Professional Documents
Culture Documents
G.R. No. 198075 September 4, 2013 Two (2) days before the lease incorporated in the Deed of Donation
and Amended Deed of Donation was set to expire, or on 23 May 2000,
FKI and respondent executed another contract of lease ( 2000 Lease
KOPPEL, INC. (formerly known as KPL AIRCON, INC.), Petitioner,
Contract )15 covering the subject land. In this 2000 Lease Contract,
vs.
FKI and respondent agreed on a new five-year lease to take effect on
MAKATI ROTARY CLUB FOUNDATION, INC., Respondent.
the 26th of May 2000, with annual rents ranging from ₱4,000,000 for
the first year up to ₱4,900,000 for the fifth year. 16 The 2000 Lease
DECISION Contract also contained an arbitration clause enforceable in the event
the parties come to disagreement about the" interpretation,
application and execution" of the lease, viz :
PEREZ, J.:
19. Governing Law – The provisions of this 2000 Lease Contract shall
This case is an appeal1 from the Decision2 dated 19 August 2011 of be governed, interpreted and construed in all aspects in accordance
the Court of Appeals in C.A.-G.R. SP No. 116865. with the laws of the Republic of the Philippines.
Verily, by virtue of the lease agreement contained in the Deed of Petitioner points out that while a definite amount of rent for the second
Donation and Amended Deed of Donation , FKI was able to continue twenty-five (25) year lease was not fixed in the Deed of Donation and
in its possession and use of the subject land.
Amended Deed of Donation , both deeds nevertheless prescribed premises and, therefore, the refusal to comply there with
rules and limitations by which the same may be determined. Such does not give rise to an action for unlawful detainer.47
rules and limitations ought to be observed in any succeeding lease
agreements between petitioner and respondent for they are, in
2. Assuming that the MeTC was able to acquire jurisdiction,
themselves, material conditions of the donation of the subject land. 28
it may not exercise the same until the disagreement
between the parties is first referred to arbitration pursuant
In this connection, petitioner cites item 2(g) of the Deed of Donation to the arbitration clause of the 2005 Lease Contract.48
and Amended Deed of Donation that supposedly limits the amount of
rent for the lease over the second twenty-five (25) years to only " three
3. Assuming further that the MeTC has jurisdiction that it
percent (3%) of the fair market value of the subject land excluding the
can exercise, ejectment still would not lie as the 2005 Lease
improvements.29
Contract is void abinitio.49 The stipulation in the 2005 Lease
Contract requiring petitioner to give yearly " donations " to
For petitioner then, the rental stipulations of both the 2000 Lease respondent is a simulation, for they are, in fact, parts of the
Contract and 2005 Lease Contract cannot be enforced as they are rent. 50 Such grants were only denominated as " donations
clearly, in view of their exorbitant exactions, in violation of the " in the contract so that the respondent—anon-stock and
aforementioned threshold in item 2(g) of the Deed of Donation and non-profit corporation—could evade payment of the taxes
Amended Deed of Donation . Consequently, petitioner insists that the otherwise due thereon.51
amount of rent it has to pay thereon is and must still be governed by
the limitations prescribed in the Deed of Donation and Amended Deed
In due course, petitioner and respondent both submitted their position
of Donation.30
papers, together with their other documentary
evidence.52 Remarkably, however, respondent failed to submit the
The Demand Letters Second Demand Letter as part of its documentary evidence.
On 1 June 2009, respondent sent a letter (First Demand Letter)31 to Rulings of the MeTC, RTC and Court of Appeals
petitioner notifying the latter of its default " per Section 12 of the 2005
Lease Contract " and demanding for the settlement of the rent and "
On 27 April 2010, the MeTC rendered judgment53 in favor of the
donation " due for the year 2009. Respondent, in the same letter,
petitioner. While the MeTC refused to dismiss the action on the
further intimated of canceling the 2005 Lease Contract should
ground that the dispute is subject to arbitration, it nonetheless sided
petitioner fail to settle the said obligations. 32 Petitioner received the
with the petitioner with respect to the issues regarding the
First Demand Letter on2 June 2009.33
insufficiency of the respondent’s demand and the nullity of the 2005
Lease Contract.54 The MeTC thus disposed:
On 22 September 2009, petitioner sent a reply34 to respondent
expressing its disagreement over the rental stipulations of the 2005
WHEREFORE, judgment is hereby rendered dismissing the case x x
Lease Contract — calling them " severely disproportionate,"
x, without pronouncement as to costs.
"unconscionable" and "in clear violation to the nominal rentals
mandated by the Amended Deed of Donation." In lieu of the amount
demanded by the respondent, which purportedly totaled to SO ORDERED.55
₱8,394,000.00, exclusive of interests, petitioner offered to pay only
₱80,502.79,35 in accordance with the rental provisions of the Deed of
The respondent appealed to the Regional Trial Court (RTC). This
Donation and Amended Deed of Donation.36 Respondent refused this
offer.37 appeal was assigned to Branch 274 of the RTC of Parañaque City
and was docketed as Civil Case No. 10-0255.
Petitioner refused to comply with the demands of the respondent. (1) to vacate the lease[d] premises made subject of the
Instead, on 30 September 2009, petitioner filed with the Regional Trial case and to restore the possession thereof to the plaintiff-
Court (RTC) of Parañaque City a complaint42 for the rescission or appellant;
cancellation of the Deed of Donation and Amended Deed of Donation
against the respondent. This case is currently pending before Branch
257 of the RTC, docketed as Civil Case No. CV 09-0346. (2) to pay to the plaintiff-appellant the amount of Nine
Million Three Hundred Sixty Two Thousand Four Hundred
Thirty Six Pesos (₱9,362,436.00), penalties and net of 5%
The Ejectment Suit withholding tax, for the lease period from May 25, 2009 to
May 25, 2010 and such monthly rental as will accrue during
On 5 October 2009, respondent filed an unlawful detainer the pendency of this case;
case43 against the petitioner before the Metropolitan Trial Court
(MeTC) of Parañaque City. The ejectment case was raffled to Branch (3) to pay attorney’s fees in the sum of ₱100,000.00 plus
77 and was docketed as Civil Case No. 2009-307. appearance fee of ₱3,000.00;
On 4 November 2009, petitioner filed an Answer with Compulsory (4) and costs of suit.
