OFD planning and Correction of System Deficiency work of Chandil Left Main Canal System including CADWM Report

- WORK SCHEDULE
Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19
Sl.
No. Details of activity W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4

1 Correction of System Deficiency Works of Distribution system from (0 to 78.58 km)

a) Survey of canal system for system deficiency (On-going)

b) Verification of the survey by the department

b) System deficiency studies (0 to 78.58 km) including design & cost estimates

Submission of Distributary-wise Planning, Design, Drawings & Cost estimate of OFD works of
2
distribution system between (0 to 78.58 km) and (78.58 to 127.88 km)

a) Planning, Design, Drawings & Cost estimate of distribution system (0 to 78.58 km)

b) Planning, Design, Drawings & Cost estimate of distribution system (78.58km - Tail end)

3 Final Report on OFD works and Final Report on System Deficinecy

a) Incorporation of observations and suggestions on Distributary-wise submission

b) Any updation on system deficiency works based on planning and design

Preparation of CADWM report as per CWC guidelines (Submitted)


4 Completed

DELIVERABLES
1 Survey of canal system for system deficiency (0.00 - 78.58 km)

2 Survey of canal system for OFD Planning (0.00 - 78.58 km)

3 System deficiency studies (0 to 78.58 km) including design & cost estimates

Submission of Distributary-wise Planning, Design, Drawings & Cost estimate of OFD works of
4
distribution system between (0 to 78.58 km)

Submission of Distributary-wise Planning, Design, Drawings & Cost estimate of OFD works of
5
distribution system between (78.58 to 127.88 km)

Preparation of CADWM report as per CWC guidelines


9 Completed

Activity Deliverables