Professional Documents
Culture Documents
CASE DIGEST
March 9. 2015
FACTS
ISSUE
RULINGS
At the time of the ocular inspection conducted by the HLURB ENCRFO, the
unit was not yet completely finished as the kitchen cabinets and fixtures were not yet
installed and the agreed amenities were not yet available. The delay for the
completion of the project in accordance with the license to sell also renders the
petitioners liable for the payment of the administrative fine.
The CA found it apparent that the petitioner has indeed committed delay in
the performance of the obligation, which is to finish and deliver the subject unit to the
respondent within the stipulated period. This results to a breach of contract made by
the petitioner.
The Supreme Court affirmed the ruling of the CA, with modification for the
amount of moral damages to be paid by the petitioners.
Basic is the rule that the right of rescission of a party to an obligation under
Art. 1191 is predicated on a breach of faith by the party who violates the reciprocity
between them. The breach contemplated in the said provision is the obligor’s failure
to comply with an existing obligation. The court shall decree the rescission if the
breach is found without just cause. The delays in the completion of the project as
well as in the delivery of the unit are breaches of statutory and contractual
obligations which entitle the respondent to rescind the contract, demand a refund,
and payment of damages.