Counterclaim.44 In it, petitioner reiterated its objection over the rental
stipulations of the 2005 Lease Contract for being violative of the
material conditions of the Deed of Donation and Amended Deed of As to the existing improvements belonging to the defendant-appellee,
Donation.45 In addition to the foregoing, however, petitioner also as these were built in good faith, the provisions of Art. 1678of the Civil
interposed the following defenses: Code shall apply.
Aggrieved, the petitioner appealed to the Court of Appeals. Curiously, despite the lucidity of the arbitration clause of the 2005
Lease Contract, the petitioner, as well as the MeTC, RTC and the
Court of Appeals, vouched for the non-application of the same in the
On 19 August 2011, the Court of Appeals affirmed66 the decision of
instant case. A plethora of arguments was hurled in favor of bypassing
the RTC:
arbitration. We now address them.
xxxx
1. The disagreement between the petitioner and
respondent is non-arbitrable as it will inevitably touch upon
SO ORDERED.67 the issue of the validity of the 2005 Lease Contract.71 It was
submitted that one of the reasons offered by the petitioner
in justifying its failure to pay under the 2005 Lease Contract
Hence, this appeal.
was the nullity of such contract for being contrary to law and
public policy.72 The Supreme Court, in Gonzales v. Climax
On 5 September 2011, this Court granted petitioner’s prayer for the Mining, Ltd.,73 held that " the validity of contract cannot be
issuance of a Temporary Restraining Order68 staying the immediate subject of arbitration proceedings " as such questions are "
implementation of the decisions adverse to it. legal in nature and require the application and interpretation
of laws and jurisprudence which is necessarily a judicial
function ." 74
OUR RULING
Second. Petitioner may still invoke the arbitration clause of the 2005
In Gonzales, a complaint for arbitration was filed before the Panel of
Lease Contract notwithstanding the fact that it assails the validity of
Arbitrators of the Mines and Geosciences Bureau (PA-MGB) seeking
such contract. This is due to the doctrine of separability. 91
the nullification of a Financial Technical Assistance Agreement and
other mining related agreements entered into by private parties.82
Under the doctrine of separability, an arbitration agreement is
considered as independent of the main contract.92 Being a separate
Grounds invoked for the nullification of such agreements include fraud
contract in itself, the arbitration agreement may thus be invoked
and unconstitutionality.83 The pivotal issue that confronted the Court
regardless of the possible nullity or invalidity of the main contract.93
then was whether the PA-MGB has jurisdiction over that particular
arbitration complaint. Stated otherwise, the question was whether the
complaint for arbitration raises arbitrable issues that the PA-MGB can Once again instructive is Cargill, wherein this Court held that, as a
take cognizance of. further consequence of the doctrine of separability, even the very
party who repudiates the main contract may invoke its arbitration
clause.94
Gonzales decided the issue in the negative. In holding that the PA-
MGB was devoid of any jurisdiction to take cognizance of the
complaint for arbitration, this Court pointed out to the provisions of Third . The operation of the arbitration clause in this case is not at all
R.A. No. 7942, or the Mining Act of 1995, which granted the PA-MGB defeated by the failure of the petitioner to file a formal "request" or
with exclusive original jurisdiction only over mining disputes, i.e., application therefor with the MeTC. We find that the filing of a
disputes involving " rights to mining areas," "mineral agreements or "request" pursuant to Section 24 of R.A. No. 9285 is not the sole
permits," and " surface owners, occupants, claim holders or means by which an arbitration clause may be validly invoked in a
concessionaires" requiring the technical knowledge and experience pending suit.
of mining authorities in order to be resolved. 84 Accordingly, since the
complaint for arbitration in Gonzales did not raise mining disputes as
contemplated under R.A. No. 7942 but only issues relating to the Section 24 of R.A. No. 9285 reads:
validity of certain mining related agreements, this Court held that such
complaint could not be arbitrated before the PA-MGB.85 It is in this SEC. 24. Referral to Arbitration . - A court before which an action is
context that we made the pronouncement now in discussion: brought in a matter which is the subject matter of an arbitration
agreement shall, if at least one party so requests not later that the pre-
trial conference, or upon the request of both parties thereafter, refer
Arbitration before the Panel of Arbitrators is proper only when there is
a disagreement between the parties as to some provisions of the the parties to arbitration unless it finds that the arbitration agreement
contract between them, which needs the interpretation and the is null and void, inoperative or incapable of being performed.
[Emphasis ours; italics original]
application of that particular knowledge and expertise possessed by
members of that Panel. It is not proper when one of the parties
repudiates the existence or validity of such contract or agreement on The " request " referred to in the above provision is, in turn,
the ground of fraud or oppression as in this case. The validity of the implemented by Rules 4.1 to 4.3 of A.M. No. 07-11-08-SC or the
contract cannot be subject of arbitration proceedings. Allegations of Special Rules of Court on Alternative Dispute Resolution (Special
fraud and duress in the execution of a contract are matters within the ADR Rules):
jurisdiction of the ordinary courts of law. These questions are legal in
nature and require the application and interpretation of laws and
jurisprudence which is necessarily a judicial function. 86 (Emphasis RULE 4: REFERRAL TO ADR
supplied)
Rule 4.1. Who makes the request. - A party to a pending action filed
The Court in Gonzales did not simply base its rejection of the in violation of the arbitration agreement, whether contained in an
complaint for arbitration on the ground that the issue raised therein, arbitration clause or in a submission agreement, may request the
i.e. , the validity of contracts, is per se non-arbitrable. The real court to refer the parties to arbitration in accordance with such
consideration behind the ruling was the limitation that was placed by agreement.
R.A. No. 7942 upon the jurisdiction of the PA-MGB as an arbitral body
. Gonzales rejected the complaint for arbitration because the issue Rule 4.2. When to make request. - (A) Where the arbitration
raised therein is not a mining dispute per R.A. No. 7942 and it is for agreement exists before the action is filed . - The request for referral
this reason, and only for this reason, that such issue is rendered non- shall be made not later than the pre-trial conference. After the pre-trial
arbitrable before the PA-MGB. As stated beforehand, R.A. No. 7942 conference, the court will only act upon the request for referral if it is
clearly limited the jurisdiction of the PA-MGB only to mining made with the agreement of all parties to the case.
disputes.87
(B) Submission agreement . - If there is no existing arbitration
Much more instructive for our purposes, on the other hand, is the agreement at the time the case is filed but the parties subsequently
recent case of Cargill Philippines, Inc. v. San Fernando Regal enter into an arbitration agreement, they may request the court to refer
Trading, Inc.88 In Cargill , this Court answered the question of whether their dispute to arbitration at any time during the proceedings.
issues involving the rescission of a contract are arbitrable. The
respondent in Cargill argued against arbitrability, also citing therein
Gonzales . After dissecting Gonzales , this Court ruled in favor of Rule 4.3. Contents of request. - The request for referral shall be in the
arbitrability.89 Thus, We held: form of a motion, which shall state that the dispute is covered by an
arbitration agreement.
