution2 dated December 8, In his Answer,12 Mabunay claimed that the delay was caused by
2011 of the Court of Appeals (CA) in CA-G.R. SP No. 112808. retrofitting and other revision works ordered by Joo Han Lee. He
asserted that he actually had until April 30, 2009 to finish the project
since the 365 days period of completion started only on May 2, 2008
The Facts after clearing the retrofitted old structure. Hence, the termination of
the contract by petitioner was premature and the filing of the complaint
On December 24, 2007, petitioner J Plus Asia Development against him was baseless, malicious and in bad faith.
Corporation represented by its Chairman, Joo Han Lee, and Martin E.
Mabunay, doing business under the name and style of Seven Shades Respondent, on the other hand, filed a motion to dismiss on the
of Blue Trading and Services, entered into a Construction
ground that petitioner has no cause of action and the complaint states
Agreement3 whereby the latter undertook to build the former's 72- no cause of action against it. The CIAC denied the motion to dismiss.
room condominium/hotel (Condotel Building 25) located at the Respondent’s motion for reconsideration was likewise denied. 13
Fairways & Bluewaters Golf & Resort in Boracay Island, Malay, Aklan.
The project, costing ₱42,000,000.00, was to be completed within one
year or 365 days reckoned from the first calendar day after signing of In its Answer Ex Abundante Ad Cautelam With Compulsory
the Notice of Award and Notice to Proceed and receipt of down Counterclaims and Cross-claims,14 respondent argued that the
payment (20% of contract price). The ₱8,400,000.00 down payment performance bond merely guaranteed the 20% down payment and
was fully paid on January 14, 2008.4 Payment of the balance of the not the entire obligation of Mabunay under the Construction
contract price will be based on actual work finished within 15 days Agreement. Since the value of the project’s accomplishment already
from receipt of the monthly progress billings. Per the agreed work exceeded the said amount, respondent’s obligation under the
schedule, the completion date of the project was December performance bond had been fully extinguished. As to the claim for
2008.5 Mabuhay also submitted the required Performance alleged overpayment to Mabunay, respondent contended that it
Bond6 issued by respondent Utility Assurance Corporation should not be credited against the 20% down payment which was
(UTASSCO) in the amount equivalent to 20% down payment or ₱8.4 already exhausted and such application by petitioner is tantamount to
million. reviving an obligation that had been legally extinguished by payment.
Respondent also set up a cross-claim against Mabunay who executed
in its favor an Indemnity Agreement whereby Mabunay undertook to
Mabunay commenced work at the project site on January 7, 2008.
indemnify respondent for whatever amounts it may be adjudged liable
Petitioner paid up to the 7th monthly progress billing sent by Mabunay. to pay petitioner under the surety bond.
As of September 16, 2008, petitioner had paid the total amount of
₱15,979,472.03 inclusive of the 20% down payment. However, as of
said date, Mabunay had accomplished only 27.5% of the project. 7 Both petitioner and respondent submitted their respective
documentary and testimonial evidence. Mabunay failed to appear in
the scheduled hearings and to present his evidence despite due
In the Joint Construction Evaluation Result and Status Report8 signed
notice to his counsel of record. The CIAC thus declared that Mabunay
by Mabunay assisted by Arch. Elwin Olavario, and Joo Han Lee is deemed to have waived his right to present evidence.15
assisted by Roy V. Movido, the following findings were accepted as
true, accurate and correct:
On February 2, 2010, the CIAC rendered its Decision16 and made the
following award:
III STATUS OF PROJECT AS OF 14 NOVEMBER 2008

Accordingly, in view of our foregoing discussions and dispositions, the


1) After conducting a joint inspection and evaluation of the Tribunal hereby adjudges, orders and directs:
project to determine the actual percentage of
accomplishment, the contracting parties, assisted by their
respective technical groups, SSB assisted by Arch. Elwin 1. Respondents Mabunay and Utassco to jointly and
Olavario and JPLUS assisted by Engrs. Joey Rojas and severally pay claimant the following:
Shiela Botardo, concluded and agreed that as of 14
November 2008, the project is only Thirty One point Thirty
a) ₱4,469,969.90, as liquidated damages, plus
Nine Percent (31.39%) complete.
legal interest thereon at the rate of 6% per annum
computed from the date of this decision up to the
2) Furthermore, the value of construction materials time this decision becomes final, and 12% per
allocated for the completion of the project and currently on annum computed from the date this decision
site has been determined and agreed to be ONE MILLION becomes final until fully paid, and
FORTY NINE THOUSAND THREE HUNDRED SIXTY
FOUR PESOS AND FORTY FIVE CENTAVOS
b) ₱2,379,441.53 as unrecouped down payment
(₱1,049,364.45)
plus interest thereon at the rate of 6% per annum
computed from the date of this decision up to the
3) The additional accomplishment of SSB, reflected in its time this decision becomes final, and 12% per
reconciled and consolidated 8th and 9th billings, is Three annum computed from the date this decision
point Eighty Five Percent (3.85%) with a gross value of becomes final until fully paid.
₱1,563,553.34 amount creditable to SSB after deducting
the withholding tax is ₱1,538,424.84
It being understood that respondent Utassco’s liability shall
in no case exceed ₱8.4 million.
4) The unrecouped amount of the down payment is
₱2,379,441.53 after deducting the cost of materials on site
2. Respondent Mabunay to pay to claimant the amount of
and the net billable amount reflected in the reconciled and
₱98,435.89, which is respondent Mabunay’s share in the
consolidated 8th and 9th billings. The uncompleted portion
arbitration cost claimant had advanced, with legal interest ASSIGNED AS ANERROR, AND NOT ARGUED IN ANY
thereon from January 8, 2010 until fully paid. OF THE PLEADINGS FILED BEFORE THE COURT.

3. Respondent Mabunay to indemnify respondent Utassco C. THE COURT OF APPEALS SERIOUSLY ERRED IN
of the amounts respondent Utassco will have paid to RELYING ON THE CASE OF AEROSPACE CHEMICAL
claimant under this decision, plus interest thereon at the INDUSTRIES, INC. v. COURT OF APPEALS, 315 SCRA
rate of 12% per annum computed from the date he is 94, WHICH HAS NOTHING TO DO WITH
notified of such payment made by respondent Utassco to CONSTRUCTION AGREEMENTS.21
claimant until fully paid, and to pay Utassco ₱100,000.00
as attorney’s fees.
Our Ruling

SO ORDERED.17
On the procedural issues raised, we find no merit in petitioner’s
contention that with the institutionalization of alternative dispute
Dissatisfied, respondent filed in the CA a petition for review under resolution under Republic Act (R.A.) No. 9285,22 otherwise known as
Rule 43 of the 1997 Rules of Civil Procedure, as amended. the Alternative Dispute Resolution Act of 2004, the CA was divested
of jurisdiction to review the decisions or awards of the CIAC. Petitioner
erroneously relied on the provision in said law allowing any party to a
In the assailed decision, the CA agreed with the CIAC that the specific
domestic arbitration to file in the Regional Trial Court (RTC) a petition
condition in the Performance Bond did not clearly state the limitation
either to confirm, correct or vacate a domestic arbitral award.
of the surety’s liability. Pursuant to Article 137718 of the Civil Code, the
CA said that the provision should be construed in favor of petitioner
considering that the obscurely phrased provision was drawn up by We hold that R.A. No. 9285 did not confer on regional trial courts
respondent and Mabunay. Further, the appellate court stated that jurisdiction to review awards or decisions of the CIAC in construction
respondent could not possibly guarantee the down payment because disputes. On the contrary, Section 40 thereof expressly declares that
it is not Mabunay who owed the down payment to petitioner but the confirmation by the RTC is not required, thus:
other way around. Consequently, the completion by Mabunay of
31.39% of the construction would not lead to the extinguishment of
SEC. 40. Confirmation of Award. – The confirmation of a domestic
respondent’s liability. The ₱8.4 million was a limit on the amount of
arbitral award shall be governed by Section 23 of R.A. 876.
respondent’s liability and not a limitation as to the obligation or
undertaking it guaranteed.
A domestic arbitral award when confirmed shall be enforced in the
same manner as final and executory decisions of the Regional Trial
However, the CA reversed the CIAC’s ruling that Mabunay had
Court.
incurred delay which entitled petitioner to the stipulated liquidated
damages and unrecouped down payment. Citing Aerospace
Chemical Industries, Inc. v. Court of Appeals,19 the appellate court The confirmation of a domestic award shall be made by the regional
said that not all requisites in order to consider the obligor or debtor in trial court in accordance with the Rules of Procedure to be
default were present in this case. It held that it is only from December promulgated by the Supreme Court.
24, 2008 (completion date) that we should reckon default because the
Construction Agreement provided only for delay in the completion of
the project and not delay on a monthly basis using the work schedule A CIAC arbitral award need not be confirmed by the regional trial court
to be executory as provided under E.O. No. 1008. (Emphasis
approved by petitioner as the reference point. Hence, petitioner’s
termination of the contract was premature since the delay in this case supplied.)
was merely speculative; the obligation was not yet demandable.
Executive Order (EO) No. 1008 vests upon the CIAC original and
The dispositive portion of the CA Decision reads: exclusive jurisdiction over disputes arising from, or connected with,
contracts entered into by parties involved in construction in the
Philippines, whether the dispute arises before or after the completion
WHEREFORE, premises considered, the instant petition for review is of the contract, or after the abandonment or breach thereof. By
GRANTED. The assailed Decision dated 13 January 2010 rendered express provision of Section 19 thereof, the arbitral award of the CIAC
by the CIAC Arbitral Tribunal in CIAC Case No. 03-2009 is hereby is final and unappealable, except on questions of law, which are
REVERSED and SET ASIDE. Accordingly, the Writ of Execution appealable to the Supreme Court. With the amendments introduced
dated 24 November 2010 issued by the same tribunal is hereby by R.A. No. 7902 and promulgation of the 1997 Rules of Civil
ANNULLED and SET ASIDE. Procedure, as amended, the CIAC was included in the enumeration
of quasijudicial agencies whose decisions or awards may be appealed
to the CA in a petition for review under Rule 43. Such review of the
SO ORDERED.20
CIAC award may involve either questions of fact, of law, or of fact and
law.23
Petitioner moved for reconsideration of the CA decision while
respondent filed a motion for partial reconsideration. Both motions
Petitioner misread the provisions of A.M. No. 07-11-08-SC (Special
were denied.
ADR Rules) promulgated by this Court and which took effect on
October 30, 2009. Since R.A. No. 9285 explicitly excluded CIAC
The Issues awards from domestic arbitration awards that need to be confirmed to
be executory, said awards are therefore not covered by Rule 11 of the
Special ADR Rules,24 as they continue to be governed by EO No.
Before this Court petitioner seeks to reverse the CA insofar as it
1008, as amended and the rules of procedure of the CIAC. The CIAC
denied petitioner’s claims under the Performance Bond and to
Revised Rules of Procedure Governing Construction
reinstate in its entirety the February 2, 2010 CIAC Decision.
Arbitration25 provide for the manner and mode of appeal from CIAC
Specifically, petitioner alleged that –
decisions or awards in Section 18 thereof, which reads:

