EOT Note Hafeezpet To Patel Cheruvu
EOT Note Hafeezpet To Patel Cheruvu
2. In this regard it is to submit that as per the estimate box drain of size 2.0 X 1.5m
is proposed for a length of 1100m from Hafeezpet Cheruvu to Culvert on NH65 at Alwyn X
Roads, which passes through Janapriya Nagar Main Road and BR Hemadurga Apartment Court
Yard Portion.
3. Accordingly, work started at two reaches in Janapriya nagar and by July 2018
235m length completed and further work was kept on hold due to monsoon season. Meanwhile
nala widening inside BR Hemadurga apartments was objected by Apartment Residents on 25-12-
2017, and they have approached Hon’ble High Court on 26-12-2017 vide WP No 44337/2017.
Further, while taking up work on downstream side of BR Hemadurga apartments in road portion
of 100m length on 05-04-2018, once again the Apartment Association stopped the work stating
that it is a private road to Hemadurga Apartments. Due to pending court case and stiff resistance
from Residents of BR Hemadurga, the Clear stretch available is 450m only, out of sanctioned
length of 1100m and finally 255m RCC box is completed out of 450m clear length available.
i. Service lines such as water, electricity, communication cables, were passing in the
alignment of proposed nala, due to which extra care is taken while excavation and
restoration of accidentally damaged service lines consumed lot of time.
ii. BR Hemadurga stretch not handed over to take up work.
iii. BT Dismantling work taken up from BR Hemadurga Entrance gate upto NH65 and due to
stiff resistance from residents claiming it as private road, the work was kept on hold.
5. Further as this total work is being taken up on road portion the work was carried
out in 30m stretches consumed lot of time as RCC box construction sequence takes more time. In
view of slow progress of work and inconvenience the local people raised the issue several times.
Finally during discussion it was informed to the local residents that the contractor requested to
close the contract and accordingly the local people requested to terminate work to the extent of
work taken up and requested to resume the work after monsoon.
A decision was taken by The Commissioner GHMC vide during review meeting dated
01-Oct-2019, in which he instructed to complete the balance works with existing
contractor, therefore, in order to mobilize men and machinery and complete the balance
length of 195m EOT is requested upto 31-03-2020.
9. In the matter related to granting EOTs , the Commissioner, GHMC has directed to
put the proposals before the Technical Committee comprising of three Chief Engineers and in
pursuant of note orders of Commissioner, GHMC, the Chief Engineer (P) has issued proceedings
to this effect vide proc no: GHMC/CE(P)/2018-19 dt:22.10.2018 according to which the
Extension Of Agreement Time (EOAT) proposals for all non-EPC project works and EPC
project works (up to first six months period) shall be examined and finalized by the Technical
Committee of three Chief Engineers.