In using the word " may " to qualify the act of filing a " request " under
R.A. No. 9285
Section 24 of R.A. No. 9285, the Special ADR Rules clearly did not
intend to limit the invocation of an arbitration agreement in a pending
suit solely via such "request." After all, non-compliance with an Section 24. Referral to Arbitration. - A court before which an action is
arbitration agreement is a valid defense to any offending suit and, as brought in a matter which is the subject matter of an arbitration
such, may even be raised in an answer as provided in our ordinary agreement shall, if at least one party so requests not later that the pre-
rules of procedure.95 trial conference, or upon the request of both parties thereafter, refer
the parties to arbitration unless it finds that the arbitration agreement
is null and void, in operative or incapable of being performed.
In this case, it is conceded that petitioner was not able to file a
[Emphasis supplied]
separate " request " of arbitration before the MeTC. However, it is
equally conceded that the petitioner, as early as in its Answer with
Counterclaim ,had already apprised the MeTC of the existence of the It is clear that under the law, the instant unlawful detainer action
arbitration clause in the 2005 Lease Contract96 and, more should have been stayed;101 the petitioner and the respondent should
significantly, of its desire to have the same enforced in this have been referred to arbitration pursuant to the arbitration clause of
case.97 This act of petitioner is enough valid invocation of his right to the 2005 Lease Contract . The MeTC, however, did not do so in
arbitrate. Fourth . The fact that the petitioner and respondent already violation of the law—which violation was, in turn, affirmed by the RTC
under went through JDR proceedings before the RTC, will not make and Court of Appeals on appeal.
the subsequent conduct of arbitration between the parties
unnecessary or circuitous. The JDR system is substantially different
The violation by the MeTC of the clear directives under R.A. Nos.876
from arbitration proceedings.
and 9285 renders invalid all proceedings it undertook in the ejectment
case after the filing by petitioner of its Answer with Counterclaim —
The JDR framework is based on the processes of mediation, the point when the petitioner and the respondent should have been
conciliation or early neutral evaluation which entails the submission of referred to arbitration. This case must, therefore, be remanded to the
a dispute before a " JDR judge " who shall merely " facilitate MeTC and be suspended at said point. Inevitably, the decisions of the
settlement " between the parties in conflict or make a " non-binding MeTC, RTC and the Court of Appeals must all be vacated and set
evaluation or assessment of the chances of each party’s aside.
case."98 Thus in JDR, the JDR judge lacks the authority to render a
resolution of the dispute that is binding upon the parties in conflict. In
The petitioner and the respondent must then be referred to arbitration
arbitration, on the other hand, the dispute is submitted to an
pursuant to the arbitration clause of the 2005 Lease Contract.
arbitrator/s —a neutral third person or a group of thereof— who shall
have the authority to render a resolution binding upon the parties. 99
This Court is not unaware of the apparent harshness of the Decision
that it is about to make. Nonetheless, this Court must make the same
Clearly, the mere submission of a dispute to JDR proceedings would
if only to stress the point that, in our jurisdiction, bona fide arbitration
not necessarily render the subsequent conduct of arbitration a mere
agreements are recognized as valid;102 and that laws,103 rules and
surplusage. The failure of the parties in conflict to reach an amicable
regulations104 do exist protecting and ensuring their enforcement as a
settlement before the JDR may, in fact, be supplemented by their
matter of state policy. Gone should be the days when courts treat
resort to arbitration where a binding resolution to the dispute could
otherwise valid arbitration agreements with disdain and hostility, if not
finally be achieved. This situation precisely finds application to the
outright " jealousy,"105 and then get away with it. Courts should instead
case at bench.
learn to treat alternative means of dispute resolution as effective
partners in the administration of justice and, in the case of arbitration
Neither would the summary nature of ejectment cases be a valid agreements, to afford them judicial restraint.106 Today, this Court only
reason to disregard the enforcement of the arbitration clause of the performs its part in upholding a once disregarded state policy.
2005 Lease Contract . Notwithstanding the summary nature of
ejectment cases, arbitration still remains relevant as it aims not only
Civil Case No. CV 09-0346
to afford the parties an expeditious method of resolving their dispute.
This Court notes that, on 30 September 2009, petitioner filed with the
A pivotal feature of arbitration as an alternative mode of dispute
RTC of Parañaque City, a complaint107 for the rescission or
resolution is that it is, first and foremost, a product of party autonomy
cancellation of the Deed of Donation and Amended Deed of Donation
or the freedom of the parties to " make their own arrangements to
against the respondent. The case is currently pending before Branch
resolve their own disputes."100 Arbitration agreements manifest not
257 of the RTC, docketed as Civil Case No. CV 09-0346.
only the desire of the parties in conflict for an expeditious resolution
of their dispute. They also represent, if not more so, the parties’
mutual aspiration to achieve such resolution outside of judicial This Court recognizes the great possibility that issues raised in Civil
auspices, in a more informal and less antagonistic environment under Case No. CV 09-0346 may involve matters that are rightfully arbitrable
the terms of their choosing. Needless to state, this critical feature can per the arbitration clause of the 2005 Lease Contract. However, since
never be satisfied in an ejectment case no matter how summary it the records of Civil Case No. CV 09-0346 are not before this Court,
may be. We can never know with true certainty and only speculate. In this light,
let a copy of this Decision be also served to Branch 257of the RTC of
Parañaque for its consideration and, possible, application to Civil
Having hurdled all the challenges against the application of the
Case No. CV 09-0346.
arbitration clause of the 2005 Lease Agreement in this case, We shall
now proceed with the discussion of its legal effects.