A. THE COURT OF APPEALS SERIOUSLY ERRED IN


SECTION 18.2 Petition for review. – A petition for review from a final
NOT HOLDING THAT THE ALTERNATIVE DISPUTE
award may be taken by any of the parties within fifteen (15) days from
RESOLUTION ACT AND THE SPECIAL RULES ON
receipt thereof in accordance with the provisions of Rule 43 of the
ALTERNATIVE DISPUTE RESOLUTION HAVE
Rules of Court.
STRIPPED THE COURT OF APPEALS OF
JURISDICTION TO REVIEW ARBITRAL AWARDS.
As to the alleged error committed by the CA in deciding the case upon
an issue not raised or litigated before the CIAC, this assertion has no
B. THE COURT OF APPEALS SERIOUSLY ERRED IN
basis. Whether or not Mabunay had incurred delay in the performance
REVERSING THE ARBITRAL AWARD ON AN ISSUE
of his obligations under the Construction Agreement was the very first
THAT WAS NOT RAISED IN THE ANSWER. NOT
issue stipulated in the Terms of Reference26 (TOR), which is distinct
IDENTIFIED IN THE TERMS OF REFERENCE, NOT
from the issue of the extent of respondent’s liability under the Records showed that as early as April 2008, or within four months
Performance Bond. after Mabunay commenced work activities, the project was already
behind schedule for reasons not attributable to petitioner. In the
succeeding months, Mabunay was still unable to catch up with his
Indeed, resolution of the issue of delay was crucial upon which
accomplishment even as petitioner constantly advised him of the
depends petitioner’s right to the liquidated damages pursuant to the
delays, as can be gleaned from the following notices of delay sent by
Construction Agreement. Contrary to the CIAC’s findings, the CA
petitioner’s engineer and construction manager, Engr. Sheila N.
opined that delay should be reckoned only after the lapse of the one-
Botardo:
year contract period, and consequently Mabunay’s liability for
liquidated damages arises only upon the happening of such condition.
April 30, 2008
We reverse the CA.
Seven Shades of Blue
Boracay Island
Default or mora on the part of the debtor is the delay in the fulfillment
Malay, Aklan
of the prestation by reason of a cause imputable to the former. It is
the non-fulfillment of an obligation with respect to time.27
1âwphi1
Article 1169 of the Civil Code provides:
Attention : Mr. Martin Mabunay
General Manager
ART. 1169. Those obliged to deliver or to do something incur in delay
from the time the obligee judicially or extrajudicially demands from Thru : Engr. Reynaldo Gapasin
them the fulfillment of their obligation.
Project : Villa Beatriz
xxxx
Subject : Notice of Delay

It is a general rule that one who contracts to complete certain work


within a certain time is liable for the damage for not completing it within Dear Mr. Mabunay:
such time, unless the delay is excused or waived.28
This is to formalize our discussion with your Engineers during our
The Construction Agreement provides in Article 10 thereof the meeting last April 23, 2008 regarding the delay in the implementation
following conditions as to completion time for the project of major activities based on your submitted construction schedule.
Substantial delay was noted in concreting works that affects your roof
framing that should have been 40% completed as of this date. This
1. The CONTRACTOR shall complete the works called for
delay will create major impact on your over-all schedule as the
under this Agreement within ONE (1) YEAR or 365 Days
finishing works will all be dependent on the enclosure of the building.
reckoned from the 1st calendar day after signing of the
Notice of Award and Notice to Proceed and receipt of down
payment. In this regard, we recommend that you prepare a catch-up schedule
and expedite the delivery of critical materials on site. We would highly
appreciate if you could attend our next regular meeting so we could
2. In this regard the CONTRACTOR shall submit a detailed
immediately address this matter. Thank you.
work schedule for approval by OWNER within Seven (7)
days after signing of this Agreement and full payment of
20% of the agreed contract price. Said detailed work Very truly yours,
schedule shall follow the general schedule of activities and
shall serve as basis for the evaluation of the progress of
work by CONTRACTOR.29 Engr. Sheila N. Botardo
Construction Manager – LMI/FEPI32

In this jurisdiction, the following requisites must be present in order


that the debtor may be in default: (1) that the obligation be October 15, 2008
demandable and already liquidated; (2) that the debtor delays
performance; and (3) that the creditor requires the performance xxxx
judicially or extrajudicially.30
Dear Mr. Mabunay,
In holding that Mabunay has not at all incurred delay, the CA pointed
out that the obligation to perform or complete the project was not yet
demandable as of November 19, 2008 when petitioner terminated the We have noticed continuous absence of all the Engineers that you
contract, because the agreed completion date was still more than one have assigned on-site to administer and supervise your contracted
month away (December 24, 2008). Since the parties contemplated work. For the past two (2) weeks, your company does not have a
delay in the completion of the entire project, the CA concluded that Technical Representative manning the jobsite considering the critical
the failure of the contractor to catch up with schedule of work activities activities that are in progress and the delays in schedule that you have
did not constitute delay giving rise to the contractor’s liability for already incurred. In this regard, we would highly recommend the
damages. immediate replacement of your Project Engineer within the week.

We cannot sustain the appellate court’s interpretation as it is We would highly appreciate your usual attention on this matter.
inconsistent with the terms of the Construction Agreement. Article
1374 of the Civil Code requires that the various stipulations of a x x x x33
contract shall be interpreted together, attributing to the doubtful ones
that sense which may result from all of them taken jointly. Here, the
work schedule approved by petitioner was intended, not only to serve November 5, 2008
as its basis for the payment of monthly progress billings, but also for
evaluation of the progress of work by the contractor. Article 13.01 (g) xxxx
(iii) of the Construction Agreement provides that the contractor shall
be deemed in default if, among others, it had delayed without
justifiable cause the completion of the project "by more than thirty (30) Dear Mr. Mabunay,
calendar days based on official work schedule duly approved by the
OWNER."31 This is in reference to your discussion during the meeting with Mr.
Joohan Lee last October 30, 2008 regarding the construction of the
Field Office and Stock Room for Materials intended for Villa Beatriz
use only. We understand that you have committed to complete it OWNER when the works called for under this Agreement have been
November 5, 2008 but as of this date there is no improvement or any finished and completed.
ongoing construction activity on the said field office and stockroom.
Liquidated Damage[s] payable to the OWNER shall be automatically
We are expecting deliveries of Owner Supplied Materials very soon, deducted from the contractors collectibles without prior consent and
therefore, this stockroom is badly needed. We will highly appreciate if concurrence by the CONTRACTOR.
this matter will be given your immediate attention.
12.02 To give full force and effect to the foregoing, the
Thank you. CONTRACTOR hereby, without necessity of any further act and deed,
authorizes the OWNER to deduct any amount that may be due under
Item (a) above, from any and all money or amounts due or which will
x x x x34
become due to the CONTRACTOR by virtue of this Agreement and/or
to collect such amounts from the Performance Bond filed by the
November 6, 2008 CONTRACTOR in this Agreement.36 (Emphasis supplied.)

xxxx Liability for liquidated damages is governed by Articles 2226 to 2228


of the Civil Code, which provide:
Dear Mr. Mabunay,
ART. 2226. Liquidated damages are those agreed upon by the parties
to a contract, to be paid in case of breach thereof.
We would like to call your attention regarding the decrease in your
manpower assigned on site. We have observed that for the past three
(3) weeks instead of increasing your manpower to catch up with the ART. 2227. Liquidated damages, whether intended as an indemnity
delay it was reduced to only 8 workers today from an average of 35 or a penalty, shall be equitably reduced if they are iniquitous or
workers in the previous months. unconscionable.

