FOR RENOVATION WORKS AT SANDBOX‐LABADI,ACCRA‐GHANA


Description Duration Start Finish

October 2019 November 2019


30 03 06 09 12 15 18 21 24 27 30 02 05 08 11 14 17 20 23 26 29
PROPOSED SANDBOX COMPLEX RENOVATION 53 days Tue 01-10-19 Sat 30-11-19
Construction of lower floor 27 days Tue 01-10-19 Thu 31-10-19
Setting out 2 days Tue 01-10-19 Wed 02-10-19
Earthwork excavation 8 days Tue 01-10-19 Wed 09-10-19
Reinforcement works for joining pool wall and 2 days Fri 11-10-19 Sat 12-10-19
suspended slaps
Formworks for pool walls for suspended slaps 4 days Tue 15-10-19 Fri 18-10-19
Concrete works 1 day Sat 19-10-19 Mon 21-10-19
Backfilling 1 day Mon 21-10-19 Tue 22-10-19
Blockworks 3 days Wed 02-10-19 Fri 04-10-19
Finishing works for lower floor 20 days Mon 07-10-19 Tue 29-10-19
First fix works for plumbing, electrical and 3 days Mon 07-10-19 Wed 09-10-19
aircondition
Internal and external plastering and rendering 3 days Thu 10-10-19 Sat 12-10-19
Fixing of window and door frames 2 days Mon 07-10-19 Tue 08-10-19
Fixing of window and door 2 days Mon 14-10-19 Tue 15-10-19
Ceiling works 3 days Wed 16-10-19 Fri 18-10-19
Wall and floor tiling 2 days Thu 10-10-19 Fri 11-10-19
Second fix for plumbing, electricals and mechanica 5 days Mon 14-10-19 Fri 18-10-19
Painting works 5 days Thu 14-11-19 Tue 19-11-19
Construction of ground floor 35 days Tue 01-10-19 Sat 09-11-19
Setting out 1 day Tue 01-10-19 Tue 01-10-19
Earthwork excavation 3 days Wed 25-09-19 Fri 27-09-19
Construction of column base 2 days Tue 01-10-19 Wed 02-10-19
Blockworks for ground floor 14 days Thu 03-10-19 Fri 18-10-19
Backfilling 3 days Sat 19-10-19 Tue 22-10-19
Reinforcement works for joining beams and slab 3 days Wed 23-10-19 Fri 25-10-19
Formworks for beams and slaps 3 days Sat 26-10-19 Tue 29-10-19
Concrete works 5 days Wed 30-10-19 Mon 04-11-19
Construction of stair 4 days Wed 09-10-19 Sat 12-10-19
Finishing works for ground floor 38 days Mon 07-10-19 Tue 19-11-19
First fix works for plumbing, electrical and 5 days Mon 07-10-19 Fri 11-10-19
aircondition
Internal and external plastering and rendering 5 days Sat 12-10-19 Fri 18-10-19
Fixing of window and door frames 3 days Wed 09-10-19 Fri 11-10-19
Fixing of window and door 3 days Sat 19-10-19 Wed 23-10-19
Fixing of roofing 3 days Sat 02-11-19 Wed 06-11-19
Ceiling works 5 days Thu 24-10-19 Tue 29-10-19
Wall and floor tiling 5 days Sat 12-10-19 Fri 18-10-19
Second fix for plumbing, electricals and mechanica 5 days Sat 19-10-19 Fri 25-10-19
Painting works 7 days Mon 11-11-19 Mon 18-11-19
Construction of upper floor 5 days Mon 07-10-19 Fri 11-10-19
Setting out 1 day? Mon 07-10-19 Mon 07-10-19
Blockworks for upper floor 2 days Mon 07-10-19 Tue 08-10-19
Form work for pigmented concrete 1 day? Thu 10-10-19 Thu 10-10-19
Pigmented concrete 1 day? Mon 14-10-19 Mon 14-10-19
Finishing works for upper floor 17 days Wed 09-10-19 Mon 28-10-19
First fix works for plumbing, electrical and 3 days Wed 09-10-19 Fri 11-10-19
aircondition
Internal and external plastering and rendering 2 days Sat 12-10-19 Tue 15-10-19
Fixing of window and door frames 2 days Wed 16-10-19 Thu 17-10-19
Fixing of window and door 2 days Sat 19-10-19 Tue 22-10-19
Ceiling works 3 days Wed 23-10-19 Fri 25-10-19
Floor finishes 1 day? Sat 26-10-19 Mon 28-10-19
Second fix for plumbing, electricals and 1 day? Tue 29-10-19 Tue 29-10-19
mechanical
Painting works 2 days Mon 11-11-19 Tue 12-11-19
Construction of luxurious building 17 days Thu 03-10-19 Tue 22-10-19
Demolition and levelling of site and disposal of 1 day? Thu 03-10-19 Thu 03-10-19
debris
Setting out 1 day? Fri 04-10-19 Fri 04-10-19
Earthwork excavation 2 days Fri 04-10-19 Sat 05-10-19
Construction of retaining wall for luxurious 2 days Thu 03-10-19 Fri 04-10-19
building
Construction of column base 1 day? Mon 07-10-19 Mon 07-10-19
Blockworks for luxurious building 5 days Tue 08-10-19 Sat 12-10-19
Backfilling 1 day? Sat 05-10-19 Mon 07-10-19
Reinforcement works for joining beams and slab 2 days Tue 08-10-19 Wed 09-10-19

Formworks for beams and slaps 1 day? Thu 10-10-19 Thu 10-10-19
Concrete works 1 day? Fri 11-10-19 Fri 11-10-19
Finishing works for ground floor 26 days Mon 14-10-19 Tue 12-11-19
First fix works for plumbing, electrical and 5 days Mon 14-10-19 Fri 18-10-19
aircondition
Internal and external plastering and rendering 3 days Sat 19-10-19 Tue 22-10-19
Fixing of window and door frames 2 days Wed 23-10-19 Thu 24-10-19
Fixing of window and door 2 days Sat 19-10-19 Tue 22-10-19
Ceiling works 4 days Tue 22-10-19 Fri 25-10-19
Wall and floor tiling 2 days Wed 16-10-19 Thu 17-10-19
Second fix for plumbing, electricals and 5 days Thu 17-10-19 Tue 22-10-19
mechanical
Painting works 3 days Mon 11-11-19 Wed 13-11-19
External works 15 days Thu 14-11-19 Sat 30-11-19
Construction of external underground pipeline 5 days Thu 14-11-19 Tue 19-11-19
Drilling of manhole 5 days Fri 01-11-19 Wed 06-11-19
External landscaping 5 days Thu 14-11-19 Tue 19-11-19
Preparation for handing over 12 days Mon 18-11-19 Sat 30-11-19
Test and commissioning of electrical,AC,plumbing 5 days Mon 18-11-19 Fri 22-11-19
Internal and external cleaning 4 days Mon 25-11-19 Thu 28-11-19
Handing over 2 days Fri 29-11-19 Sat 30-11-19