WHEREFORE, premises considered, the petition is hereby
GRANTED . Accordingly, We hereby render a Decision:
Legal Effect of the Application of the
Arbitration Clause
1. SETTING ASIDE all the proceedings undertaken by the
Metropolitan Trial Court, Branch 77, of Parañaque City in
Since there really are no legal impediments to the application of the
relation to Civil Case No. 2009-307 after the filing by
arbitration clause of the 2005 Contract of Lease in this case, We find
petitioner of its Answer with Counterclaim ;
that the instant unlawful detainer action was instituted in violation of
such clause. The Law, therefore, should have governed the fate of the
parties and this suit:
2. REMANDING the instant case to the MeTC,
SUSPENDED at the point after the filing by petitioner of its
Answer with Counterclaim;
3. Respondent Mabunay to indemnify respondent Utassco C. THE COURT OF APPEALS SERIOUSLY ERRED IN
of the amounts respondent Utassco will have paid to RELYING ON THE CASE OF AEROSPACE CHEMICAL
claimant under this decision, plus interest thereon at the INDUSTRIES, INC. v. COURT OF APPEALS, 315 SCRA
rate of 12% per annum computed from the date he is 94, WHICH HAS NOTHING TO DO WITH
notified of such payment made by respondent Utassco to CONSTRUCTION AGREEMENTS.21
claimant until fully paid, and to pay Utassco ₱100,000.00
as attorney’s fees.
Our Ruling
SO ORDERED.17
On the procedural issues raised, we find no merit in petitioner’s
contention that with the institutionalization of alternative dispute
Dissatisfied, respondent filed in the CA a petition for review under resolution under Republic Act (R.A.) No. 9285,22 otherwise known as
Rule 43 of the 1997 Rules of Civil Procedure, as amended. the Alternative Dispute Resolution Act of 2004, the CA was divested
of jurisdiction to review the decisions or awards of the CIAC. Petitioner
erroneously relied on the provision in said law allowing any party to a
In the assailed decision, the CA agreed with the CIAC that the specific
domestic arbitration to file in the Regional Trial Court (RTC) a petition
condition in the Performance Bond did not clearly state the limitation
either to confirm, correct or vacate a domestic arbitral award.
of the surety’s liability. Pursuant to Article 137718 of the Civil Code, the
CA said that the provision should be construed in favor of petitioner
considering that the obscurely phrased provision was drawn up by We hold that R.A. No. 9285 did not confer on regional trial courts
respondent and Mabunay. Further, the appellate court stated that jurisdiction to review awards or decisions of the CIAC in construction
respondent could not possibly guarantee the down payment because disputes. On the contrary, Section 40 thereof expressly declares that
it is not Mabunay who owed the down payment to petitioner but the confirmation by the RTC is not required, thus:
other way around. Consequently, the completion by Mabunay of
31.39% of the construction would not lead to the extinguishment of
SEC. 40. Confirmation of Award. – The confirmation of a domestic
respondent’s liability. The ₱8.4 million was a limit on the amount of
arbitral award shall be governed by Section 23 of R.A. 876.
respondent’s liability and not a limitation as to the obligation or
undertaking it guaranteed.
A domestic arbitral award when confirmed shall be enforced in the
same manner as final and executory decisions of the Regional Trial
However, the CA reversed the CIAC’s ruling that Mabunay had
Court.
incurred delay which entitled petitioner to the stipulated liquidated
damages and unrecouped down payment. Citing Aerospace
Chemical Industries, Inc. v. Court of Appeals,19 the appellate court The confirmation of a domestic award shall be made by the regional
said that not all requisites in order to consider the obligor or debtor in trial court in accordance with the Rules of Procedure to be
default were present in this case. It held that it is only from December promulgated by the Supreme Court.
24, 2008 (completion date) that we should reckon default because the
Construction Agreement provided only for delay in the completion of
the project and not delay on a monthly basis using the work schedule A CIAC arbitral award need not be confirmed by the regional trial court
to be executory as provided under E.O. No. 1008. (Emphasis
approved by petitioner as the reference point. Hence, petitioner’s
termination of the contract was premature since the delay in this case supplied.)
was merely speculative; the obligation was not yet demandable.
Executive Order (EO) No. 1008 vests upon the CIAC original and
The dispositive portion of the CA Decision reads: exclusive jurisdiction over disputes arising from, or connected with,
contracts entered into by parties involved in construction in the
Philippines, whether the dispute arises before or after the completion
WHEREFORE, premises considered, the instant petition for review is of the contract, or after the abandonment or breach thereof. By
GRANTED. The assailed Decision dated 13 January 2010 rendered express provision of Section 19 thereof, the arbitral award of the CIAC
by the CIAC Arbitral Tribunal in CIAC Case No. 03-2009 is hereby is final and unappealable, except on questions of law, which are
REVERSED and SET ASIDE. Accordingly, the Writ of Execution appealable to the Supreme Court. With the amendments introduced
dated 24 November 2010 issued by the same tribunal is hereby by R.A. No. 7902 and promulgation of the 1997 Rules of Civil
ANNULLED and SET ASIDE. Procedure, as amended, the CIAC was included in the enumeration
of quasijudicial agencies whose decisions or awards may be appealed
to the CA in a petition for review under Rule 43. Such review of the
SO ORDERED.20
CIAC award may involve either questions of fact, of law, or of fact and
law.23
Petitioner moved for reconsideration of the CA decision while
respondent filed a motion for partial reconsideration. Both motions
Petitioner misread the provisions of A.M. No. 07-11-08-SC (Special
were denied.
ADR Rules) promulgated by this Court and which took effect on
October 30, 2009. Since R.A. No. 9285 explicitly excluded CIAC
The Issues awards from domestic arbitration awards that need to be confirmed to
be executory, said awards are therefore not covered by Rule 11 of the
Special ADR Rules,24 as they continue to be governed by EO No.
Before this Court petitioner seeks to reverse the CA insofar as it
1008, as amended and the rules of procedure of the CIAC. The CIAC
denied petitioner’s claims under the Performance Bond and to
Revised Rules of Procedure Governing Construction
reinstate in its entirety the February 2, 2010 CIAC Decision.
Arbitration25 provide for the manner and mode of appeal from CIAC
Specifically, petitioner alleged that –
decisions or awards in Section 18 thereof, which reads:
We cannot sustain the appellate court’s interpretation as it is We would highly appreciate your usual attention on this matter.
inconsistent with the terms of the Construction Agreement. Article
1374 of the Civil Code requires that the various stipulations of a x x x x33
contract shall be interpreted together, attributing to the doubtful ones
that sense which may result from all of them taken jointly. Here, the
work schedule approved by petitioner was intended, not only to serve November 5, 2008
as its basis for the payment of monthly progress billings, but also for
evaluation of the progress of work by the contractor. Article 13.01 (g) xxxx
(iii) of the Construction Agreement provides that the contractor shall
be deemed in default if, among others, it had delayed without
justifiable cause the completion of the project "by more than thirty (30) Dear Mr. Mabunay,
calendar days based on official work schedule duly approved by the
OWNER."31 This is in reference to your discussion during the meeting with Mr.