Please note that based on your submitted revised schedule you are ART. 2228. When the breach of the contract committed by the
already delayed by approximately 57% and this will worsen should defendant is not the one contemplated by the parties in agreeing upon
you not address this matter properly. the liquidated damages, the law shall determine the measure of
damages, and not the stipulation.
We are looking forward for [sic] your cooperation and continuous
commitment in delivering this project as per contract agreement. A stipulation for liquidated damages is attached to an obligation in
order to ensure performance and has a double function: (1) to provide
for liquidated damages, and (2) to strengthen the coercive force of the
x x x x35 obligation by the threat of greater responsibility in the event of
breach.37 The amount agreed upon answers for damages suffered by
Subsequently, a joint inspection and evaluation was conducted with the owner due to delays in the completion of the project.38 As a
the assistance of the architects and engineers of petitioner and precondition to such award, however, there must be proof of the fact
Mabunay and it was found that as of November 14, 2008, the project of delay in the performance of the obligation.39
was only 31.39% complete and that the uncompleted portion was
68.61% with an estimated value per Construction Agreement as
Concededly, Article 12.01 of the Construction Agreement mentioned
₱27,880,419.52. Instead of doubling his efforts as the scheduled only the failure of the contractor to complete the project within the
completion date approached, Mabunay did nothing to remedy the stipulated period or the extension granted by the owner. However, this
delays and even reduced the deployment of workers at the project
will not defeat petitioner’s claim for damages nor respondent’s liability
site. Neither did Mabunay, at anytime, ask for an extension to under the Performance Bond. Mabunay was clearly in default
complete the project. Thus, on November 19, 2008, petitioner advised considering the dismal percentage of his accomplishment (32.38%) of
Mabunay of its decision to terminate the contract on account of the
the work he contracted on account of delays in executing the
tremendous delay the latter incurred. This was followed by the claim scheduled work activities and repeated failure to provide sufficient
against the Performance Bond upon the respondent on December 18, manpower to expedite construction works. The events of default and
2008.
remedies of the Owner are set forth in Article 13, which reads:

Petitioner’s claim against the Performance Bond included the ARTICLE 13 – DEFAULT OF CONTRACTOR:
liquidated damages provided in the Construction Agreement, as
follows:
13.01 Any of the following shall constitute an Event of Default on the
part of the CONTRACTOR.
ARTICLE 12 – LIQUIDATED DAMAGES:

xxxx
12.01 Time is of the essence in this Agreement. Should the
CONTRACTOR fail to complete the PROJECT within the period
stipulated herein or within the period of extension granted by the g. In case the CONTRACTOR has done any of the following:
OWNER, plus One (1) Week grace period, without any justifiable
reason, the CONTRACTOR hereby agrees –
(i.) has abandoned the Project

a. The CONTRACTOR shall pay the OWNER liquidated


(ii.) without reasonable cause, has failed to commence the
damages equivalent to One Tenth of One Percent (1/10 of
construction or has suspended the progress of the Project
1%) of the Contract Amount for each day of delay after any
for twenty-eight days
and all extensions and the One (1) week Grace Period until
completed by the CONTRACTOR.
(iii.) without justifiable cause, has delayed the completion of
the Project by more than thirty (30) calendar days based on
b. The CONTRACTOR, even after paying for the liquidated
official work schedule duly approved by the OWNER
damages due to unexecuted works and/or delays shall not
relieve it of the obligation to complete and finish the
construction. (iv.) despite previous written warning by the OWNER, is not
executing the construction works in accordance with the
Agreement or is persistently or flagrantly neglecting to carry
Any sum which maybe payable to the OWNER for such loss may be
out its obligations under the Agreement.
deducted from the amounts retained under Article 9 or retained by the
(v.) has, to the detriment of good workmanship or in Lodgings inside Fairways and Bluewater, Boracay Island, Malay,
defiance of the Owner’s instructions to the contrary, sublet Aklan.
any part of the Agreement.
Whereas, said contract required said Principal to give a good and
13.02 If the CONTRACTOR has committed any of the above reasons sufficient bond in the above-stated sum to secure the full and faithful
cited in Item 13.01, the OWNER may after giving fourteen (14) performance on his part of said contract.
calendar days notice in writing to the CONTRACTOR, enter upon the
site and expel the CONTRACTOR therefrom without voiding this
It is a special provision of this undertaking that the liability of the surety
Agreement, or releasing the CONTRACTOR from any of its
under this bond shall in no case exceed the sum of ₱8,400,000.00
obligations, and liabilities under this Agreement. Also without
Philippine Currency.
diminishing or affecting the rights and powers conferred on the
OWNER by this Agreement and the OWNER may himself complete
the work or may employ any other contractor to complete the work. If Now, Therefore, if the Principal shall well and truly perform and fulfill
the OWNER shall enter and expel the CONTRACTOR under this all the undertakings, covenants, terms, conditions and agreements
clause, the OWNER shall be entitled to confiscate the performance stipulated in said contract, then this obligation shall be null and void;
bond of the CONTRACTOR to compensate for all kinds of damages otherwise to remain in full force and effect.43 (Emphasis supplied.)
the OWNER may suffer. All expenses incurred to finish the Project
shall be charged to the CONTRACTOR and/or his bond. Further, the
OWNER shall not be liable to pay the CONTRACTOR until the cost of While the above condition or specific guarantee is unclear, the rest of
the recitals in the bond unequivocally declare that it secures the full
execution, damages for the delay in the completion, if any, and all;
other expenses incurred by the OWNER have been ascertained which and faithful performance of Mabunay’s obligations under the
amount shall be deducted from any money due to the CONTRACTOR Construction Agreement with petitioner. By its nature, a performance
bond guarantees that the contractor will perform the contract, and
on account of this Agreement. The CONTRACTOR will not be
compensated for any loss of profit, loss of goodwill, loss of use of any usually provides that if the contractor defaults and fails to complete
equipment or property, loss of business opportunity, additional the contract, the surety can itself complete the contract or pay
damages up to the limit of the bond.44 Moreover, the rule is that if the
financing cost or overhead or opportunity losses related to the
unaccomplished portions of the work.40 (Emphasis supplied.) language of the bond is ambiguous or uncertain, it will be construed
most strongly against a compensated surety and in favor of the
obligees or beneficiaries under the bond, in this case petitioner as the
As already demonstrated, the contractor’s default in this case pertains Project Owner, for whose benefit it was ostensibly executed. 45
to his failure to substantially perform the work on account of
tremendous delays in executing the scheduled work activities. Where
a party to a building construction contract fails to comply with the duty The imposition of interest on the claims of petitioner is likewise in
imposed by the terms of the contract, a breach results for which an order. As we held in Commonwealth Insurance Corporation v. Court
of Appeals46
action may be maintained to recover the damages sustained thereby,
and of course, a breach occurs where the contractor inexcusably fails
to perform substantially in accordance with the terms of the contract. 41 Petitioner argues that it should not be made to pay interest because
its issuance of the surety bonds was made on the condition that its
The plain and unambiguous terms of the Construction Agreement liability shall in no case exceed the amount of the said bonds.
authorize petitioner to confiscate the Performance Bond to answer for
all kinds of damages it may suffer as a result of the contractor’s failure We are not persuaded. Petitioner’s argument is misplaced.
to complete the building. Having elected to terminate the contract and
expel the contractor from the project site under Article 13 of the said
Agreement, petitioner is clearly entitled to the proceeds of the bond Jurisprudence is clear on this matter. As early as Tagawa vs.
as indemnification for damages it sustained due to the breach Aldanese and Union Gurantee Co. and reiterated in Plaridel Surety &
committed by Mabunay. Such stipulation allowing the confiscation of Insurance Co., Inc. vs. P.L. Galang Machinery Co., Inc., and more
the contractor’s performance bond partakes of the nature of a penalty recently, in Republic vs. Court of Appeals and R & B Surety and
clause. A penalty clause, expressly recognized by law, is an Insurance Company, Inc., we have sustained the principle that if a
accessory undertaking to assume greater liability on the part of the surety upon demand fails to pay, he can be held liable for interest,
obligor in case of breach of an obligation. It functions to strengthen even if in thus paying, its liability becomes more than the principal
the coercive force of obligation and to provide, in effect, for what could obligation. The increased liability is not because of the contract but
be the liquidated damages resulting from such a breach. The obligor because of the default and the necessity of judicial collection.
would then be bound to pay the stipulated indemnity without the
necessity of proof on the existence and on the measure of damages Petitioner’s liability under the suretyship contract is different from its
caused by the breach. It is well-settled that so long as such stipulation liability under the law.1âwphi1 There is no question that as a surety,
does not contravene law, morals, or public order, it is strictly binding petitioner should not be made to pay more than its assumed obligation
upon the obligor.42 under the surety bonds. However, it is clear from the above-cited
jurisprudence that petitioner’s liability for the payment of interest is not
Respondent, however, insists that it is not liable for the breach by reason of the suretyship agreement itself but because of the delay
committed by Mabunay because by the terms of the surety bond it in the payment of its obligation under the said
issued, its liability is limited to the performance by said contractor to agreement.47 (Emphasis supplied; citations omitted.)
the extent equivalent to 20% of the down payment. It stresses that
with the 32.38% completion of the project by Mabunay, its liability was WHEREFORE, the petition for review on certiorari is GRANTED. The
extinguished because the value of such accomplishment already Decision dated January 27, 2011 and Resolution dated December 8,
exceeded the sum equivalent to 20% down payment (₱8.4 million). 2011 of the Court of Appeals in CA-G.R. SP No. 112808 are hereby
REVERSED and SET ASIDE.
The appellate court correctly rejected this theory of respondent when
it ruled that the Performance Bond guaranteed the full and faithful The Award made in the Decision dated February 2, 2010 of the
compliance of Mabunay’s obligations under the Construction Construction Industry Arbitration Commission Is hereby
Agreement, and that nowhere in law or jurisprudence does it state that REINSTATED with the following MODIFICATIONS:
the obligation or undertaking by a surety may be apportioned.
"Accordingly, in view of our foregoing discussions and dispositions,
The pertinent portions of the Performance Bond provide: the Tribunal hereby adjudges, orders and directs:

The conditions of this obligation are as follows: 1) Respondent Utassco to pay to petitioner J Plus Asia
Development Corporation the full amount of the
Whereas the JPLUS ASIA, requires the principal SEVEN SHADES Performance Bond, ₱8,400,000.00, pursuant to Art. 13 of
OF BLUE CONSTRUCTION AND DEVELOPMENT, INC. to post a the Construction Agreement dated December 24, 2007,
bond of the abovestated sum to guarantee 20% down payment for the with interest at the rate of 6% per annum computed from
construction of Building 25 (Villa Beatriz) 72-Room Condotel, The the date of the filing of the complaint until the finality of this
decision, and 12% per annum computed from the date this
decision becomes final until fully paid; and

2) Respondent Mabunay to indemnify respondent Utassco


of the amounts respondent Utassco will have paid to
claimant under this decision, plus interest thereon at the
rate of 12% per annum computed from the date he is
notified of such payment made by respondent Utassco to
claimant until fully paid, and to pay Utassco ₱100,000.00
as attorney's fees.

SO ORDERED.

With the above modifications, the Writ of Execution dated November


24, 2010 issued by the CIAC Arbitral Tribunal in CIAC Case No. 03-
2009 is hereby REINSTATED and UPHELD.

No pronouncement as to costs.

