Formworks for beams and slaps 1 day? Thu 10-10-19 Thu 10-10-19
Concrete works 1 day? Fri 11-10-19 Fri 11-10-19
Finishing works for ground floor 26 days Mon 14-10-19 Tue 12-11-19
First fix works for plumbing, electrical and 5 days Mon 14-10-19 Fri 18-10-19
aircondition
Internal and external plastering and rendering 3 days Sat 19-10-19 Tue 22-10-19
Fixing of window and door frames 2 days Wed 23-10-19 Thu 24-10-19
Fixing of window and door 2 days Sat 19-10-19 Tue 22-10-19
Ceiling works 4 days Tue 22-10-19 Fri 25-10-19
Wall and floor tiling 2 days Wed 16-10-19 Thu 17-10-19
Second fix for plumbing, electricals and 5 days Thu 17-10-19 Tue 22-10-19
mechanical
Painting works 3 days Mon 11-11-19 Wed 13-11-19
External works 15 days Thu 14-11-19 Sat 30-11-19
Construction of external underground pipeline 5 days Thu 14-11-19 Tue 19-11-19
Drilling of manhole 5 days Fri 01-11-19 Wed 06-11-19
External landscaping 5 days Thu 14-11-19 Tue 19-11-19
Preparation for handing over 12 days Mon 18-11-19 Sat 30-11-19
Test and commissioning of electrical,AC,plumbing 5 days Mon 18-11-19 Fri 22-11-19
Internal and external cleaning 4 days Mon 25-11-19 Thu 28-11-19
Handing over 2 days Fri 29-11-19 Sat 30-11-19