Joohan Lee last October 30, 2008 regarding the construction of the
Field Office and Stock Room for Materials intended for Villa Beatriz
use only. We understand that you have committed to complete it OWNER when the works called for under this Agreement have been
November 5, 2008 but as of this date there is no improvement or any finished and completed.
ongoing construction activity on the said field office and stockroom.
Liquidated Damage[s] payable to the OWNER shall be automatically
We are expecting deliveries of Owner Supplied Materials very soon, deducted from the contractors collectibles without prior consent and
therefore, this stockroom is badly needed. We will highly appreciate if concurrence by the CONTRACTOR.
this matter will be given your immediate attention.
12.02 To give full force and effect to the foregoing, the
Thank you. CONTRACTOR hereby, without necessity of any further act and deed,
authorizes the OWNER to deduct any amount that may be due under
Item (a) above, from any and all money or amounts due or which will
x x x x34
become due to the CONTRACTOR by virtue of this Agreement and/or
to collect such amounts from the Performance Bond filed by the
November 6, 2008 CONTRACTOR in this Agreement.36 (Emphasis supplied.)
Please note that based on your submitted revised schedule you are ART. 2228. When the breach of the contract committed by the
already delayed by approximately 57% and this will worsen should defendant is not the one contemplated by the parties in agreeing upon
you not address this matter properly. the liquidated damages, the law shall determine the measure of
damages, and not the stipulation.
We are looking forward for [sic] your cooperation and continuous
commitment in delivering this project as per contract agreement. A stipulation for liquidated damages is attached to an obligation in
order to ensure performance and has a double function: (1) to provide
for liquidated damages, and (2) to strengthen the coercive force of the
x x x x35 obligation by the threat of greater responsibility in the event of
breach.37 The amount agreed upon answers for damages suffered by
Subsequently, a joint inspection and evaluation was conducted with the owner due to delays in the completion of the project.38 As a
the assistance of the architects and engineers of petitioner and precondition to such award, however, there must be proof of the fact
Mabunay and it was found that as of November 14, 2008, the project of delay in the performance of the obligation.39
was only 31.39% complete and that the uncompleted portion was
68.61% with an estimated value per Construction Agreement as
Concededly, Article 12.01 of the Construction Agreement mentioned
₱27,880,419.52. Instead of doubling his efforts as the scheduled only the failure of the contractor to complete the project within the
completion date approached, Mabunay did nothing to remedy the stipulated period or the extension granted by the owner. However, this
delays and even reduced the deployment of workers at the project
will not defeat petitioner’s claim for damages nor respondent’s liability
site. Neither did Mabunay, at anytime, ask for an extension to under the Performance Bond. Mabunay was clearly in default
complete the project. Thus, on November 19, 2008, petitioner advised considering the dismal percentage of his accomplishment (32.38%) of
Mabunay of its decision to terminate the contract on account of the
the work he contracted on account of delays in executing the
tremendous delay the latter incurred. This was followed by the claim scheduled work activities and repeated failure to provide sufficient
against the Performance Bond upon the respondent on December 18, manpower to expedite construction works. The events of default and
2008.
remedies of the Owner are set forth in Article 13, which reads:
Petitioner’s claim against the Performance Bond included the ARTICLE 13 – DEFAULT OF CONTRACTOR:
liquidated damages provided in the Construction Agreement, as
follows:
13.01 Any of the following shall constitute an Event of Default on the
part of the CONTRACTOR.
ARTICLE 12 – LIQUIDATED DAMAGES:
xxxx
12.01 Time is of the essence in this Agreement. Should the
CONTRACTOR fail to complete the PROJECT within the period
stipulated herein or within the period of extension granted by the g. In case the CONTRACTOR has done any of the following:
OWNER, plus One (1) Week grace period, without any justifiable
reason, the CONTRACTOR hereby agrees –
(i.) has abandoned the Project
The conditions of this obligation are as follows: 1) Respondent Utassco to pay to petitioner J Plus Asia
Development Corporation the full amount of the
Whereas the JPLUS ASIA, requires the principal SEVEN SHADES Performance Bond, ₱8,400,000.00, pursuant to Art. 13 of
OF BLUE CONSTRUCTION AND DEVELOPMENT, INC. to post a the Construction Agreement dated December 24, 2007,
bond of the abovestated sum to guarantee 20% down payment for the with interest at the rate of 6% per annum computed from
construction of Building 25 (Villa Beatriz) 72-Room Condotel, The the date of the filing of the complaint until the finality of this
decision, and 12% per annum computed from the date this
decision becomes final until fully paid; and
SO ORDERED.
No pronouncement as to costs.
SO ORDERED.
G.R. No. 91228. March 22, 1993. accordance with the terms of their agreement (Sec. 6 Republic Act
876). Respondent's arguments touching upon the merits of the
dispute are improperly raised herein. They should be addressed to
PUROMINES, INC., petitioner, vs. COURT OF APPEAL and PHILIPP
the arbitrators. This proceeding is merely a summary remedy to
BROTHERS OCEANIC, INC., respondents.
enforce the agreement to arbitrate. The duty of the court in this case
is not to resolve the merits of the parties' claims but only to determine
SYLLABUS if they should proceed to arbitration or not. And although it has been
ruled that a privolous or patently baseless claim should not be ordered
to arbitration it is also recognized that the mere fact that a defense
1. CIVIL LAW; OBLIGATIONS OF VENDOR; DAMAGES ARISING exist against a claim does not make it frivolous or baseless."
FROM CARRIAGE AND DELIVERY. — We agree with the court a
quo that the sales contract is comprehensive enough to include claims
for damages arising from carriage and delivery of the goods. As a 7. REMEDIAL LAW; CIVIL PROCEDURE; PLEADINGS;
general rule, the seller has the obligation to transmit the goods to the COMPLAINT; ANNEXES ATTACHED THEREOF, PART OF THE
buyer, and concomitant thereto, the contracting of a carrier to deliver RECORD. — Petitioner contend that the arbitration provision in the
the same. bills of lading should not have been discussed as an issue in the
decision of the Court of Appeals since it was not raised as a special
or affirmative defense. The three bills of lading were attached to the
2. COMMERCIAL LAW; MARITIME TRANSPORTATION; MARITIME complaint as Annexes "A," "B," and "C," and are therefore parts
COMMERCE; CHARTER PARTIES, CONSTRUED. — American thereof and may be considered as evidence although not introduced
jurisprudence defines charter party as a contract by which an entire
as such. Hence, it was then proper for the court a quo to discuss the
ship or some principal part thereof is let by the owner to another contents of the bills of lading, having been made part of the record.