SO ORDERED.
G.R. No. 91228. March 22, 1993. accordance with the terms of their agreement (Sec. 6 Republic Act
876). Respondent's arguments touching upon the merits of the
dispute are improperly raised herein. They should be addressed to
PUROMINES, INC., petitioner, vs. COURT OF APPEAL and PHILIPP
the arbitrators. This proceeding is merely a summary remedy to
BROTHERS OCEANIC, INC., respondents.
enforce the agreement to arbitrate. The duty of the court in this case
is not to resolve the merits of the parties' claims but only to determine
SYLLABUS if they should proceed to arbitration or not. And although it has been
ruled that a privolous or patently baseless claim should not be ordered
to arbitration it is also recognized that the mere fact that a defense
1. CIVIL LAW; OBLIGATIONS OF VENDOR; DAMAGES ARISING exist against a claim does not make it frivolous or baseless."
FROM CARRIAGE AND DELIVERY. — We agree with the court a
quo that the sales contract is comprehensive enough to include claims
for damages arising from carriage and delivery of the goods. As a 7. REMEDIAL LAW; CIVIL PROCEDURE; PLEADINGS;
general rule, the seller has the obligation to transmit the goods to the COMPLAINT; ANNEXES ATTACHED THEREOF, PART OF THE
buyer, and concomitant thereto, the contracting of a carrier to deliver RECORD. — Petitioner contend that the arbitration provision in the
the same. bills of lading should not have been discussed as an issue in the
decision of the Court of Appeals since it was not raised as a special
or affirmative defense. The three bills of lading were attached to the
2. COMMERCIAL LAW; MARITIME TRANSPORTATION; MARITIME complaint as Annexes "A," "B," and "C," and are therefore parts
COMMERCE; CHARTER PARTIES, CONSTRUED. — American thereof and may be considered as evidence although not introduced
jurisprudence defines charter party as a contract by which an entire
as such. Hence, it was then proper for the court a quo to discuss the
ship or some principal part thereof is let by the owner to another contents of the bills of lading, having been made part of the record.
person for a specified time or use. Charter or charter parties are of
two kinds. Charter of demise or bareboat and contracts of
affreightment. DECISION

3. ID.; ID.; ID.; ID.; KINDS; CHARTER OF DEMISE, CONSTRUED. NOCON, J p:


— Under the demise or bareboat charter of the vessel, the charterer
will generally be considered as owner for the voyage or service
This is a special civil action for certiorari and prohibition to annul and
stipulated. The charterer mans the vessel with his own people and
set aside the Decision of the respondent Court of Appeals dated
becomes, in effect, the owner pro hac vice, subject to liability to others
November 16, 1989 1 reversing the order of the trial court and
for damages caused by negligence. To create a demise the owner of
dismissing petitioner's compliant in Civil Case No. 89-47403, entitled
a vessel must completely and exclusively relinquish possession,
Puromines, Inc. v. Maritime Factors, Inc. and Philipp Brothers
anything short of such a complete transfer is a contract of
Oceanic, Inc.
affreightment (time or voyage charter party) or not a charter party at
all.
Culled from the records of this case, the facts show that petitioner,
Puromines, Inc. (Puromines for brevity) and Makati Agro Trading, Inc.
4. ID.; ID.; ID.; ID.; ID.; CONTRACT OF AFFREIGNMENT,
(not a party in this case) entered into a contract with private
CONSTRUED. — A contract of affreightment is in which the owner of
respondents Philipp Brothers Oceanic, Inc. for the sale of prilled Urea
the vessel leases part or all of its space to haul goods for others. It is
in bulk. The Sales Contract No. S151.8.01018 provided, among
a contract for a special service to be rendered by the owner of the
others an arbitration clause which states, thus:
vessel and under such contract the general owner retains the
possession, command and navigation of the ship, the charterer or
freighter merely having use of the space in the vessel in return for his "9. Arbitration
payment of the charter hire. If the charter is a contract of
affreightment, which leaves the general owner in possession of the
"Any disputes arising under this contract shall be settled by arbitration
ship as owner for the voyage, the rights, responsibilities of ownership
in London in accordance with the Arbitration Act 1950 and any
rest on the owner and the charterer is usually free from liability to third
statutory amendment or modification thereof. Each party is to appoint
persons in respect of the ship.
an Arbitrator, and should they be unable to agree, the decision of an
Umpire appointed by them to be final. The Arbitrators and Umpire are
5. ID.; ID.; ID.; ID.; LIABILITY TO THIRD PERSONS FOR GOODS all to be commercial men and resident in London. This submission
SHIPPED ON BOARD A VESSEL. — Responsibility to third persons may be made a rule of the High Court of Justice in England by either
for goods shipped on board a vessel follows the vessel's possession party." 2
and employment; and if possession is transferred to the charterer by
virtue of a demise, the charterer, and not the owner, is liable as carrier
On or about May 22, 1988, the vessel M/V "Liliana Dimitrova" loaded
on the contract of affreightment made by himself or by the master with
on board at Yuzhny, USSR a shipment of 15,500 metric tons prilled
third persons, and is answerable for loss, damage or non-delivery of
Urea in bulk complete and in good order and condition for transport to
goods received for transportation. An owner who retains possession
Iloilo and Manila, to be delivered to petitioner. Three bills of lading
of the ship, though the hold is the property of the charterer, remains
were issued by the ship-agent in the Philippines, Maritime Factors
liable as carrier and must answer for any breach of duty as to the care,
Inc., namely: Bill of Lading No. dated May 12, 1988 covering 10,000
loading or unloading of the cargo.
metric tons for discharge Manila; Bill of Lading No. 2 of even date
covering 4,000 metric tons for unloading in Iloilo City; and Bill of
6. ID.; ID.; ID.; ID.; BILLS OF LADING; ARBITRATION PROVISION Lading No. 3, also dated May 12, 1988, covering 1,500 metric tons
THEREOF, CONSIDERED AND RESPECTED. — Whether the likewise for discharged in Manila
liability of respondent should be based on the same contract or that
of the bill of lading, the parties are nevertheless obligated to respect
The shipment covered by Bill of Lading No. 2 was discharged in Iloilo
the arbitration provisions on the sales contract and/or the bill of lading.
City complete and in good order and condition. However, the
Petitioner being a signatory and party to the sales contract cannot
shipments covered by Bill of Lading Nos. 1 and 3 were discharged in
escape from his obligation under the arbitration clause as stated
Manila in bad order and condition, caked, hardened and lumpy,
therein. Arbitration has been held valid and constitutional. Even before
discolored and contaminated with rust and dirt. Damages were valued
the enactment of Republic Act No. 876, this Court has countenanced
at P683, 056. 29 including additional discharging expenses.
the settlement of disputes through arbitration. The rule now is that
unless the agreement is such as absolutely to close the doors of the
courts against the parties, which agreement would be void, the courts Consequently, petitioner filed a complaint 3 with the trial court 4 for
will look with favor upon such amicable arrangements and will only breach of contract of carriage against Maritime Factors Inc. (which
interfere with great reluctance to anticipate or nullify the action of the was not included as respondent in this petition) as ship-agent in the
arbitrator. As pointed out in the case of Mindanao Portland Cement Philippines for the owners of the vessel MV "Liliana Dimitrova," while
Corp. v. McDough Construction Company of Florida 18 wherein the private respondent, Philipp Brothers Oceanic Inc., was impleaded as
plaintiff sued defendant for damages arising from a contract, the Court charterer of the said vessel and proper party to accord petitioner
said: "Since there obtains herein a written provision for arbitration as complete relief. Maritime Factors, Inc. filed its Answer 5 to the
well as failure on respondent's part to comply therewith, the court a complaint, while private respondent filed a motion to dismiss, dated
quo rightly ordered the parties to proceed to their arbitration in February 9, 1989, on the grounds that the complaint states no cause
of action; that it was prematurely filed; and that petitioner should for the respondent court to touch upon the arbitration provision of the
comply with the arbitration clause in the sales contract. 6 bills lading in its decision inasmuch as the same was not raised as an
issue by private respondent who was not a party in the bills of lading
(emphasis Ours). Petitioner contradicts itself.
The motion to dismiss was opposed by petitioner contending the
inapplicability of the arbitration clause inasmuch as the cause of
action did not arise from a violation of the terms of the sales contract We agree with the court a quo that the sales contract is
but rather for claims of cargo damages where there is no arbitration comprehensive enough to include claims for damages arising from
agreement. On April 26, 1989, the trial court denied respondent's carriage and delivery of the goods. As a general rule, the seller has
motion to dismiss in this wise: the obligation to transmit the goods to the buyer, and concomitant
thereto, the contracting of a carrier to deliver the same. Art. 1523 of
the Civil Code provides:
"The sales contract in question states in part:

"Art. 1523. Where in pursuance of a contract of sale, the seller in


'Any disputes arising under this contract shall be settled by arbitration
authorized or required to send the goods to the buyer, delivery of the
. . .(emphasis supplied)
goods to a carrier, whether named by the buyer or not, for the purpose
of transmission to the buyer is deemed to be a delivery of the goods
"A perusal of the facts alleged in the complaint upon which the to the buyer, except in the cases provided for in article 1503, first,
question of sufficiency of the cause of action of the complaint arose second and third paragraphs, or unless a contrary intent appear.
from a breach of contract of carriage by the vessel chartered by the
defendant Philipp Brothers Oceanic, Inc. Thus, the aforementioned
"Unless otherwise authorized by the buyer, the seller must take such
arbitration clause cannot apply to the dispute in the present action
contract with the carrier on behalf of the buyer as may be reasonable,
which concerns plaintiff's claim for cargo loss/damage arising from
having regard to the nature of the goods and the other circumstances
breach of contract of carriage.
of the case. If the seller omit so to do, and the goods are lost or
damaged in course of transit, the buyer may decline to treat the
"That the defendant is not the ship owner or common carrier and delivery to the carrier as a delivery to himself,, or may hold the seller
therefore plaintiff does not have legal right against it since every action responsible in damages."
must be brought against the real party in interest has no merit either
for by the allegations in the complaint the defendant herein has been
xxx xxx xxx
impleaded as charterer of the vessel, hence, a proper party." 7

The disputed sales contact provides for conditions relative to the


Elevating the matter to the Court of Appeals, petitioner's complaint
delivery of goods, such as date of shipment, demurrage, weight as
was dismissed. The appellate court found that the arbitration provision
determined by the bill of lading at load port and more particularly the
in the sales contract and/or the bills of lading is applicable in the
following provisions:
present case. Said the court:

"3. Intention is to ship in one bottom, approximately 5,000 metrics tons


"An examination of the sales contract No. S151.8.01018 shows that it
to Puromines and approximately 15,000 metric tons to Makati Agro.
is broad enough to include the claim for damages arising from the
However, Sellers to have right to ship material as partial shipment or
carriage and delivery of the goods subject-matter thereof.
co-shipment in addition to above. In the event of co-shipment to a third
party within Philippines same to be discussed with and acceptable to
"It is also noted that the bills of lading attached as Annexes 'A', 'B' and both Puromines and Makati Agro.
'C' to the complaint state, in part, 'any dispute arising under this Bill of
Lading shall be referred to arbitration of the Maritime Arbitration
"4. Sellers to appoint neutral survey for Seller's account to conduct
Commission at the USSR Chamber of Commerce and Industry, 6
initial draft survey at first discharge port and final survey at last
Kuibyshevskaia Str., Moscow, USSR, in accordance with the rules of
discharge port. Surveyors results to be binding and final. In the event
procedure of said commission.'
draft survey results show a quantity less than the combined Bills of
Lading quantity for both Puromines and Makati Agro, Sellers to refund
Considering that the private respondent was one of the signatories to the difference. In the event that draft survey results show a quantity in
the sales contract . . . all parties are obliged o respect the terms and excess of combined Bills of Lading of quantity of both Puromines and
conditions of the said sales contract, including the provision thereof Makati Agro then Buyers to refund the difference.
on 'arbitration.' "
"5. It is expressly and mutually agreed that neither Sellers nor vessel's
Hence, this petition The issue raised is: Whether the phrase "any Owners have any liability to separate cargo or to deliver cargo
dispute arising under this contract" in the arbitration clause of the separately or to deliver minimum/maximum quantities stated on
sales contract covers a cargo claim against the vessel (owner and/or individual Bills of Lading. At each port vessel is to discharge in
charterers) for breach of contract of carriage. accordance with Buyers local requirements and it is Buyer's
responsibility to separate individual quantities required by each of
them at each port during or after discharged."
Petitioner states in its complainants that Philipp Brothers "was the
charterer of the vessel MV 'Liliana Dimitrova' which transported the
shipment from Yuzhny USSR to Manila." Petitioner further alleged As argued by respondent on its motion to dismiss, "the (petitioner)
that the caking and hardening, wetting and melting, and contamination derives his right to the cargo from the bill of lading which is the contract
by rust and dirt of the damaged portions of the shipment were due to of affreightment together with the sales contract. Consequently, the
the improper ventilation and inadequate storage facilities of the (petitioner) is bound by the provisions and terms of said bill of lading
vessel; that the wetting of the cargo was attributable to the failure of and of the arbitration clause incorporated in the sales contract."
the crew to close the hatches before and when it rained while the
shipment was being unloaded in the Port of Manila; and that as a
Assuming arguendo that the liability of respondent is not based on the
direct and natural consequence of the unseaworthiness and
sales contract, but rather on the contract of carriage, being the
negligence of the vessel (sic), petitioner suffered damages in the total
charterer of the vessel MV "Liliana Dimitrova," it would, therefore, be
amount of P683, 056.29 Philippine currency." 8 (Emphasis supplied)
material to show what kind of charter party the respondent had with
the shipowner to determine respondent's liability.
Moreover, in its Opposition to the Motion to Dismiss, petitioner said
that "[t]he cause of action of the complaint arose from breach of
American jurisprudence defines charter party as a contract by which
contract of carriage by the vessel that was chartered by defendant
an entire ship or some principal part thereof is let by the owner to
Philipp Brothers." 9
another person for a specified time or use. 10 Charter or charter
parties are of two kinds. Charter of demise or bareboat and contracts
In the present petition, petitioner argues that the sales contract does of affreightment.
not include the contract of carriage which is a different contract
entered into by the carrier with the cargo owners. That it was an error
Under the demise or bareboat charter of the vessel, the charterer will that a frivolous or patently baseless claim should not be ordered to
generally be considered as owner for the voyage or service stipulated. arbitration it is also recognized that the mere fact that a defense exist
The charterer mans the vessel with his own people and becomes, in against a claim does not make it frivolous or baseless." 19
effect, the owner pro hac vice, subject to liability to others for damages
caused by negligence. 11 To create a demise the owner of a vessel
In the case of Bengson v. Chan, 20 We upheld the provision of a
must completely and exclusively relinquish possession, anything
contract which required the parties to submit their disputes to
short of such a complete transfer is a contract of affreightment (time
arbitration and We held as follows:
or voyage charter party) or not a charter party at all.

"The trial court sensibly said that 'all the causes of action alleged in
On the other hand, a contract of affreightment is in which the owner
the plaintiffs amended complaint are based upon the supposed
of the vessel leases part or all of its space to haul goods for others. It
violations committed by the defendants of the 'Contract of
is a contract for a special service to be rendered by the owner of the
Construction of a Building' and that 'the provisions of paragraph 15
vessel 12 and under such contract the general owner retains the
hereof leave a very little room for doubt that the said causes of action
possession, command and navigation of the ship, the charterer or
are embraced within the phrase 'any and all questions, disputes or
freighter merely having use of the space in the vessel in return for his
differences between the parties hereto relative to the construction of
payment of the charter hire. 13 If the charter is a contract of
the building,' which must be determined by arbitration of two persons
affreightment, which leaves the general owner in possession of the
and such determination by the arbitrators shall be 'final, conclusive
ship as owner for the voyage, the rights, responsibilities of ownership
and binding upon both parties unless they to court, in which the case
rest on the owner and the charterer is usually free from liability to third
the determination by arbitration is a condition precedent 'for taking any
persons in respect of the ship. 14
court action."

Responsibility to third persons for goods shipped on board a vessel


xxx xxx xxx
follows the vessel's possession and employment; and if possession is
transferred to the charterer by virtue of a demise, the charterer, and
not the owner, is liable as carrier on the contract of affreightment "We hold that the terms of paragraph 15 clearly express the intention
made by himself or by the master with third persons, and is of the parties that all disputes between them should first be arbitrated
answerable for loss, damage or non-delivery of goods received for before court action can be taken by the aggrieved party." 21
transportation. An owner who retains possession of the ship, though
the hold is the property of the charterer, remains liable as carrier and
must answer for any breach of duty as to the care, loading or Premises considered, We uphold the validity and applicability of the
unloading of the cargo. 15 arbitration clause as stated in Sales Contract No. S151.8.01018 to the
present dispute.

Assuming that in the present case, the charter party is a demise or


bareboat charter, then Philipp Brothers is liable to Puromines, Inc., WHEREFORE, petition is hereby DISMISSED and decision of the
subject to the terms and conditions of the sales contract. On the other court a quo is AFFIRMED.
hand, if the contract between respondent and the owner of the vessel
MV "Liliana Dimitrova" was merely that of affreightment, then it cannot SO ORDERED.
be held liable for the damages caused by the breach of contract of
carriage, the evidence of which is the bills of lading

In any case, whether the liability of respondent should be based on


the same contract or that of the bill of lading, the parties are
nevertheless obligated to respect the arbitration provisions on the
sales contract and/or the bill of lading. Petitioner being a signatory and
party to the sales contract cannot escape from his obligation under
the arbitration clause as stated therein.

Neither can petitioner contend that the arbitration provision in the bills
of lading should not have been discussed as an issue in the decision
of the Court of Appeals since it was not raised as a special or
affirmative defense. The three bills of lading were attached to the
complaint as Annexes "A," "B," and "C," and are therefore parts
thereof and may be considered as evidence although not introduced
as such. 16 Hence, it was then proper for the court a quo to discuss
the contents of the bills of lading, having been made part of the record.

Going back to the main subject of this case, arbitration has been held
valid and constitutional. Even before the enactment of Republic Act
No. 876, this Court has countenanced the settlement of disputes
through arbitration. The rule now is that unless the agreement is such
as absolutely to close the doors of the courts against the parties,
which agreement would be void, the courts will look with favor upon
such amicable arrangements and will only interfere with great
reluctance to anticipate or nullify the action of the arbitrator. 17

As pointed out in the case of Mindanao Portland Cement Corp. v.


McDonough Construction Company of Florida 18 wherein the plaintiff
sued defendant for damages arising from a contract, the Court said:

"Since there obtains herein a written provision for arbitration as well


as failure on respondent's part to comply therewith, the court a quo
rightly ordered the parties to proceed to their arbitration in accordance
with the terms of their agreement (Sec. 6 Republic Act 876).
Respondent's arguments touching upon the merits of the dispute are
improperly raised herein. They should be addressed to the arbitrators.
This proceeding is merely a summary remedy to enforce the
agreement to arbitrate. The duty of the court in this case is not to
resolve the merits of the parties' claims but only to determine if they
should proceed to arbitration or not. And although it has been ruled
G.R. No. 96283 February 25, 1992 consequential damage
and/or interest thereon;
CHUNG FU INDUSTRIES (PHILIPPINES) INC., its Directors and
Officers namely: HUANG KUO-CHANG, HUANG AN-CHUNG, e. The parties mutually
JAMES J.R. CHEN, TRISTAN A. CATINDIG, VICENTE B. agree that the decision of
AMADOR, ROCK A.C. HUANG, JEM S.C. HUANG, MARIA the arbitrator shall be final
TERESA SOLIVEN and VIRGILIO M. DEL ROSARIO, petitioners, and unappealable.
Therefore, there shall be no
further judicial recourse if
vs.
either party disagrees with
the whole or any part of the
COURT OF APPEALS, HON. FRANCISCO X. VELEZ (Presiding arbitrator's award.
Judge, Regional Trail Court of Makati [Branch 57]) and
ROBLECOR PHILIPPINES, INC., respondents.
f. As an exception to sub-
paragraph (e) above, the
ROMERO, J.: parties mutually agree that
either party is entitled to
seek judicial assistance for
This is a special civil action for certiorari seeking to annul the purposes of enforcing the
Resolutions of the Court of Appeals* dated October 22, 1990 and
arbitrator's award;
December 3, 1990 upholding the Orders of July 31, 1990 and August
23, 1990 of the Regional Trial Court of Makati, Branch 57, in Civil
Case No. 90-1335. Respondent Court of Appeals affirmed the ruling xxx xxx xxx 4
of the trial court that herein petitioners, after submitting themselves for
arbitration and agreeing to the terms and conditions thereof, providing
(Emphasis supplied)
that the arbitration award shall be final and unappealable, are
precluded from seeking judicial review of subject arbitration award.
Respondent Regional Trial Court approved the arbitration agreement
thru its Order of May 30, 1990. Thereafter, Engr. Willardo Asuncion
It appears that on May 17, 1989, petitioner Chung Fu Industries
was appointed as the sole arbitrator.
(Philippines) (Chung Fu for brevity) and private respondent Roblecor
Philippines, Inc. (Roblecor for short) forged a construction
agreement 1 whereby respondent contractor committed to construct On June 30, 1990, Arbitrator Asuncion ordered petitioners to
and finish on December 31, 1989, petitioner corporation's immediately pay respondent contractor, the sum of P16,108,801.00.
industrial/factory complex in Tanawan, Tanza, Cavite for and in He further declared the award as final and unappealable, pursuant to
consideration of P42,000,000.00. In the event of disputes arising from the Arbitration Agreement precluding judicial review of the award.
the performance of subject contract, it was stipulated therein that the
issue(s) shall be submitted for resolution before a single arbitrator
Consequently, Roblecor moved for the confirmation of said award. On
chosen by both parties.
the other hand, Chung Fu moved to remand the case for further
hearing and asked for a reconsideration of the judgment award
Apart from the aforesaid construction agreement, Chung Fu and claiming that Arbitrator Asuncion committed twelve (12) instances of
Roblecor entered into two (2) other ancillary contracts, to wit: one grave error by disregarding the provisions of the parties' contract.
dated June 23, 1989, for the construction of a dormitory and support
facilities with a contract price of P3,875,285.00, to be completed on or
Respondent lower court denied Chung Fu's Motion to Remand thus
before October 31, 1989; 2 and the other dated August 12, 1989, for
compelling it to seek reconsideration therefrom but to no avail. The
the installation of electrical, water and hydrant systems at the plant
trial court granted Roblecor's Motion for Confirmation of Award and
site, commanding a price of P12.1 million and requiring completion
accordingly, entered judgment in conformity therewith. Moreover, it
thereof one month after civil works have been finished. 3
granted the motion for the issuance of a writ of execution filed by
respondent.
However, respondent Roblecor failed to complete the work despite
the extension of time allowed it by Chung Fu. Subsequently, the latter
Chung Fu elevated the case via a petition for certiorari to respondent
had to take over the construction when it had become evident that
Court of Appeals. On October 22,1990 the assailed resolution was
Roblecor was not in a position to fulfill its obligation.
issued. The respondent appellate court concurred with the findings
and conclusions of respondent trial court resolving that Chung Fu and
Claiming an unsatisfied account of P10,500,000.00 and unpaid its officers, as signatories to the Arbitration Agreement are bound to
progress billings of P2,370,179.23, Roblecor on May 18, 1990, filed a observe the stipulations thereof providing for the finality of the award
petition for Compulsory Arbitration with prayer for Temporary and precluding any appeal therefrom.
Restraining Order before respondent Regional Trial Court, pursuant
to the arbitration clause in the construction agreement. Chung Fu
A motion for reconsideration of said resolution was filed by petitioner,
moved to dismiss the petition and further prayed for the quashing of
but it was similarly denied by respondent Court of Appeals thru its
the restraining order.
questioned resolution of December 3, 1990.

Subsequent negotiations between the parties eventually led to the


Hence, the instant petition anchored on the following grounds:
formulation of an arbitration agreement which, among others,
provides:
First
2. The parties mutually agree that the arbitration
shall proceed in accordance with the following Respondents Court of Appeals and trial Judge
terms and conditions: — gravely abused their discretion and/or exceeded
their jurisdiction, as well as denied due process
and substantial justice to petitioners, — (a) by
xxx xxx xxx
refusing to exercise their judicial authority and
legal duty to review the arbitration award, and (b)
d. The parties mutually by declaring that petitioners are estopped from
agree that they will abide by questioning the arbitration award allegedly in
the decision of the arbitrator view of the stipulations in the parties' arbitration
including any amount that agreement that "the decision of the arbitrator
may be awarded to either shall be final and unappealable" and that "there
party as compensation, shall be no further judicial recourse if either party
disagrees with the whole or any part of the crystallizing into definite and workable form. . . .
arbitrator's award." The rule now is that unless the agreement is such
as absolutely to close the doors of the courts
against the parties, which agreement would be
Second
void, the courts will look with favor upon such
amicable arrangements and will only with great
Respondent Court of Appeals and trial Judge reluctance interfere to anticipate or nullify the
gravely abused their discretion and/or exceeded action of the arbitrator. 10
their jurisdiction, as well as denied due process
and substantial justice to petitioner, by not
That there was a growing need for a law regulating arbitration in
vacating and annulling the award dated 30 June
general was acknowledged when Republic Act No. 876 (1953),
1990 of the Arbitrator, on the ground that the
otherwise known as the Arbitration Law, was passed. "Said Act was
Arbitrator grossly departed from the terms of the
obviously adopted to
parties' contracts and misapplied the law, and
supplement — not to supplant — the New Civil Code on arbitration. It
thereby exceeded the authority and power
expressly declares that "the provisions of chapters one and two, Title
delegated to him. (Rollo, p. 17)
XIV, Book IV of the Civil Code shall remain in force." 11