person for a specified time or use. Charter or charter parties are of
two kinds. Charter of demise or bareboat and contracts of
affreightment. DECISION
"The trial court sensibly said that 'all the causes of action alleged in
On the other hand, a contract of affreightment is in which the owner
the plaintiffs amended complaint are based upon the supposed
of the vessel leases part or all of its space to haul goods for others. It
violations committed by the defendants of the 'Contract of
is a contract for a special service to be rendered by the owner of the
Construction of a Building' and that 'the provisions of paragraph 15
vessel 12 and under such contract the general owner retains the
hereof leave a very little room for doubt that the said causes of action
possession, command and navigation of the ship, the charterer or
are embraced within the phrase 'any and all questions, disputes or
freighter merely having use of the space in the vessel in return for his
differences between the parties hereto relative to the construction of
payment of the charter hire. 13 If the charter is a contract of
the building,' which must be determined by arbitration of two persons
affreightment, which leaves the general owner in possession of the
and such determination by the arbitrators shall be 'final, conclusive
ship as owner for the voyage, the rights, responsibilities of ownership
and binding upon both parties unless they to court, in which the case
rest on the owner and the charterer is usually free from liability to third
the determination by arbitration is a condition precedent 'for taking any
persons in respect of the ship. 14
court action."
Neither can petitioner contend that the arbitration provision in the bills
of lading should not have been discussed as an issue in the decision
of the Court of Appeals since it was not raised as a special or
affirmative defense. The three bills of lading were attached to the
complaint as Annexes "A," "B," and "C," and are therefore parts
thereof and may be considered as evidence although not introduced
as such. 16 Hence, it was then proper for the court a quo to discuss
the contents of the bills of lading, having been made part of the record.
Going back to the main subject of this case, arbitration has been held
valid and constitutional. Even before the enactment of Republic Act
No. 876, this Court has countenanced the settlement of disputes
through arbitration. The rule now is that unless the agreement is such
as absolutely to close the doors of the courts against the parties,
which agreement would be void, the courts will look with favor upon
such amicable arrangements and will only interfere with great
reluctance to anticipate or nullify the action of the arbitrator. 17
Allow us to take a leaf from history and briefly trace the evolution of
In recognition of the pressing need for an arbitral machinery for the
arbitration as a mode of dispute settlement.
early and expeditious settlement of disputes in the construction
industry, a Construction Industry Arbitration Commission (CIAC) was
Because conflict is inherent in human society, much effort has been created by Executive Order No. 1008, enacted on February 4, 1985.
expended by men and institutions in devising ways of resolving the
same. With the progress of civilization, physical combat has been
In practice nowadays, absent an agreement of the parties to resolve
ruled out and instead, more specific means have been evolved, such
their disputes via a particular mode, it is the regular courts that remain
as recourse to the good offices of a disinterested third party, whether
the fora to resolve such matters. However, the parties may opt for
this be a court or a private individual or individuals.
recourse to third parties, exercising their basic freedom to "establish
such stipulation, clauses, terms and conditions as they may deem
Legal history discloses that "the early judges called upon to solve convenient, provided they are not contrary to law, morals, good
private conflicts were primarily the arbiters, persons not specially customs, public order or public policy." 12 In such a case, resort to the
trained but in whose morality, probity and good sense the parties in arbitration process may be spelled out by them in a contract in
conflict reposed full trust. Thus, in Republican anticipation of disputes that may arise between them. Or this may be
Rome, arbiter and judge (judex) were synonymous. The magistrate stipulated in a submission agreement when they are actually
or praetor, after noting down the conflicting claims of litigants, and confronted by a dispute. Whatever be the case, such recourse to an
clarifying the issues, referred them for decision to a private person extrajudicial means of settlement is not intended to completely deprive
designated by the parties, by common agreement, or selected by the courts of jurisdiction. In fact, the early cases on arbitration carefully
them from an apposite listing (the album judicium) or else by having spelled out the prevailing doctrine at the time, thus: ". . . a clause in a
the arbiter chosen by lot. The judges proper, as specially trained state contract providing that all matters in dispute between the parties shall
officials endowed with own power and jurisdiction, and taking be referred to arbitrators and to them alone is contrary to public policy
cognizance of litigations from beginning to end, only appeared under and cannot oust the courts of Jurisdiction." 13
the Empire, by the so-called cognitio extra ordinem." 5
But certainly, the stipulation to refer all future disputes to an arbitrator
Such means of referring a dispute to a third party has also long been or to submit an ongoing dispute to one is valid. Being part of a contract
an accepted alternative to litigation at common law. 6 between the parties, it is binding and enforceable in court in case one
of them neglects, fails or refuses to arbitrate. Going a step further, in
the event that they declare their intention to refer their differences to
Sparse though the law and jurisprudence may be on the subject of
arbitration first before taking court action, this constitutes a condition
arbitration in the Philippines, it was nonetheless recognized in the precedent, such that where a suit has been instituted prematurely, the
Spanish Civil Code; specifically, the provisions on compromises made court shall suspend the same and the parties shall be directed
applicable to arbitrations under Articles 1820 and 1821.7 Although
forthwith to proceed to arbitration. 14
said provisions were repealed by implication with the repeal of the
Spanish Law of Civil Procedure, 8 these and additional ones were
reinstated in the present Civil Code. 9 A court action may likewise be proven where the arbitrator has not
been selected by the parties. 15
Arbitration found a fertile field in the resolution of labor-management
disputes in the Philippines. Although early on, Commonwealth Act 103 Under present law, may the parties who agree to submit their disputes
(1936) provided for compulsory arbitration as the state policy to be to arbitration further provide that the arbitrators' award shall be final,
administered by the Court of Industrial Relations, in time such a unappealable and executory?
modality gave way to voluntary arbitration. While not completely
supplanting compulsory arbitration which until today is practiced by
Article 2044 of the Civil Code recognizes the validity of such
government officials, the Industrial Peace Act which was passed in
stipulation, thus:
1953 as Republic Act No. 875, favored the policy of free collective
bargaining, in general, and resort to grievance procedure, in
particular, as the preferred mode of settling disputes in industry. It was Any stipulation that the arbitrators' award or
accepted and enunciated more explicitly in the Labor Code, which decision shall be final is valid, without prejudice
was passed on November 1, 1974 as Presidential Decree No. 442, to Articles 2038, 2039 and 2040.
with the amendments later introduced by Republic Act No. 6715
(1989).
Similarly, the Construction Industry Arbitration Law provides that the
arbitral award "shall be final and inappealable except on questions of
Whether utilized in business transactions or in employer-employee law which shall be appealable to the Supreme Court." 16
relations, arbitration was gaining wide acceptance. A consensual
process, it was preferred to orders imposed by government upon the
Under the original Labor Code, voluntary arbitration awards or
disputants. Moreover, court litigations tended to be time-consuming,
decisions were final, unappealable and executory. "However,
costly, and inflexible due to their scrupulous observance of the due
voluntary arbitration awards or decisions on money claims, involving
process of law doctrine and their strict adherence to rules of evidence.
an amount exceeding One Hundred Thousand Pesos (P100,000.00)
or forty-percent (40%) of the paid-up capital of the respondent
As early as the 1920's, this Court declared: employer, whichever is lower, maybe appealed to the National Labor
Relations Commission on any of the following grounds: (a) abuse of
discretion; and (b) gross incompetence." 17 It is to be noted that the
In the Philippines fortunately, the attitude of the
appeal in the instances cited were to be made to the National Labor
courts toward arbitration agreements is slowly
Relations Commission and not to the courts.
With the subsequent deletion of the above-cited provision from the 3. The Honorable Arbitrator committed grave
Labor Code, the voluntary arbitrator is now mandated to render an error in granting extra compensation to Roblecor
award or decision within twenty (20) calendar days from the date of for loss due to delayed payment of progress
submission of the dispute and such decision shall be final and billings;
executory after ten (10) calendar days from receipt of the copy of the
award or decision by the parties. 18
4. The Honorable Arbitrator committed grave
error in granting extra compensation to Roblecor
Where the parties agree that the decision of the arbitrator shall be final for loss of productivity due to the cement crisis;
and unappealable as in the instant case, the pivotal inquiry is whether
subject arbitration award is indeed beyond the ambit of the court's
5. The Honorable Arbitrator committed grave
power of judicial review.
error in granting extra compensation to Roblecor
for losses allegedly sustained on account of the
We rule in the negative. It is stated explicitly under Art. 2044 of the failed coup d'état;
Civil Code that the finality of the arbitrators' award is not absolute and
without exceptions. Where the conditions described in Articles 2038,
6. The Honorable Arbitrator committed grave
2039 and 2040 applicable to both compromises and arbitrations are
error in granting to Roblecor the amount
obtaining, the arbitrators' award may be annulled or
representing the alleged unpaid billings of Chung
rescinded. 19 Additionally, under Sections 24 and 25 of the Arbitration
Fu;
Law, there are grounds for vacating, modifying or rescinding an
arbitrator's award. 20 Thus, if and when the factual circumstances
referred to in the above-cited provisions are present, judicial review of 7. The Honorable Arbitrator committed grave
the award is properly warranted. error in granting to Roblecor the amount
representing the alleged extended overhead
expenses;
What if courts refuse or neglect to inquire into the factual milieu of an
arbitrator's award to determine whether it is in accordance with law or
within the scope of his authority? How may the power of judicial review 8. The Honorable Arbitrator committed grave
be invoked? error in granting to Roblecor the amount
representing expenses for change order for site
development outside the area of responsibility of
This is where the proper remedy is certiorari under Rule 65 of the
Roblecor;
Revised Rules of Court. It is to be borne in mind, however, that this
action will lie only where a grave abuse of discretion or an act without
or in excess of jurisdiction on the part of the voluntary arbitrator is 9. The Honorable Arbitrator committed grave
clearly shown. For "the writ of certiorari is an extra-ordinary remedy error in granting to Roblecor the cost of
and that certiorari jurisdiction is not to be equated with appellate warehouse No. 2;
jurisdiction. In a special civil action of certiorari, the Court will not
engage in a review of the facts found nor even of the law as
10. The Honorable Arbitrator committed grave
interpreted or applied by the arbitrator unless the supposed errors of
fact or of law are so patent and gross and prejudicial as to amount to error in granting to Roblecor extra compensation
a grave abuse of discretion or an exces de pouvoir on the part of the for airduct change in dimension;
arbitrator." 21
11. The Honorable Arbitrator committed grave
Even decisions of administrative agencies which are declared "final" error in granting to Roblecor extra compensation
for airduct plastering; and
by law are not exempt from judicial review when so warranted. Thus,
in the case of Oceanic Bic Division (FFW), et al. v. Flerida Ruth P.
Romero, et al., 22 this Court had occasion to rule that: 12. The Honorable Arbitrator committed grave
error in awarding to Roblecor attorney's fees.
. . . Inspite of statutory provisions making "final"
the decisions of certain administrative After closely studying the list of errors, as well as petitioners'
agencies, we have taken cognizance of petitions discussion of the same in their Motion to Remand Case For Further
questioning these decisions where want of Hearing and Reconsideration and Opposition to Motion for
jurisdiction, grave abuse of discretion, violation of Confirmation of Award, we find that petitioners have amply made out
due process, denial of substantial justice or a case where the voluntary arbitrator failed to apply the terms and
erroneous interpretation of the law were brought provisions of the Construction Agreement which forms part of the law
to our attention . . . 23 (Emphasis ours). applicable as between the parties, thus committing a grave abuse of
discretion. Furthermore, in granting unjustified extra compensation to
It should be stressed, too, that voluntary arbitrators, by the nature of respondent for several items, he exceeded his powers — all of which
their functions, act in a quasi-judicial capacity. 24 It stands to reason, would have constituted ground for vacating the award under Section
24 (d) of the Arbitration Law.
therefore, that their decisions should not be beyond the scope of the
power of judicial review of this Court.