Allow us to take a leaf from history and briefly trace the evolution of
In recognition of the pressing need for an arbitral machinery for the
arbitration as a mode of dispute settlement.
early and expeditious settlement of disputes in the construction
industry, a Construction Industry Arbitration Commission (CIAC) was
Because conflict is inherent in human society, much effort has been created by Executive Order No. 1008, enacted on February 4, 1985.
expended by men and institutions in devising ways of resolving the
same. With the progress of civilization, physical combat has been
In practice nowadays, absent an agreement of the parties to resolve
ruled out and instead, more specific means have been evolved, such
their disputes via a particular mode, it is the regular courts that remain
as recourse to the good offices of a disinterested third party, whether
the fora to resolve such matters. However, the parties may opt for
this be a court or a private individual or individuals.
recourse to third parties, exercising their basic freedom to "establish
such stipulation, clauses, terms and conditions as they may deem
Legal history discloses that "the early judges called upon to solve convenient, provided they are not contrary to law, morals, good
private conflicts were primarily the arbiters, persons not specially customs, public order or public policy." 12 In such a case, resort to the
trained but in whose morality, probity and good sense the parties in arbitration process may be spelled out by them in a contract in
conflict reposed full trust. Thus, in Republican anticipation of disputes that may arise between them. Or this may be
Rome, arbiter and judge (judex) were synonymous. The magistrate stipulated in a submission agreement when they are actually
or praetor, after noting down the conflicting claims of litigants, and confronted by a dispute. Whatever be the case, such recourse to an
clarifying the issues, referred them for decision to a private person extrajudicial means of settlement is not intended to completely deprive
designated by the parties, by common agreement, or selected by the courts of jurisdiction. In fact, the early cases on arbitration carefully
them from an apposite listing (the album judicium) or else by having spelled out the prevailing doctrine at the time, thus: ". . . a clause in a
the arbiter chosen by lot. The judges proper, as specially trained state contract providing that all matters in dispute between the parties shall
officials endowed with own power and jurisdiction, and taking be referred to arbitrators and to them alone is contrary to public policy
cognizance of litigations from beginning to end, only appeared under and cannot oust the courts of Jurisdiction." 13
the Empire, by the so-called cognitio extra ordinem." 5
But certainly, the stipulation to refer all future disputes to an arbitrator
Such means of referring a dispute to a third party has also long been or to submit an ongoing dispute to one is valid. Being part of a contract
an accepted alternative to litigation at common law. 6 between the parties, it is binding and enforceable in court in case one
of them neglects, fails or refuses to arbitrate. Going a step further, in
the event that they declare their intention to refer their differences to
Sparse though the law and jurisprudence may be on the subject of
arbitration first before taking court action, this constitutes a condition
arbitration in the Philippines, it was nonetheless recognized in the precedent, such that where a suit has been instituted prematurely, the
Spanish Civil Code; specifically, the provisions on compromises made court shall suspend the same and the parties shall be directed
applicable to arbitrations under Articles 1820 and 1821.7 Although
forthwith to proceed to arbitration. 14
said provisions were repealed by implication with the repeal of the
Spanish Law of Civil Procedure, 8 these and additional ones were
reinstated in the present Civil Code. 9 A court action may likewise be proven where the arbitrator has not
been selected by the parties. 15
Arbitration found a fertile field in the resolution of labor-management
disputes in the Philippines. Although early on, Commonwealth Act 103 Under present law, may the parties who agree to submit their disputes
(1936) provided for compulsory arbitration as the state policy to be to arbitration further provide that the arbitrators' award shall be final,
administered by the Court of Industrial Relations, in time such a unappealable and executory?
modality gave way to voluntary arbitration. While not completely
supplanting compulsory arbitration which until today is practiced by
Article 2044 of the Civil Code recognizes the validity of such
government officials, the Industrial Peace Act which was passed in
stipulation, thus:
1953 as Republic Act No. 875, favored the policy of free collective
bargaining, in general, and resort to grievance procedure, in
particular, as the preferred mode of settling disputes in industry. It was Any stipulation that the arbitrators' award or
accepted and enunciated more explicitly in the Labor Code, which decision shall be final is valid, without prejudice
was passed on November 1, 1974 as Presidential Decree No. 442, to Articles 2038, 2039 and 2040.
with the amendments later introduced by Republic Act No. 6715
(1989).
Similarly, the Construction Industry Arbitration Law provides that the
arbitral award "shall be final and inappealable except on questions of
Whether utilized in business transactions or in employer-employee law which shall be appealable to the Supreme Court." 16
relations, arbitration was gaining wide acceptance. A consensual
process, it was preferred to orders imposed by government upon the
Under the original Labor Code, voluntary arbitration awards or
disputants. Moreover, court litigations tended to be time-consuming,
decisions were final, unappealable and executory. "However,
costly, and inflexible due to their scrupulous observance of the due
voluntary arbitration awards or decisions on money claims, involving
process of law doctrine and their strict adherence to rules of evidence.
an amount exceeding One Hundred Thousand Pesos (P100,000.00)
or forty-percent (40%) of the paid-up capital of the respondent
As early as the 1920's, this Court declared: employer, whichever is lower, maybe appealed to the National Labor
Relations Commission on any of the following grounds: (a) abuse of
discretion; and (b) gross incompetence." 17 It is to be noted that the
In the Philippines fortunately, the attitude of the
appeal in the instances cited were to be made to the National Labor
courts toward arbitration agreements is slowly
Relations Commission and not to the courts.
With the subsequent deletion of the above-cited provision from the 3. The Honorable Arbitrator committed grave
Labor Code, the voluntary arbitrator is now mandated to render an error in granting extra compensation to Roblecor
award or decision within twenty (20) calendar days from the date of for loss due to delayed payment of progress
submission of the dispute and such decision shall be final and billings;
executory after ten (10) calendar days from receipt of the copy of the
award or decision by the parties. 18
4. The Honorable Arbitrator committed grave
error in granting extra compensation to Roblecor
Where the parties agree that the decision of the arbitrator shall be final for loss of productivity due to the cement crisis;
and unappealable as in the instant case, the pivotal inquiry is whether
subject arbitration award is indeed beyond the ambit of the court's
5. The Honorable Arbitrator committed grave
power of judicial review.
error in granting extra compensation to Roblecor
for losses allegedly sustained on account of the
We rule in the negative. It is stated explicitly under Art. 2044 of the failed coup d'état;
Civil Code that the finality of the arbitrators' award is not absolute and
without exceptions. Where the conditions described in Articles 2038,
6. The Honorable Arbitrator committed grave
2039 and 2040 applicable to both compromises and arbitrations are
error in granting to Roblecor the amount
obtaining, the arbitrators' award may be annulled or
representing the alleged unpaid billings of Chung
rescinded. 19 Additionally, under Sections 24 and 25 of the Arbitration
Fu;
Law, there are grounds for vacating, modifying or rescinding an
arbitrator's award. 20 Thus, if and when the factual circumstances
referred to in the above-cited provisions are present, judicial review of 7. The Honorable Arbitrator committed grave
the award is properly warranted. error in granting to Roblecor the amount
representing the alleged extended overhead
expenses;
What if courts refuse or neglect to inquire into the factual milieu of an
arbitrator's award to determine whether it is in accordance with law or
within the scope of his authority? How may the power of judicial review 8. The Honorable Arbitrator committed grave
be invoked? error in granting to Roblecor the amount
representing expenses for change order for site
development outside the area of responsibility of
This is where the proper remedy is certiorari under Rule 65 of the
Roblecor;
Revised Rules of Court. It is to be borne in mind, however, that this
action will lie only where a grave abuse of discretion or an act without
or in excess of jurisdiction on the part of the voluntary arbitrator is 9. The Honorable Arbitrator committed grave
clearly shown. For "the writ of certiorari is an extra-ordinary remedy error in granting to Roblecor the cost of
and that certiorari jurisdiction is not to be equated with appellate warehouse No. 2;
jurisdiction. In a special civil action of certiorari, the Court will not
engage in a review of the facts found nor even of the law as
10. The Honorable Arbitrator committed grave
interpreted or applied by the arbitrator unless the supposed errors of
fact or of law are so patent and gross and prejudicial as to amount to error in granting to Roblecor extra compensation
a grave abuse of discretion or an exces de pouvoir on the part of the for airduct change in dimension;
arbitrator." 21
11. The Honorable Arbitrator committed grave
Even decisions of administrative agencies which are declared "final" error in granting to Roblecor extra compensation
for airduct plastering; and
by law are not exempt from judicial review when so warranted. Thus,
in the case of Oceanic Bic Division (FFW), et al. v. Flerida Ruth P.
Romero, et al., 22 this Court had occasion to rule that: 12. The Honorable Arbitrator committed grave
error in awarding to Roblecor attorney's fees.
. . . Inspite of statutory provisions making "final"
the decisions of certain administrative After closely studying the list of errors, as well as petitioners'
agencies, we have taken cognizance of petitions discussion of the same in their Motion to Remand Case For Further
questioning these decisions where want of Hearing and Reconsideration and Opposition to Motion for
jurisdiction, grave abuse of discretion, violation of Confirmation of Award, we find that petitioners have amply made out
due process, denial of substantial justice or a case where the voluntary arbitrator failed to apply the terms and
erroneous interpretation of the law were brought provisions of the Construction Agreement which forms part of the law
to our attention . . . 23 (Emphasis ours). applicable as between the parties, thus committing a grave abuse of
discretion. Furthermore, in granting unjustified extra compensation to
It should be stressed, too, that voluntary arbitrators, by the nature of respondent for several items, he exceeded his powers — all of which
their functions, act in a quasi-judicial capacity. 24 It stands to reason, would have constituted ground for vacating the award under Section
24 (d) of the Arbitration Law.
therefore, that their decisions should not be beyond the scope of the
power of judicial review of this Court.
But the respondent trial court's refusal to look into the merits of the
case, despite prima facie showing of the existence of grounds
In the case at bar, petitioners assailed the arbitral award on the
following grounds, most of which allege error on the part of the warranting judicial review, effectively deprived petitioners of their
arbitrator in granting compensation for various items which apparently opportunity to prove or substantiate their allegations. In so doing, the
trial court itself committed grave abuse of discretion. Likewise, the
are disputed by said petitioners:
appellate court, in not giving due course to the petition, committed
grave abuse of discretion. Respondent courts should not shirk from
1. The Honorable Arbitrator committed grave exercising their power to review, where under the applicable laws and
error in failing to apply the terms and conditions jurisprudence, such power may be rightfully exercised; more so where
of the Construction Agreement, Dormitory the objections raised against an arbitration award may properly
Contract and Electrical Contract, and in using constitute grounds for annulling, vacating or modifying said award
instead the "practices" in the construction under the laws on arbitration WHEREFORE, the petition is
industry; GRANTED. The Resolutions of the Court of Appeals dated October
22, 1990 and December 3, 1990 as well as the Orders of respondent
Regional Trial Court dated July 31, 1990 and August 23, 1990,
2. The Honorable Arbitrator committed grave
including the writ of execution issued pursuant thereto, are hereby
error in granting extra compensation to Roblecor
SET ASIDE. Accordingly, this case is REMANDED to the court of
for loss of productivity due to adverse weather
origin for further hearing on this matter. All incidents arising therefrom
conditions;
are reverted to the status quo ante until such time as the trial court
shall have passed upon the merits of this case. No costs.
G.R. No. 139273 November 28, 2000 Set for Preliminary Hearing. On February 2, 1994 petitioners filed a
Motion for Reconsideration of the Order dated December 28, 1993.
On February 11, 1994, [the RTC] issued an Order denying petitioners’
CALIFORNIA AND HAWAIIAN SUGAR COMPANY; PACIFIC
Motion for Reconsideration. Hence, the instant petition."5
GULF MARINE, INC.; and C.F. SHARP & COMPANY, petitioners,
vs.
PIONEER INSURANCE AND SURETY Ruling of the Court of Appeals
CORPORATION, respondent.
Affirming the trial court, the CA held that petitioners cannot rely on
DECISION Section 5, Rule 166 of the pre-1997 Rules of Court,7 because a Motion
to Dismiss had previously been filed. Further, it ruled that the
arbitration clause provided in the charter party did not bind
PANGANIBAN, J.:
respondent. It reasoned as follows:

Under the pre-1997 Rules of Court, a preliminary hearing on


"Petitioners argue that [the RTC] committed grave abuse of discretion
affirmative defenses may be allowed when a motion to dismiss has
amounting to lack or excess of jurisdiction in denying the preliminary
not been filed or when, having been filed, it has not been denied
hearing of the affirmative defense of lack of cause of action for failure
unconditionally. Hence, if its resolution has merely been deferred, the
to comply with the arbitration clause.
grounds it invokes may still be raised as affirmative defenses, and a
preliminary hearing thereon allowed.
"Petitioners, in so filing the Motion to Set for Preliminary Hearing the
Affirmative Defense of Lack of Cause of Action for Failure to Comply
The Case
with Arbitration Clause, premised their alleged right to a preliminary
hearing on the provision of Section 5, Rule 16 of the Old Rules of
Before us is a Petition for Review on Certiorari under Rule 45 of the Court which provide[s]:
Rules of Court, assailing the January 21, 1999 Decision of the Court
of Appeals1 (CA) in CA-GR SP No. 33723, as well as the July 6, 1999
‘Sec. 5. Pleading grounds as affirmative defenses. Any of the grounds
CA Resolution2 denying reconsideration. The challenged Decision,
for dismissal provided for in this rule, except improper venue, may be
which sustained the Orders3 of the Regional Trial Court of Makati City,
pleaded as an affirmative defense and a preliminary hearing may be
disposed as follows:
had thereon as if a motion to dismiss had been filed.’