But the respondent trial court's refusal to look into the merits of the
case, despite prima facie showing of the existence of grounds
In the case at bar, petitioners assailed the arbitral award on the
following grounds, most of which allege error on the part of the warranting judicial review, effectively deprived petitioners of their
arbitrator in granting compensation for various items which apparently opportunity to prove or substantiate their allegations. In so doing, the
trial court itself committed grave abuse of discretion. Likewise, the
are disputed by said petitioners:
appellate court, in not giving due course to the petition, committed
grave abuse of discretion. Respondent courts should not shirk from
1. The Honorable Arbitrator committed grave exercising their power to review, where under the applicable laws and
error in failing to apply the terms and conditions jurisprudence, such power may be rightfully exercised; more so where
of the Construction Agreement, Dormitory the objections raised against an arbitration award may properly
Contract and Electrical Contract, and in using constitute grounds for annulling, vacating or modifying said award
instead the "practices" in the construction under the laws on arbitration WHEREFORE, the petition is
industry; GRANTED. The Resolutions of the Court of Appeals dated October
22, 1990 and December 3, 1990 as well as the Orders of respondent
Regional Trial Court dated July 31, 1990 and August 23, 1990,
2. The Honorable Arbitrator committed grave
including the writ of execution issued pursuant thereto, are hereby
error in granting extra compensation to Roblecor
SET ASIDE. Accordingly, this case is REMANDED to the court of
for loss of productivity due to adverse weather
origin for further hearing on this matter. All incidents arising therefrom
conditions;
are reverted to the status quo ante until such time as the trial court
shall have passed upon the merits of this case. No costs.
G.R. No. 139273 November 28, 2000 Set for Preliminary Hearing. On February 2, 1994 petitioners filed a
Motion for Reconsideration of the Order dated December 28, 1993.
On February 11, 1994, [the RTC] issued an Order denying petitioners’
CALIFORNIA AND HAWAIIAN SUGAR COMPANY; PACIFIC
Motion for Reconsideration. Hence, the instant petition."5
GULF MARINE, INC.; and C.F. SHARP & COMPANY, petitioners,
vs.
PIONEER INSURANCE AND SURETY Ruling of the Court of Appeals
CORPORATION, respondent.
Affirming the trial court, the CA held that petitioners cannot rely on
DECISION Section 5, Rule 166 of the pre-1997 Rules of Court,7 because a Motion
to Dismiss had previously been filed. Further, it ruled that the
arbitration clause provided in the charter party did not bind
PANGANIBAN, J.:
respondent. It reasoned as follows:
"1. Whether or not insurer, as subrogee of the consignee, Denial of the Motion for a Preliminary Hearing Was a Grave Abuse of
is bound by the charter party which is incorporated and Discretion
referred to in the bill of lading.
The more crucial question that we must settle here is whether the trial
2. Whether or not the motion to dismiss should be granted court committed grave abuse of discretion when it denied petitioners’
on the ground that a condition precedent has not been Motion for a Preliminary Hearing on their affirmative defense of lack
complied with, based on the arbitration clause incorporated of cause of action. Undeniably, a preliminary hearing is not
in the bill of lading. mandatory, but subject to the discretion of the trial court.16 In the light
of the circumstances in this case, though, we find that the lower court
committed grave abuse of discretion in refusing to grant the Motion.
3. Whether or not the Court of Appeals erred in holding that
the trial court did not commit grave abuse of discretion in
denying petitioners’ motion for preliminary hearing. We note that the trial court deferred the resolution of petitioners’
Motion to Dismiss because of a single issue. It was apparently unsure
whether the charter party that the bill of lading referred to was indeed
4. Whether or not the trial court can defer the resolution of the Baltimore Berth Grain Charter Party submitted by
a motion to dismiss on the ground that the ground relied petitioners.1âwphi1
upon is indubitable.
Considering that there was only one question, which may even be
5. Whether or not the petitioners have resorted to an deemed to be the very touchstone of the whole case, the trial court
improper remedy which makes them responsible for had no cogent reason to deny the Motion for Preliminary Hearing.
delaying the case." Indeed, it committed grave abuse of discretion when it denied a
preliminary hearing on a simple issue of fact that could have possibly
In the main, the two principal matters before us are: (1) the denial of settled the entire case. Verily, where a preliminary hearing appears to
petitioners’ Motion for Preliminary Hearing and (2) the propriety of the suffice, there is no reason to go on to trial. One reason why dockets
CA ruling regarding the arbitration clause. of trial courts are clogged is the unreasonable refusal to use a process
or procedure, like a motion to dismiss, which is designed to abbreviate
the resolution of a case.
The Court’s Ruling
The CA also erred when it held that the arbitration clause was not
First Issue: Preliminary Hearing of Affirmative Defense binding on respondent. We reiterate that the crux of this case is
whether the trial court committed grave abuse of discretion in denying
At the outset, we must emphasize that the crux of the present the aforecited Motion. There was neither need nor reason to rule on
controversy is the trial court’s Order denying petitioner’s Motion to Set the applicability of the arbitration clause.
for Preliminary Hearing the affirmative defense of lack of cause of
action. Not questioned here is the said court’s Order holding in Be that as it may, we find the CA’s reasoning on this point faulty.
abeyance the hearing of petitioner’s Motion to Dismiss. Citing Pan Malayan Insurance Corporation v. CA,17 it ruled that the
right of respondent insurance company as subrogee was not based
Affirmative Defense May Be Raised on the charter party or any other contract; rather, it accrued upon the
payment of the insurance claim by private respondent to the insured
consignee. There was nothing in Pan Malayan, however, that
Still in effect when the case was before the trial court, Section 5, Rule prohibited the applicability of the arbitration clause to the subrogee.
16 of the pre-1997 Rules of Court, reads: That case merely discussed, inter alia, the accrual of the right of
subrogation and the legal basis therefor.18 This issue is completely
"Sec. 5. Pleading grounds as affirmative defenses. - Any of the different from that of the consequences of such subrogation; that is,
grounds for dismissal provided for in this Rule, except improper the rights that the insurer acquires from the insured upon payment of
venue, may be pleaded as an affirmative defense, and a preliminary the indemnity.
hearing may be had thereon as if a motion to dismiss had been filed."
WHEREFORE, the Petition is GRANTED and the appealed Decision
Respondent argues that the above provision cannot be applied, is hereby REVERSED. The case is REMANDED to the trial court for
because petitioners have already filed a Motion to Dismiss. preliminary hearing on petitioners’ affirmative defense. No costs.