"WHEREFORE, [there being] no grave abuse of discretion on the part


"Petitioners’ reliance on said provision is misplaced. The above-
of public respondent, the instant petition is
mentioned provision contemplates a situation where no motion to
hereby DISMISSED."4 (emphasis in the original)
dismiss is filed. If a motion to dismiss has been filed, as in the case at
bar, Section 5, Rule 16 of the Old Rules of Court will not come into
The Facts play. Furthermore, the same provision gives the judge discretion
whether to set for preliminary hearing the grounds for affirmative
defenses. Respondent judge deferred the hearing and determination
The facts, as summarized by the CA, are as follows: of the Motion to Dismiss until the trial since the ground relied upon by
petitioners therein did not appear to be indubitable. Petitioners then
"On November 27, 1990, the vessel MV "SUGAR ISLANDER" arrived filed their Answer as ordered by the Court again raising as an
at the port of Manila carrying a cargo of soybean meal in bulk affirmative defense lack of cause of action for failure to comply with
consigned to several consignees, one of which was the Metro Manila [the] arbitration clause, praying for the dismissal of the complaint
Feed Millers Association (Metro for [b]revity). Discharging of cargo against them, and filing afterwards a Motion to Set for Preliminary
from vessel to barges commenced on November 30, 1990. From the Hearing the Affirmative Defense of lack of Cause of Action. In effect,
barges, the cargo was allegedly offloaded, rebagged and reloaded on petitioners are asking the trial court to set aside its Order denying the
consignee’s delivery trucks. Respondent, however, claims that when Motion to Dismiss and Order denying the Motion for Reconsideration
the cargo [was] weighed on a licensed truck scale a shortage of thereof.
255.051 metric tons valued at P1,621,171.16 was discovered. The
above-mentioned shipment was insured with private respondent "Petitioners cannot do this.
against all risk in the amount of P19,976,404.00. Due to the alleged
refusal of petitioners to settle their respective liabilities, respondent,
as insurer, paid the consignee Metro Manila Feed Miller’s Association. "The remedy of the aggrieved party in a denied motion to dismiss is
On March 26, 1992, as alleged subrogee of Metro, private respondent to file an answer and interpose as defense or defenses, the objection
filed a complaint for damages against herein petitioners. Within the or objections raised by him in said motion to dismiss, then proceed to
reglementary period to file an Answer, petitioners filed a Motion to trial and, in case of adverse decision, to elevate the entire case by
Dismiss the complaint on the ground that respondent’s claim is appeal in due course. Petitioners could also resort to the extraordinary
premature, the same being arbitrable. Private respondent filed its legal remedies of certiorari, prohibition and mandamus to question the
Opposition thereto and petitioners filed their Reply to Opposition. denial of the motion to dismiss. As correctly ruled by the trial court in
its Order dated June 30, 1993, denying the Motion for
Reconsideration of the Order dated November 11, 1992 (denying the
"On November 11, 1992, [the RTC] issued an Order deferring the Motion to Dismiss) the ground relied upon by petitioners is a matter of
hearing on the Motion to Dismiss until the trial and directing petitioners defense which petitioners must prove with their evidence at the trial.
to file their Answer. Petitioners then moved to reconsider said Order
which was, however, denied by [the RTC] on the ground that the
reason relied upon by herein petitioners in its Motion to Dismiss and "Petitioners in asking the lower court to set the case for preliminary
Motion for Reconsideration [was] a matter of defense which they must hearing further argue that this would give the court and the parties a
prove with their evidence. shorter time to resolve the matter and the case without a full blown
trial. However, petitioners fail to realize that they themselves are
delaying the determination and resolution of the issues involved by
"On August 20, 1993, petitioners filed their Answer with Counterclaim
resorting to an improper remedy.
and Crossclaim alleging therein that plaintiff, herein respondent, did
not comply with the arbitration clause of the charter party; hence, the
complaint was allegedly prematurely filed. The trial court set the case "On the issue raised by petitioners that private respondent’s claim is
for pre-trial on November 26, 1993. premature for failure to comply with [the] arbitration clause, we hold
that the right of the respondent as subrogee, in filing the complaint
against herein petitions is not dependent upon the charter party relied
"On November 15 and 16, 1993, petitioners filed a Motion to Defer
upon by petitioners; nor does it grow out of any privity contract or upon
Pre-Trial and Motion to Set for Preliminary Hearing the Affirmative written assignment of claim. It accrues simply upon payment of the
Defense of Lack of Cause of Action for Failure to comply with insurance claim by respondent as insurer to the insured. This was the
Arbitration Clause, respectively. Private respondent did not file an
pronouncement by the Supreme Court in the case of Pan Malayan
Opposition to the said Motion to Set for Preliminary Hearing. On Insurance Corp. vs. Court of Appeals 184 SCRA 54, to wit:
December 28, 1993, [the RTC] issued an Order denying the Motion to
‘Payment by the insurer to the insured operates as an equitable of affirmative defenses once a motion to dismiss has been filed
assignment to the former of all the remedies which the latter may have because such defense should have already been resolved. In the
against the third party whose negligence or wrongful (sic) caused the present case, however, the trial court did not categorically resolve
loss. The right of subrogation is not dependent upon, nor does it grow petitioners’ Motion to Dismiss, but merely deferred resolution
out of, any privity contract or upon written assignment of claim. It thereof.13
accrues simply upon payment of the insurance claim by the insurer.’"8
Indeed, the present Rules are consistent with Section 5, Rule 16 of
Hence, this recourse.9 the pre-1997 Rules of Court, because both presuppose that no motion
to dismiss had been filed; or in the case of the pre-1997 Rules, if one
has been filed, it has not been unconditionally denied.14 Hence, the
The Issues
ground invoked may still be pleaded as an affirmative defense even if
the defendant’s Motion to Dismiss has been filed but not definitely
In their Memorandum, petitioners submit the following issues for our resolved, or if it has been deferred as it could be under the pre-1997
consideration:10 Rules.15

"1. Whether or not insurer, as subrogee of the consignee, Denial of the Motion for a Preliminary Hearing Was a Grave Abuse of
is bound by the charter party which is incorporated and Discretion
referred to in the bill of lading.
The more crucial question that we must settle here is whether the trial
2. Whether or not the motion to dismiss should be granted court committed grave abuse of discretion when it denied petitioners’
on the ground that a condition precedent has not been Motion for a Preliminary Hearing on their affirmative defense of lack
complied with, based on the arbitration clause incorporated of cause of action. Undeniably, a preliminary hearing is not
in the bill of lading. mandatory, but subject to the discretion of the trial court.16 In the light
of the circumstances in this case, though, we find that the lower court
committed grave abuse of discretion in refusing to grant the Motion.
3. Whether or not the Court of Appeals erred in holding that
the trial court did not commit grave abuse of discretion in
denying petitioners’ motion for preliminary hearing. We note that the trial court deferred the resolution of petitioners’
Motion to Dismiss because of a single issue. It was apparently unsure
whether the charter party that the bill of lading referred to was indeed
4. Whether or not the trial court can defer the resolution of the Baltimore Berth Grain Charter Party submitted by
a motion to dismiss on the ground that the ground relied petitioners.1âwphi1
upon is indubitable.

Considering that there was only one question, which may even be
5. Whether or not the petitioners have resorted to an deemed to be the very touchstone of the whole case, the trial court
improper remedy which makes them responsible for had no cogent reason to deny the Motion for Preliminary Hearing.
delaying the case." Indeed, it committed grave abuse of discretion when it denied a
preliminary hearing on a simple issue of fact that could have possibly
In the main, the two principal matters before us are: (1) the denial of settled the entire case. Verily, where a preliminary hearing appears to
petitioners’ Motion for Preliminary Hearing and (2) the propriety of the suffice, there is no reason to go on to trial. One reason why dockets
CA ruling regarding the arbitration clause. of trial courts are clogged is the unreasonable refusal to use a process
or procedure, like a motion to dismiss, which is designed to abbreviate
the resolution of a case.
The Court’s Ruling

Second Issue: The Arbitration Clause


The Petition is meritorious.

The CA also erred when it held that the arbitration clause was not
First Issue: Preliminary Hearing of Affirmative Defense binding on respondent. We reiterate that the crux of this case is
whether the trial court committed grave abuse of discretion in denying
At the outset, we must emphasize that the crux of the present the aforecited Motion. There was neither need nor reason to rule on
controversy is the trial court’s Order denying petitioner’s Motion to Set the applicability of the arbitration clause.
for Preliminary Hearing the affirmative defense of lack of cause of
action. Not questioned here is the said court’s Order holding in Be that as it may, we find the CA’s reasoning on this point faulty.
abeyance the hearing of petitioner’s Motion to Dismiss. Citing Pan Malayan Insurance Corporation v. CA,17 it ruled that the
right of respondent insurance company as subrogee was not based
Affirmative Defense May Be Raised on the charter party or any other contract; rather, it accrued upon the
payment of the insurance claim by private respondent to the insured
consignee. There was nothing in Pan Malayan, however, that
Still in effect when the case was before the trial court, Section 5, Rule prohibited the applicability of the arbitration clause to the subrogee.
16 of the pre-1997 Rules of Court, reads: That case merely discussed, inter alia, the accrual of the right of
subrogation and the legal basis therefor.18 This issue is completely
"Sec. 5. Pleading grounds as affirmative defenses. - Any of the different from that of the consequences of such subrogation; that is,
grounds for dismissal provided for in this Rule, except improper the rights that the insurer acquires from the insured upon payment of
venue, may be pleaded as an affirmative defense, and a preliminary the indemnity.
hearing may be had thereon as if a motion to dismiss had been filed."
WHEREFORE, the Petition is GRANTED and the appealed Decision
Respondent argues that the above provision cannot be applied, is hereby REVERSED. The case is REMANDED to the trial court for
because petitioners have already filed a Motion to Dismiss. preliminary hearing on petitioners’ affirmative defense. No costs.

We disagree. Respondent relies on the amendments introduced in the SO ORDERED.


1997 Rules on Civil Procedure ("1997 Rules"), but ignores equally
relevant provisions thereof, as well as the clear intendment of the pre-
1997 Rules. True, Section 6, Rule 16 of the 1997 Rules,11 specifically
provides that a preliminary hearing on the affirmative defenses may
be allowed only when no motion to dismiss has been filed. Section 6,
however, must be viewed in the light of Section 3 of the same
Rule,12 which requires courts to resolve a motion to dismiss and
prohibits them from deferring its resolution on the ground of
indubitability. Clearly then, Section 6 disallows a preliminary hearing

You might also like